Attached files

file filename
8-K - 8-K - Coeur Mining, Inc.cde-20210428.htm

NEWS RELEASE             image0a821a.jpg
Coeur Reports First Quarter 2021 Results
Reaffirms Full-Year 2021 Guidance

Chicago, Illinois - April 28, 2021 - Coeur Mining, Inc. (“Coeur” or the “Company”) (NYSE: CDE) today reported first quarter 2021 financial results, including revenue of $202.1 million, cash flow from operating activities of $(4.4) million and GAAP net income from continuing operations of $2.1 million, or $0.01 per share. On an adjusted basis1, the Company reported EBITDA of $65.9 million, cash flow from operating activities before changes in working capital of $41.6 million and net income from continuing operations of $13.9 million, or $0.06 per share.
The Company also reaffirmed its full-year 2021 production guidance of 322,500 - 367,500 ounces of gold and 9.7 - 12.2 million ounces of silver. Additionally, full-year cost, exploration and capital expenditure guidance was reaffirmed.
Key Highlights
Higher margins helped drive a stronger start to the year – Coeur’s first quarter results reflect a strong start to the year led by solid production and higher prices. Notably, quarterly revenue, operating cash flow before changes in working capital1 and adjusted EBITDA1 increased 17%, 38% and 42% year-over-year, respectively
Solid gold production and unit costs – The Company’s gold production of 85,225 ounces exceeded expectations for the quarter, tracking well towards its full-year guidance range. Additionally, all of the Company’s site-level gold unit costs were either below or within their full-year guidance ranges
Further enhanced liquidity and balance sheet – Coeur successfully refinanced its 5.875% senior notes due 2024 with 5.125% senior notes due 2029, capturing a lower interest rate, extending the maturity and opportunistically upsizing the offering. The Company also extended the maturity of its senior secured revolving credit facility (“RCF”) from October 2022 to March 2025. Together, these efforts improved Coeur’s liquidity profile and bolstered its balance sheet, helping to enhance financial flexibility ahead of a period of planned capital intensity
Commenced major construction on Rochester expansion – The Company began major construction on the Plan of Operations Amendment 11 (“POA 11”) expansion at its Rochester mine. Overall project progress was approximately 20% complete at the end of the first quarter. Key elements of the project timeline remain on schedule and are expected to be largely completed by late next year
Encouraging results from aggressive investment in exploration – Following its successful program in 2020, Coeur began the year with the largest exploration campaign in Company history. The Company invested approximately $14.9 million ($9.7 million expensed and $5.2 million capitalized) in exploration during the quarter, drilling roughly 250,500 feet (76,375 meters) across all sites. Drilling activities at Silvertip and Crown ramped up significantly during the quarter, while Coeur’s other sites continued to advance their resource expansion and infill programs

1


“Our first quarter results were in-line with our expectations driven by strong gold production performance across our portfolio of assets, which led to double digit year-over-year increases in quarterly revenue, adjusted EBITDA1 and operating cash flow before changes in working capital1,” said Mitchell J. Krebs, President and Chief Executive Officer. “Additionally, we achieved an important milestone by commencing major construction on the expansion of our Rochester mine in Nevada. The project remains on track and is expected to be largely completed by late next year, helping to drive an anticipated step change in production and cash flow.”
Mr. Krebs continued, “We took advantage of the low interest rate environment in March to opportunistically refinance our senior notes and extend the maturity of our RCF, which fortified our financial flexibility as we head into a phase of significant planned capital investment this year and next. On the exploration front, we are seeing early encouraging results as we execute on the largest drilling campaign in Company history. By following our strategy, adhering to our capital allocation framework, and executing our near-, medium- and long-term objectives, we are confident in our ability to maximize cash flow, returns and net asset value for our stockholders.”
2


Financial and Operating Highlights (Unaudited)
(Amounts in millions, except per share amounts, gold/silver ounces produced & sold, and per-ounce metrics)1Q 20214Q 20203Q 20202Q 20201Q 2020
Gold Sales$138.3 $162.0 $167.1 $127.9 $127.6 
Silver Sales$63.8 $66.4 $62.6 $26.3 $44.9 
Consolidated Revenue$202.1 $228.3 $229.7 $154.2 $173.2 
Costs Applicable to Sales2
$108.1 $118.6 $112.8 $90.0 $118.9 
General and Administrative Expenses$11.6 $8.4 $7.8 $8.6 $8.9 
Net Income (Loss)$2.1 $11.9 $26.9 $(1.2)$(11.9)
Net Income (Loss) Per Share$0.01 $0.05 $0.11 $(0.01)$(0.05)
Adjusted Net Income (Loss)1
$13.9 $19.1 $38.2 $2.6 $(0.9)
Adjusted Net Income (Loss)1 Per Share
$0.06 $0.08 $0.16 $0.01 $— 
Weighted Average Shares Outstanding244.5 244.3 243.8 240.9 240.3 
EBITDA1
$49.7 $76.7 $77.3 $35.3 $25.5 
Adjusted EBITDA1
$65.9 $84.0 $90.8 $42.2 $46.5 
Cash Flow from Operating Activities$(4.4)$67.3 $79.5 $9.9 $(8.0)
Capital Expenditures$59.4 $37.4 $23.0 $16.7 $22.2 
Free Cash Flow1
$(63.8)$29.8 $56.5 $(6.7)$(30.2)
Cash, Equivalents & Short-Term Investments$154.1 $92.8 $77.1 $70.9 $52.9 
Total Debt3
$412.1 $275.5 $301.1 $348.6 $343.1 
Average Realized Price Per Ounce – Gold$1,664 $1,663 $1,754 $1,641 $1,490 
Average Realized Price Per Ounce – Silver$26.19 $24.21 $24.15 $16.25 $16.63 
Gold Ounces Produced85,225 96,377 95,995 78,229 85,077 
Silver Ounces Produced2.4 2.8 2.6 1.6 2.7 
Gold Ounces Sold83,112 97,400 95,283 77,933 85,635 
Silver Ounces Sold2.4 2.7 2.6 1.6 2.7 

