Attached files

file filename
8-K - CURRENT REPORT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315_chinaenergy.htm
EX-16.1 - LETTER FROM JOHN SCRUDATO CPA - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex16i_chinaenergy.htm
EX-10.1 - SPLIT-OFF AGREEMENT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10i_chinaenergy.htm
EX-10.5 - FORM OF EXCLUSIVE OPTION AGREEMENT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10v_chinaenergy.htm
EX-10.10 - LOAN AGREEMENT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10x_chinaenergy.htm
EX-21.1 - SUBSIDIARIES OF REGISTRANT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex21i_chinaenergy.htm
EX-2.2 - SHARE EXCHANGE AGREEMENT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex2ii_chinaenergy.htm
EX-10.11 - INVESTMENT CONTRACT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10xi_chinaenergy.htm
EX-10.2 - GENERAL RELEASE AGREEMENT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10ii_chinaenergy.htm
EX-10.6 - FORM OF POWER OF ATTORNEY - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10vi_chinaenergy.htm
EX-10.9 - LEASE AGREEMENT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10ix_chinaenergy.htm
EX-10.4 - EQUITY INTEREST PLEDGE AGREEMENT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10iv_chinaenergy.htm
EX-10.7 - FORM OF SPOUSAL CONSENT LETTER - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10vii_chinaenergy.htm
EX-10.16 - AMENDMENT TO LOAN AGREEMENT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10xvi_chinaenergy.htm
EX-10.3 - EXCLUSIVE BUSINESS COOPERATION AGREEMENT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10iii_chinaenergy.htm
EX-10.12 - PROJECT CONSTRUCTION AGREEMENT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10xii_chinaenergy.htm
EX-10.14 - SHAREHOLDERS REPAYMENT PLAN - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10xiv_chinaenergy.htm
EX-10.8 - RENTAL AGREEMENT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10viii_chinaenergy.htm
EX-10.13 - EMPLOYMENT AGREEMENT - CHINA ENERGY TECHNOLOGY CORP., LTD.f8k0315ex10xiii_chinaenergy.htm

Exhibit 10.15

 

Loan agreement

 

Party A: Anhui Renrenjia Solar Energy Co., Ltd.

 

Party B: Anhui Haishuai Electronic Manufacture Co., Ltd

 

Both parties agreed upon the following terms.

 

1. Purpose of the loan

 

The money borrowed from Party A will be used to maintain company’s normal daily operation.

  

2. Loan amount and repay schedule

 

Party B borrows 13.5 million RMB from Party A, must be paid back before Jan 1st, 2013.

 

3. Term of the loan

 

The term of the loan is from Jan 1st, 2012 to Dec 31, 2012.

 

4. Party B shall pay back the loan and interests according this agreement. After Party B pay back the loan in full, party A shall return this agreement to party B.

 

5. Interests

 

The interest rate for this loan is 1.5% per month, if party B does not pay back the loan on time, the unpaid amount will be charged addition 0.5% interest per month.

 

6. Rights and obligations

 

Party A has the right to supervise the use of this loan, and value the pay back ability of Party B, party B shall provide all necessary documents if needed. If Party B uses the loan not according to this agreement, party A has the right to collect the remaining loan interest penalty.

 

7. Promise terms

 

  1) Party B voluntarily use real estate as mortgage for this loan, if party B can’t pay back the loan on time, party A has the right to dispose the mortgage.

 

  2) Party B has to use the loan according to this agreement.

 

  3) Party B shall pay back the loan and interest according to this agreement.

 

8. Enforcement terms and payback time

 

  1) Both parties confirm that after signing this agreement, this agreement will be entitled for enforcement power.

 

  2) The deadline for this loan is Jan 1st, 2013. Party B accepts the enforcement execution by the people court if the loan is past due.

 

9. Settlement solutions

 

Both parties shall seek negotiator to solve the conflicts occurred during the term of this agreement. If the conflicts cannot be settled by the negotiator, either party can institute a law suit to the people’s court.

 

10. The agreement will be in effect upon signature and stamp by both parties, each party holds one copy of this agreement.

 

11. Other unsettled issues not mentioned in this agreement shall be executed according to the contract law of the People’s Republic of China.

 

 
 

 

Party A: Anhui Renrenjia Solar Energy Co., Ltd

 

Date: Jan 1st, 2012

 

Party B: Anhui Haishuai Electronic Manufacture Co., Ltd.

  