Financial Results
First quarter 2021 revenue totaled $202.1 million compared to $228.3 million in the prior period and $173.2 million in the first quarter of 2020. The Company produced 85,225 and 2.4 million ounces of gold and silver, respectively, during the quarter. Metal sales totaled 83,112 ounces of gold and 2.4 million ounces of silver.
Average realized gold and silver prices for the quarter were $1,664 and $26.19 per ounce, respectively, compared to $1,663 and $24.21 per ounce in the prior period. Gold and silver sales accounted for 68% and 32% of quarterly revenue, respectively. The Company’s U.S. operations accounted for approximately 60% of first quarter revenue, relatively consistent with the prior period.
Costs applicable to sales2 decreased 9% quarter-over-quarter to $108.1 million, largely due to lower production in the period as well as a non-cash adjustment at Rochester in the prior quarter. General and administrative expenses for the quarter totaled $11.6 million compared to $8.4 million in the prior period, reflecting higher employee-related expenses including increased costs related to annual incentive payments.
Coeur invested approximately $14.9 million ($9.7 million expensed and $5.2 million capitalized) in exploration during the quarter, compared to roughly $14.5 million ($11.6 million expensed and $2.9 million capitalized) in the fourth quarter of 2020. Slightly higher exploration investment was driven by a
3


greater allocation to capitalized infill drilling quarter-over-quarter. See the “Operations” and “Exploration” sections for additional detail on the Company’s exploration activities.
Operating costs related to COVID-19 mitigation and response efforts totaled $3.0 million during the first quarter, compared to $5.1 million in the prior period. These costs were primarily driven by employee-related expenses at Kensington and Palmarejo, and are included in “Pre-development, reclamation, and other expenses” on the Company’s income statement. Coeur continues to implement and maintain rigorous health and safety protocols across its operations and in surrounding communities aimed at limiting the exposure and transmission of COVID-19 while minimizing business interruptions.
Coeur recorded an income tax expense of $12.8 million during the first quarter. Cash income and mining taxes paid during the period totaled approximately $26.7 million, including the annual payment of the Mexican mining royalty tax of $9.6 million.
Quarterly operating cash flow totaled $(4.4) million compared to $67.3 million in the prior period, largely driven by lower metal sales, higher cash taxes and unfavorable changes in working capital. Changes in working capital during the quarter were $(45.9) million, compared to $8.8 million in the prior period, reflecting the timing of Mexican tax payments as well as the build-up of inventories primarily related to leach pads. First quarter operating cash flow also includes a cash outflow of $7.9 million associated with the Company’s prepayment agreement at Kensington. Coeur expects the remaining $7.1 million cash outflow under the arrangement to occur in the second quarter.
Capital expenditures during the first quarter were $59.4 million compared to $37.4 million in the prior period, reflecting increased investment across the Company’s portfolio. Investment related to the POA 11 expansion at Rochester totaled $28.1 million during the quarter, compared to $14.8 million in the fourth quarter of 2020. Sustaining and development capital expenditures accounted for approximately 43% and 57%, respectively, of the Company’s total capital investment during the quarter.

Balance Sheet Update
Coeur continued to prudently manage its balance sheet during the first quarter of 2021. The Company successfully refinanced $230.0 million in aggregate principal outstanding of its 5.875% senior notes due 2024 with $375.0 million of 5.125% senior notes due 2029. The Company also extended the maturity of its $300.0 million RCF from October 2022 to March 2025. Together, these initiatives strengthened Coeur’s financial flexibility ahead of the next two years of expected capital intensity. Coeur ended the quarter with total debt3 of $412.1 million and cash and cash equivalents of $154.1 million.

Hedging Update
The Company did not execute any additional zero-cost collar (“ZCC”) hedges during the first quarter. Coeur’s hedging strategy remains focused on supporting cash flow generation during the POA 11 expansion project at Rochester, which the Company expects to fund with a combination of cash on hand, internally generated cash flow and debt capacity.
Coeur previously completed its gold hedging program for 2021 and will proactively monitor market conditions to potentially layer in additional ZCC hedges on up to 50% of expected gold production in 2022. The Company’s silver price exposure remains unhedged. An overview of the hedges currently implemented is outlined below:
4


20212022
Gold Ounces Hedged119,025126,000
Avg. Ceiling ($/oz)$1,877$2,030
Avg. Floor ($/oz)$1,600$1,626

Rochester Expansion
Coeur began major construction activities on the POA 11 expansion project at Rochester in January 2021, including excavation of areas for the Merrill-Crowe process plant and crusher corridor. Project-specific offices and supporting infrastructure have been completed and are operational. At the end of the first quarter, Coeur and SNC-Lavalin (engineering, procurement and project management contractor) substantially completed detailed design work for the expansion project, and almost all of the equipment procurement and service arrangements have been committed. The Company had over $300.0 million of capital committed to the expansion project, including 72 executed contracts valued at approximately $290.0 million as of March 31, 2021. Overall project progress was approximately 20% complete at the end of the quarter.
Over the coming quarters, Coeur expects to remain focused on safely delivering the project with placement of over-liner material for the Stage VI leach pad, mobilization of a cement batch plant, construction of a new high-voltage power line and initiation of electrical substation upgrades planned mid-year. Additionally, structural steel erection for the crusher corridor is expected to begin in early 2022.
Key elements of the project timeline remain on schedule and are highlighted below:
Expected Start DateTarget Completion Date
Leach Pad (Incl. Ancillary Facilities)
2H 2020 P
Mid-2022
Merrill-Crowe Process Plant
1H 2021 P
YE 2022
Crushing Circuit
1H 2021 P
YE 2022
Supporting Infrastructure
2H 2020 P
Mid-2022

5


Operations
First quarter 2021 highlights for each of the Company’s operations are provided below.
Palmarejo, Mexico
(Dollars in millions, except per ounce amounts)1Q 20214Q 20203Q 20202Q 20201Q 2020
Tons milled484,390509,848492,474269,641479,562
Average gold grade (oz/t)0.060.080.070.070.07
Average silver grade (oz/t)4.074.304.374.464.69
Average recovery rate – Au95.7%88.9%91.3%86.0%91.6%
Average recovery rate – Ag81.3%81.3%82.8%72.2%81.5%
Gold ounces produced28,60534,51129,29615,22331,578
Silver ounces produced (000’s)1,6031,7831,7848671,835
Gold ounces sold25,68735,35927,25216,92431,287
Silver ounces sold (000’s)1,6381,7671,7658751,895
Average realized price per gold ounce$1,462$1,395$1,446$1,399$1,331
Average realized price per silver ounce$26.12$24.45$23.98$16.35$17.25
Metal sales$80.3$92.5$81.8$38.0$74.3
Costs applicable to sales2
$34.0$36.1$34.3$18.8$36.0
Adjusted CAS per AuOz1
$621$542$602$686$645
Adjusted CAS per AgOz1
$10.98$9.61$10.06$8.13$8.37
Exploration expense$1.7$2.6$2.0$0.9$1.5
Cash flow from operating activities$13.2$43.2$49.7$(3.5)$28.9
Sustaining capital expenditures (excludes capital lease payments)$10.0$9.0$4.9$4.5$7.1
Development capital expenditures$—$(0.1)$0.1$—$—
Total capital expenditures$10.0$8.9$5.0$4.5$7.1
Free cash flow1
$3.2$34.3$44.7$(8.0)$21.8
Operational
First quarter gold and silver production totaled 28,605 and 1.6 million ounces, respectively, compared to 34,511 and 1.8 million ounces in the prior period and 31,578 and 1.8 million ounces in the first quarter of 2020
Gold and silver production was impacted by a 5% decrease in mill throughput quarter-over-quarter, driven by a change in mine sequencing due to geotechnically-challenging conditions as well as lower average grades. First quarter recovery rates benefited from a drawdown of in-circuit inventory
Financial
First quarter adjusted CAS1 for gold and silver on a co-product basis increased 15% and 14% to $621 and $10.98 per ounce, respectively, compared to the prior quarter, largely driven by a decrease in average grades
Capital expenditures increased 12% quarter-over-quarter to $10.0 million, reflecting higher planned mine development and equipment purchases
Free cash flow1 in the first quarter totaled $3.2 million compared to $34.3 million in the prior period, driven by the payment of cash income and mining taxes totaling $25.1 million as well as lower metal sales quarter-over-quarter
Exploration
6


Exploration investment for the first quarter totaled approximately $3.0 million ($1.7 million expensed and $1.3 million capitalized), compared to roughly $3.7 million ($2.6 million expensed and $1.1 million capitalized) in the prior period
Up to seven surface and underground core rigs were active during the quarter following the success of both expansion and infill drilling during late 2020. A total of approximately 54,200 feet (16,525 meters) were drilled during the period, including 16,800 feet (5,125 meters) of expansion and 37,400 feet (11,400 meters) of infill
Infill drilling during the quarter focused on specific zones within the Independencia and Guadalupe deposits. Surface rigs targeted areas of the Hidalgo and La Patria zones as well as the northern portion of the Independencia zone, while underground rigs focused on the southern portion of the Independencia zone
Expansion drilling focused on the Hidalgo, North Independencia and Bavisa North/Ojito zones, located to the north of the Independencia deposit
Expansion and greenfield target generation is expected to continue moving north and east from the Independencia and Guadalupe deposits
In parallel, a new initiative to evaluate, target and drill the Guazapares district (located east of the Palmarejo district) was launched with the expectation of drilling to begin in the second half of the year
Coeur plans to maintain seven active drill rigs at Palmarejo, ramping up as needed later in the year
Other
Approximately 34% (8,738 ounces) of Palmarejo’s gold sales in the first quarter were sold under its gold stream agreement at a price of $800 per ounce
Guidance
Full-year 2021 production is expected to be 100,000 - 110,000 ounces of gold and 6.5 - 7.8 million ounces of silver
CAS1 are expected to be $710 - $810 per gold ounce and $11.00 - $12.00 per silver ounce
Capital expenditures are expected to be approximately $40 - $45 million
7



Rochester, Nevada
(Dollars in millions, except per ounce amounts)1Q 20214Q 20203Q 20202Q 20201Q 2020
Ore tons placed3,240,9174,000,8894,523,7673,743,3313,428,578
Average silver grade (oz/t)0.450.530.490.510.57
Average gold grade (oz/t)0.0030.0020.0020.0020.002
Silver ounces produced (000’s)7741,020740728687
Gold ounces produced6,9049,5906,4625,1595,936
Silver ounces sold (000’s)771912786724632
Gold ounces sold6,9348,6726,8345,2785,473
Average realized price per silver ounce$26.34$24.35$24.49$16.11$16.99
Average realized price per gold ounce$1,794$1,825$1,882$1,702$1,583
Metal sales$32.8$38.2$32.1$20.6$19.4
Costs applicable to sales2
$24.0$31.7$19.1$18.3$17.0
Adjusted CAS per AgOz1
$19.07$20.18$14.98$13.75$14.38
Adjusted CAS per AuOz1
$1,300$1,537$1,148$1,481$1,359
Exploration expense$0.5$0.8$0.5$1.8$0.2
Cash flow from operating activities$(8.7)$4.7$2.1$(5.6)$(9.3)
Sustaining capital expenditures (excludes capital lease payments)$2.0$2.9$2.5$1.5$0.1
Development capital expenditures$28.2$13.9$7.3$4.3$5.0
Total capital expenditures$30.2$16.8$9.8$5.8$5.1
Free cash flow1
$(38.9)$(12.1)$(7.7)$(11.4)$(14.4)
Operational
Silver and gold production during the quarter totaled 0.8 million and 6,904 ounces, respectively, compared to 1.0 million and 9,590 ounces in the fourth quarter of 2020. Year-over-year silver and gold production increased 13% and 16%, respectively
Coeur crushed approximately 30,200 tons per day during the first quarter compared to roughly 34,000 tons per day in the fourth quarter of 2020. Additionally, the Company supplemented placement rates in the quarter by stacking approximately 524,400 tons of run-of-mine material compared to just over 877,000 tons in the prior period
The Company encountered a new, softer ore type that required changes to crush size and throughput rates to help manage the amount of fine particles, with the ultimate goal of improving leachability and recoveries on the Stage IV leach pad
Lower production during the quarter was primarily driven by (i) reduced leaching rates on material placed in the prior period as a result of additional fine particles, (ii) the placement of material on deeper portions of the Stage IV leach pad, (iii) lower average silver grade consistent with the mine plan, and (iv) lower placement rates. Approximately 65,000 ounces of silver were held as work-in-process inventory at the end of the period and are expected to be recovered in the second quarter
The Company is executing the swap out of the secondary crushing unit during the month of April and plans to complete the fourth phase of its inter-lift liner strategy around mid-year. Both projects are aimed at de-risking the execution of POA 11 and further improving recovery rates on the Stage IV leach pad
Financial
First quarter adjusted CAS1 for silver and gold on a co-product basis decreased 6% and 15% quarter-over-quarter, respectively, to $19.07 and $1,300 per ounce, primarily driven by a non-cash adjustment
8


of approximately $7.2 million in the prior period related to a change in the Company’s recovery rate assumption on the Stage IV leach pad as well as lower production levels and fewer ounces sold during the quarter
Capital expenditures increased 80% quarter-over-quarter to $30.2 million, largely due to the commencement of major construction on the POA 11 expansion project
Free cash flow1 in the first quarter totaled $(38.9) million, compared to $(12.1) million in the prior period, largely driven by higher capital expenditures and lower metal sales
Exploration
Quarterly exploration investment totaled approximately $0.7 million ($0.5 million expensed and $0.2 million capitalized), compared to roughly $1.2 million ($0.8 million expensed and $0.4 million capitalized) in the prior period
One reverse circulation rig continued drilling the northern portion of East Rochester as well as North Rochester and East Packard during the quarter. A total of approximately 8,900 feet (2,700 meters) were drilled during the period, primarily focused on resource expansion
The Company believes there is significant potential for resource growth both north and south of East Rochester and at North Rochester. Coeur continues to receive assay results that were not included in the updated technical report filed in December 2020, and expects to incorporate these results in its year-end 2021 reserves and resources
For the remainder of the year, Coeur plans to ramp up exploration activities at Rochester with at least three rigs focusing on infill drilling in the Rochester and Packard pits as well as expansion drilling at North Rochester, the southern portion of East Rochester and East Packard. Separately, Coeur also plans to mobilize two rigs towards the end of the second quarter to conduct infill drilling at the Lincoln Hill zone and expansion drilling at the Gold Ridge zone, both located immediately west of Rochester
Guidance
Full-year 2021 production is expected to be 3.2 - 4.4 million ounces of silver and 22,500 - 32,500 ounces of gold
CAS1 in 2021 are expected to be $15.00 - $17.00 per silver ounce and $1,180 - $1,330 per gold ounce
Capital expenditures are expected to be approximately $155 - $195 million

9


Kensington, Alaska
(Dollars in millions, except per ounce amounts)1Q 20214Q 20203Q 20202Q 20201Q 2020
Tons milled170,358179,636163,276170,478162,341
Average gold grade (oz/t)0.190.200.180.210.21
Average recovery rate93.2%93.0%93.7%92.0%93.5%
Gold ounces produced30,68132,99026,79733,05832,022
Gold ounces sold31,59531,83027,81532,36732,781
Average realized price per gold ounce, gross$1,754$1,837$1,917$1,762$1,603
Treatment and refining charges per gold ounce$30$37$35$57$27
Average realized price per gold ounce, net$1,724$1,800$1,882$1,705$1,576
Metal sales$54.5$57.2$52.4$55.2$51.7
Costs applicable to sales2
$31.4$29.3$31.5$30.4$30.5
Adjusted CAS per AuOz1
$989$919$1,128$934$928
Prepayment, working capital cash flow$(7.9)$5.1$(5.1)$7.0$(7.0)
Exploration expense$1.1$0.8$3.4$2.6$1.8
Cash flow from operating activities$11.0$31.0$9.1$27.8$11.9
Sustaining capital expenditures (excludes capital lease payments)$7.2$5.8$5.3$3.9$4.8
Development capital expenditures$—$—$—$—$—
Total capital expenditures$7.2$5.8$5.3$3.9$4.8
Free cash flow1
$3.8$25.2$3.8$23.9$7.1
Operational
Gold production in the first quarter totaled 30,681 ounces, compared to 32,990 ounces in the prior period and 32,022 ounces in the first quarter of 2020
Relatively lower production during the quarter was driven by a decrease in mill throughput from additional planned mill maintenance as well as slightly lower average grade as the Company developed ore headings and increased stope drilling capacity
Jualin accounted for approximately 17% of Kensington’s first quarter production, slightly lower than the prior period of roughly 19%, due to a focus on ore development
Financial
Adjusted CAS1 increased 8% quarter-over-quarter to $989 per ounce, largely driven by lower average grade as well as higher fuel costs and additional planned mill maintenance
Capital expenditures increased 24% quarter-over-quarter to $7.2 million, primarily due to the timing of payments related to projects in the prior period
Free cash flow1 in the first quarter totaled $3.8 million, including cash outflow of $7.9 million associated with the Company’s prepayment agreement at Kensington. Excluding the effect of the prepayment, free cash flow1 totaled approximately $11.7 million in the first quarter
Exploration
Exploration investment in the first quarter totaled approximately $2.1 million ($1.1 million expensed and $1.0 million capitalized), compared to $2.2 million ($0.8 million expensed and $1.4 million capitalized) in the prior quarter
Two underground core rigs were active during the quarter, drilling from the Elmira development drift established in 2020. A total of approximately 34,700 feet (10,575 meters) were drilled during the
10


period, including 15,900 feet (4,850 meters) of expansion drilling and 18,800 feet (5,725 meters) of infill drilling
Infill drilling during the quarter was primarily focused on the Elmira vein, while also occasionally testing the Johnson vein which the Company considers a resource expansion target
The two underground rigs are expected to remain active for most of the year, continuing to target the Elmira and Johnson veins. The Company plans to add an additional rig during the second half of 2021 to drill resource expansion targets from surface
Guidance
Production in 2021 is expected to be 115,000 - 130,000 ounces of gold
CAS1 in 2021 are expected to be $1,010 - $1,110 per gold ounce
Capital expenditures are expected to be approximately $23 - $30 million

Wharf, South Dakota
(Dollars in millions, except per ounce amounts)1Q 20214Q 20203Q 20202Q 20201Q 2020
Ore tons placed1,114,0431,047,6471,315,5421,401,237946,449
Average gold grade (oz/t)0.0300.0240.0250.0320.025
Gold ounces produced19,03519,28633,44024,78915,541
Silver ounces produced (000’s)2633422515
Gold ounces sold18,89621,53933,38223,36416,094
Silver ounces sold (000’s)2635412315
Average realized price per gold ounce$1,791$1,835$1,872$1,715$1,592
Metal sales$34.5$40.3$63.5$40.5$25.9
Costs applicable to sales2
$18.7$21.4$27.9$22.5$17.8
Adjusted CAS per AuOz1
$952$954$804$804$1,090
Exploration expense$0.1$0.3$0.5$0.1$—
Cash flow from operating activities$7.8$14.1$39.1$19.1$2.6
Sustaining capital expenditures (excludes capital lease payments)$0.4$1.2$0.5$0.3$0.4
Development capital expenditures$1.1$—$—$—$—
Total capital expenditures$1.5$1.2$0.5$0.3$0.4
Free cash flow1
$6.3$12.9$38.6$18.8$2.2
Operational
Gold production remained relatively consistent quarter-over-quarter at 19,035 ounces, largely due to the timing of ounces placed on the leach pads. Year-over-year gold production increased 22%
Notably, tons placed and average gold grade increased 6% and 25% quarter-over-quarter, respectively. Higher placement rates reflect favorable weather conditions, better crusher maintenance planning and enhanced operational strategies
Financial
Adjusted CAS1 on a by-product basis remained relatively consistent quarter-over-quarter at $952 per ounce
First quarter capital expenditures totaled $1.5 million compared to $1.2 million in the prior period, reflecting a ramp up in infill drilling
11


Free cash flow1 was $6.3 million in the first quarter compared to $12.9 million in the fourth quarter of 2020, largely driven by lower metal sales
Exploration
Exploration investment in the first quarter totaled approximately $1.2 million ($0.1 million expensed and $1.1 million capitalized), compared to roughly $0.3 million (substantially all expensed) in the prior period
A total of approximately 38,600 feet (11,775 meters) were drilled during the period using one reverse circulation rig, focusing on infill targets at the Portland Ridge – Boston claim group (located on the southern edge of the operation)
Coeur is in the process of evaluating 2020 drill assays, surface mapping and geochemistry results, and planning its next steps regarding Richmond Hill. The Company has an exclusive option agreement with two subsidiaries of Barrick Gold Corporation to acquire the project that expires in September 2021
Once infill drilling at Portland Ridge is completed, expected around mid-year, Coeur plans to shift its focus to the Flossie area, west of Portland Ridge, and the Juno area, located on the north side of Wharf
Guidance
Gold production in 2021 is expected to be 85,000 - 95,000 ounces
CAS1 in 2021 are expected to be $960 - $1,060 per gold ounce
Capital expenditures are expected to be approximately $5 - $8 million

Silvertip, British Columbia
(Dollars in millions)1Q 20214Q 20203Q 20202Q 20201Q 2020
Metal sales$—$—$—$—$1.9
Costs applicable to sales2
$—$—$—$—$17.7
Exploration expense$2.9$5.1$3.9$2.9$0.3
Cash flow from operating activities$(7.5)$(8.2)$(8.2)$(14.9)$(27.1)
Sustaining capital expenditures (excludes capital lease payments)$5.7$(0.5)$(1.8)$1.9$4.6
Development capital expenditures$4.7$5.0$3.9$—$—
Total capital expenditures$10.4$4.5$2.1$1.9$4.6
Free cash flow1
$(17.9)$(12.7)$(10.3)$(16.8)$(31.7)
Mining and processing activities were temporarily suspended at Silvertip on February 19, 2020 (unrelated to COVID-19)
Operational
Coeur continued advancing Silvertip’s revised 1,750 tonnes per day flowsheet through a more comprehensive engineering and design phase, with detailed design approaching 30% completion and exploration results demonstrating the potential for mine life extensions with continued drilling
Technical work remains focused on (i) advancing engineering to de-risk capital estimates, (ii) increasing confidence in the expected concentrate qualities from all of the existing zones of the ore body with confirmatory metallurgical testing, and (iii) enhancing schedule certainty with respect to a potential restart
12


The Company plans to release an updated mine plan and economic analysis for Silvertip at the end of the year, including additional exploration results as well as information regarding the anticipated benefits of the revised 1,750 tonnes per day flowsheet which will be reflected in a technical report that is expected to be filed in early 2022
Financial
Coeur did not realize any temporary suspension costs related to the ramp-down of active mining and processing activities during the quarter as the Company began allocating these expenses to Silvertip’s ongoing carrying costs
Ongoing carrying costs in the first quarter were $6.9 million, compared to $4.7 million in the fourth quarter of 2020. Temporary suspension costs totaled $1.1 million in the prior period
Capital expenditures during the first quarter totaled $10.4 million compared to $4.5 million in the prior period, reflecting work related to the potential restart and expansion of the project as well as the ramp up of infill drilling. Free cash flow1 for the quarter totaled $(17.9) million
Exploration
Exploration investment in the first quarter totaled approximately $4.5 million ($2.9 million expensed and $1.6 million capitalized), compared to roughly $5.1 million (substantially all expensed) in the prior period
The Company had up to six active core rigs during the quarter, ramping up from three rigs at the end of 2020. A total of approximately 80,600 feet (24,575 meters) were drilled during the period, including 47,200 feet (14,375 meters) of expansion drilling and 33,400 feet (10,200 meters) of infill drilling
Infill and expansion drilling (both from surface and underground) focused on the 65 Zone, Discovery East, Discovery North and Camp Creek zones
During the coming months, surface drilling is expected to continue with three active rigs targeting the Camp Creek, Discovery North and Discovery East zones
Underground drilling is planned to ramp up to two rigs, focusing on expansion and infill drilling in the 65 Zone as well as the Central, Discovery South and Camp Creek zones
The latest underground drill results suggest the 65 Zone has high-grade mineralization that connects the Silver Creek zone with the Discovery South zone, representing potential for significant resource growth at Silvertip
Guidance
2021 capital expenditures are expected to total $35 - $45 million
13


Exploration
During the first quarter, the Company drilled roughly 250,500 feet (76,375 meters) at a total investment of approximately $14.9 million ($9.7 million expensed and $5.2 million capitalized), compared to roughly 181,800 feet (55,400 meters) at a total investment of approximately $14.5 million ($11.6 million expensed and $2.9 million capitalized) in the prior period. The increase in exploration activity was largely driven by a ramp up of drilling at Silvertip and Crown as well as the continuation of expansion and infill programs across the rest of the Company’s portfolio.
In addition to Coeur’s mine sites, up to five drill rigs were active at the Crown exploration property in southern Nevada during the first quarter. Up to four reverse circulation rigs drilled expansion holes at Daisy, SNA and C-Horst, while one diamond core rig was active at Secret Pass and C-Horst to better characterize metallurgy and geologic domains. The Company drilled approximately 33,500 feet (10,225 meters) in the quarter, compared to approximately 13,100 feet (4,000 meters) in the prior period.
For the remainder of 2021, Coeur plans to continue the same pace of resource expansion drilling within its recently received 300-acre disturbance permit at Crown. The Company also expects to receive an amended disturbance permit to begin expanding C-Horst to the south. In parallel, exploration activities are scheduled to begin in the second quarter at Sterling, focusing on infill drilling at the main Sterling deposit and expansion drilling at the Diamond Queen zone.

14


2021 Production Guidance
GoldSilver
(oz)(K oz)
Palmarejo100,000 - 110,0006,500 - 7,750
Rochester22,500 - 32,5003,200 - 4,400
Kensington115,000 - 130,000
Wharf85,000 - 95,000
Total322,500 - 367,5009,700 - 12,150


2021 Costs Applicable to Sales Guidance
GoldSilver
($/oz)($/oz)
Palmarejo (co-product)$710 - $810$11.00 - $12.00
Rochester (co-product)$1,180 - $1,330$15.00 - $17.00
Kensington$1,010 - $1,110
Wharf (by-product)$960 - $1,060


2021 Capital, Exploration and G&A Guidance
($M)
Capital Expenditures, Sustaining$80 - $100
Capital Expenditures, Development$180 - $225
Exploration, Expensed$46 - $51
Exploration, Capitalized$17 - $21
General & Administrative Expenses$37 - $41

Note: The Company’s guidance figures assume $1,850/oz gold and $24.00/oz silver as well as CAD of 1.27 and MXN of 19.50. Guidance figures exclude the impact of any metal sales or foreign exchange hedges.
15


Financial Results and Conference Call
Coeur will host a conference call to discuss its first quarter 2021 financial results on April 29, 2021 at 11:00 a.m. Eastern Time.

Dial-In Numbers:        (855) 560-2581 (U.S.)
        (855) 669-9657 (Canada)
        (412) 542-4166 (International)
Conference ID:        Coeur Mining

Hosting the call will be Mitchell J. Krebs, President and Chief Executive Officer of Coeur, who will be joined by Thomas S. Whelan, Senior Vice President and Chief Financial Officer, Michael “Mick” Routledge, Senior Vice President and Chief Operating Officer, and other members of management. A replay of the call will be available through May 6, 2021.

Replay numbers:        (877) 344-7529 (U.S.)
        (855) 669-9658 (Canada)
        (412) 317-0088 (International)
Conference ID:        101 53 291

About Coeur
Coeur Mining, Inc. is a U.S.-based, well-diversified, growing precious metals producer with five wholly-owned operations: the Palmarejo gold-silver complex in Mexico, the Rochester silver-gold mine in Nevada, the Kensington gold mine in Alaska, the Wharf gold mine in South Dakota, and the Silvertip silver-zinc-lead mine in British Columbia. In addition, the Company has interests in several precious metals exploration projects throughout North America.

Cautionary Statements
This news release contains forward-looking statements within the meaning of securities legislation in the United States and Canada, including statements regarding strategy, value, cash flow, capital allocation and investment, returns, net asset values, exploration and development efforts and plans, expectations regarding the potential expansion and restart at Silvertip (including technical report timing), expectations regarding the Rochester POA 11 expansion project, hedging strategies, anticipated production, costs and expenses, COVID-19 mitigation efforts, and operations at Palmarejo, Rochester, Wharf, Kensington and Silvertip. Such forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause Coeur’s actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others, the risk that anticipated production, cost and expense levels are not attained, the risks and hazards inherent in the mining business (including risks inherent in developing large-scale mining projects, environmental hazards, industrial accidents, weather or geologically-related conditions), changes in the market prices of gold, silver, zinc and lead and a sustained lower price or higher treatment and refining charge environment, the uncertainties inherent in Coeur’s production, exploratory and developmental activities, including risks relating to permitting and regulatory delays (including the impact of government shutdowns), ground conditions and, grade variability, any future labor disputes or work stoppages (involving the Company and its subsidiaries or third parties), the uncertainties inherent in the estimation of mineral reserves, changes that could result from Coeur’s future acquisition of new mining properties or businesses, the loss of access or insolvency of any third-party refiner or smelter to which Coeur markets its production, the potential effects of the COVID-19 pandemic, including impacts to the availability of our workforce, continued access to financing sources, government orders that may require temporary suspension of operations at one or more of our sites and effects on our suppliers or the refiners and smelters to whom the Company markets its production and on the communities where we operate, the effects of environmental and other governmental regulations and government shut-downs, the risks inherent in the ownership or operation of or investment in mining properties or businesses in foreign countries, Coeur’s ability to raise additional financing necessary to conduct its business, make payments or refinance its debt, as well as other uncertainties and risk factors set out in filings made from time to time with the United States Securities and Exchange
16


Commission, and the Canadian securities regulators, including, without limitation, Coeur’s most recent reports on Form 10-K and Form 10-Q. Actual results, developments and timetables could vary significantly from the estimates presented. Readers are cautioned not to put undue reliance on forward-looking statements. Coeur disclaims any intent or obligation to update publicly such forward-looking statements, whether as a result of new information, future events or otherwise. Additionally, Coeur undertakes no obligation to comment on analyses, expectations or statements made by third parties in respect of Coeur, its financial or operating results or its securities. This does not constitute an offer of any securities for sale.

Christopher Pascoe, Coeur’s Director, Technical Services and a qualified person under Canadian National Instrument 43-101, approved the scientific and technical information concerning Coeur’s mineral projects in this news release. For a description of the key assumptions, parameters and methods used to estimate mineral reserves and resources, as well as data verification procedures and a general discussion of the extent to which the estimates may be affected by any known environmental, permitting, legal, title, taxation, socio-political, marketing or other relevant factors, Canadian investors should refer to the Technical Reports for each of Coeur’s properties, including the recently-filed Technical Report for Rochester, as filed on SEDAR at www.sedar.com.

Non-U.S. GAAP Measures
We supplement the reporting of our financial information determined under United States generally accepted accounting principles (U.S. GAAP) with certain non-U.S. GAAP financial measures, including EBITDA, adjusted EBITDA, adjusted EBITDA margin, free cash flow, adjusted net income (loss), operating cash flow before changes in working capital and adjusted costs applicable to sales per ounce (gold and silver) or pound (zinc or lead). We believe that these adjusted measures provide meaningful information to assist management, investors and analysts in understanding our financial results and assessing our prospects for future performance. We believe these adjusted financial measures are important indicators of our recurring operations because they exclude items that may not be indicative of, or are unrelated to our core operating results, and provide a better baseline for analyzing trends in our underlying businesses. We believe EBITDA, adjusted EBITDA, adjusted EBITDA margin, free cash flow, adjusted net income (loss) and adjusted costs applicable to sales per ounce (gold and silver) and pound (zinc and lead) are important measures in assessing the Company’s overall financial performance. For additional explanation regarding our use of non-U.S. GAAP financial measures, please refer to our Form 10-K for the year ended December 31, 2020 and our Form 10-Q for the quarter ended March 31, 2021.

Notes
1.    EBITDA, adjusted EBITDA, adjusted EBITDA margin, free cash flow, adjusted net income (loss), operating cash flow before changes in working capital and adjusted costs applicable to sales per ounce (gold and silver) or pound (lead and zinc) are non-GAAP measures. Please see tables in the Appendix for the reconciliation to U.S. GAAP. Free cash flow is defined as cash flow from operating activities less capital expenditures. Please see table in Appendix for the calculation of consolidated free cash flow.
2. Excludes amortization.
3. Includes capital leases. Net of debt issuance costs and premium received.

Average Spot Prices
1Q 20214Q 20203Q 20202Q 20201Q 2020
Average Gold Spot Price Per Ounce$1,794 $1,874 $1,908 $1,711 $1,583 
Average Silver Spot Price Per Ounce$26.26 $24.39 $24.26 $16.38 $16.90 
Average Zinc Spot Price Per Pound$1.25 $1.19 $1.06 $0.89 $0.96 
Average Lead Spot Price Per Pound$0.91 $0.86 $0.85 $0.76 $0.84 

For Additional Information
Coeur Mining, Inc.
104 S. Michigan Avenue, Suite 900
Chicago, IL 60603
Attention: Paul DePartout, Director, Investor Relations
Phone: (312) 489-5800
www.coeur.com
17


COEUR MINING, INC. AND SUBSIDIARIES
CONDENSED CONSOLIDATED BALANCE SHEETS (UNAUDITED)

March 31, 2021December 31, 2020
ASSETSIn thousands, except share data
CURRENT ASSETS
Cash and cash equivalents$154,066 $92,794 
Receivables22,606 23,484 
Inventory53,591 51,210 
Ore on leach pads78,689 74,866 
Prepaid expenses and other27,274 27,254 
336,226 269,608 
NON-CURRENT ASSETS
Property, plant and equipment, net248,237 230,139 
Mining properties, net739,559 716,790 
Ore on leach pads87,723 81,963 
Restricted assets9,266 9,492 
Equity securities8,209 12,943 
Receivables25,605 26,447 
Other60,590 56,595 
TOTAL ASSETS$1,515,415 $1,403,977 
LIABILITIES AND STOCKHOLDERS’ EQUITY
CURRENT LIABILITIES
Accounts payable$96,715 $90,577 
Accrued liabilities and other62,682 119,158 
Debt21,404 22,074 
Reclamation2,299 2,299 
183,100 234,108 
NON-CURRENT LIABILITIES
Debt390,721 253,427 
Reclamation139,112 136,975 
Deferred tax liabilities34,577 34,202 
Other long-term liabilities47,399 51,786 
611,809 476,390 
COMMITMENTS AND CONTINGENCIES
STOCKHOLDERS’ EQUITY
Common stock, par value $0.01 per share; authorized 300,000,000 shares, 243,469,002 issued and outstanding at March 31, 2021 and 243,751,283 at December 31, 20202,435 2,438 
Additional paid-in capital3,610,631 3,610,297 
Accumulated other comprehensive income (loss)13,500 (11,136)
Accumulated deficit(2,906,060)(2,908,120)
720,506 693,479 
TOTAL LIABILITIES AND STOCKHOLDERS’ EQUITY$1,515,415 $1,403,977 












18


COEUR MINING, INC. AND SUBSIDIARIES
CONDENSED CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME (LOSS) (UNAUDITED)
 Three Months Ended March 31,
 20212020
 In thousands, except share data
Revenue$202,117 $173,167 
COSTS AND EXPENSES
Costs applicable to sales(1)
108,147 118,917 
Amortization29,937 36,162 
General and administrative11,554 8,920 
Exploration9,666 6,386 
Pre-development, reclamation, and other13,712 6,555 
Total costs and expenses173,016 176,940 
OTHER INCOME (EXPENSE), NET
Loss on debt extinguishment(9,173)— 
Fair value adjustments, net(3,799)(8,819)
Interest expense, net of capitalized interest(4,910)(5,128)
Other, net3,627 1,881 
Total other income (expense), net(14,255)(12,066)
Income (loss) before income and mining taxes14,846 (15,839)
Income and mining tax (expense) benefit(12,786)3,939 
NET INCOME (LOSS) $2,060 $(11,900)
OTHER COMPREHENSIVE INCOME (LOSS):
Change in fair value of derivative contracts designated as cash flow hedges, net of tax of $0 and $22 for the three months ended March 31, 2021 and 2020, respectively.27,357 206 
Reclassification adjustments for realized (gain) loss on cash flow hedges(2,721)— 
Other comprehensive income (loss) 24,636 206 
COMPREHENSIVE INCOME (LOSS)$26,696 $(11,694)
NET INCOME (LOSS) PER SHARE
Basic income (loss) per share:
Basic$0.01 $(0.05)
Diluted$0.01 $(0.05)
(1) Excludes amortization.







19


COEUR MINING, INC. AND SUBSIDIARIES
CONDENSED CONSOLIDATED STATEMENTS OF CASH FLOWS (UNAUDITED)
 Three Months Ended March 31,
 20212020
 In thousands
CASH FLOWS FROM OPERATING ACTIVITIES:
Net income (loss)$2,060 $(11,900)
Adjustments:
Amortization29,937 36,162 
Accretion2,905 2,847 
Deferred taxes124 (5,487)
Loss on debt extinguishment9,173 — 
Fair value adjustments, net3,799 8,819 
Stock-based compensation4,256 2,013 
Gain on modification of right of use lease— (4,051)
Write-downs— 10,381 
Deferred revenue recognition(8,346)(7,548)
Other(2,328)(1,092)
Changes in operating assets and liabilities:
Receivables999 (813)
Prepaid expenses and other current assets(655)(346)
Inventory and ore on leach pads(17,486)(21,925)
Accounts payable and accrued liabilities(28,797)(15,051)
CASH PROVIDED BY (USED IN) OPERATING ACTIVITIES (4,359)(7,991)
CASH FLOWS FROM INVESTING ACTIVITIES:
Capital expenditures(59,424)(22,208)
Proceeds from the sale of assets4,588 4,506 
Sale of investments935 — 
Other(17)(17)
CASH PROVIDED BY (USED IN) INVESTING ACTIVITIES (53,918)(17,719)
CASH FLOWS FROM FINANCING ACTIVITIES:
Issuance of notes and bank borrowings, net of issuance costs367,493 50,000 
Payments on debt, finance leases, and associated costs(243,967)(5,901)
Silvertip contingent consideration— (18,750)
Other(3,925)(1,973)
CASH PROVIDED BY (USED IN) FINANCING ACTIVITIES 119,601 23,376 
Effect of exchange rate changes on cash and cash equivalents(51)(626)
INCREASE (DECREASE) IN CASH, CASH EQUIVALENTS AND RESTRICTED CASH61,273 (2,960)
Cash, cash equivalents and restricted cash at beginning of period94,170 57,018 
Cash, cash equivalents and restricted cash at end of period$155,443 $54,058 

20


Adjusted EBITDA Reconciliation
(Dollars in thousands except per share amounts)LTM 1Q
2021
1Q20214Q 20203Q 20202Q 20201Q 2020
Net income (loss)$39,587 $2,060 $11,880 $26,856 $(1,209)$(11,900)
Interest expense, net of capitalized interest20,490 4,910 4,719 5,096 5,765 5,128 
Income tax provision (benefit)53,770 12,786 25,027 13,113 2,844 (3,939)
Amortization125,162 29,937 35,133 32,216 27,876 36,162 
EBITDA239,009 49,693 76,759 77,281 35,276 25,451 
Fair value adjustments, net(12,621)3,799 (4,110)(2,243)(10,067)8,819 
Foreign exchange (gain) loss2,942 773 1,581 599 (11)76 
Asset retirement obligation accretion11,812 2,905 3,031 2,968 2,908 2,847 
Inventory adjustments and write-downs1,241 572 105 (230)793 476 
(Gain) loss on sale of assets and securities(1,195)(4,053)391 2,476 (9)(374)
Loss on debt extinguishment9,172 9,172 — — — — 
Silvertip inventory write-down3,336 — — 1,232 2,104 10,381 
Silvertip temporary suspension costs3,655 — 1,092 838 1,725 3,509 
Silvertip lease modification— — — — — (4,051)
Silvertip gain on contingent consideration— — — — — (955)
COVID-19 costs18,288 3,005 5,138 4,037 6,108 272 
Novation3,819 — — 3,819 — — 
Wharf inventory write-down3,323 — — — 3,323 — 
Adjusted EBITDA$282,781 $65,866 $83,987 $90,777 $42,150 $46,451 
Revenue$814,411 $202,117 $228,317 $229,728 $154,249 $173,167 
Adjusted EBITDA Margin35 %33 %37 %40 %27 %27 %

Adjusted Net Income (Loss) Reconciliation
(Dollars in thousands except per share amounts)1Q20214Q 20203Q 20202Q 20201Q 2020
Net income (loss)$2,060 $11,880 $26,856 $(1,209)$(11,900)
Fair value adjustments, net3,799 (4,110)(2,243)(10,067)8,819 
Foreign exchange loss (gain)(43)4,692 1,233 626 (6,620)
(Gain) loss on sale of assets and securities(4,053)391 2,476 (9)(374)
Loss on debt extinguishment9,172 — — — — 
Silvertip inventory write-down— — 1,232 2,104 10,381 
Silvertip temporary suspension costs— 1,092 838 1,725 3,509 
Silvertip lease modification— — — — (4,051)
Silvertip gain on contingent consideration— — — — (955)
COVID-19 costs3,005 5,138 4,037 6,108 272 
Novation— — 3,819 — — 
Wharf inventory write-down— — — 3,323 — 
Adjusted net income (loss)$13,940 $19,083 $38,248 $2,601 $(919)
Adjusted net income (loss) per share - Basic$0.06 $0.08 $0.16 $0.01 $0.00 
Adjusted net income (loss) per share - Diluted$0.06 $0.08 $0.16 $0.01 $0.00 
Consolidated Free Cash Flow Reconciliation
(Dollars in thousands)1Q20214Q 20203Q 20202Q 20201Q 2020
Cash flow from operations$(4,359)$67,289 $79,464 $9,947 $(7,991)
Capital expenditures59,424 37,393 22,996 16,682 22,208 
Free cash flow $(63,783)$29,896 $56,468 $(6,735)$(30,199)

21


Consolidated Operating Cash Flow
Before Changes in Working Capital Reconciliation
(Dollars in thousands)1Q20214Q 20203Q 20202Q 20201Q 2020
Cash provided by (used in) operating activities $(4,359)$67,289 $79,464 $9,947 $(7,991)
Changes in operating assets and liabilities:
Receivables(999)5,617 1,497 1,536 813 
Prepaid expenses and other655 1,435 1,921 (1,081)346 
Inventories17,486 1,491 3,066 8,056 21,925 
Accounts payable and accrued liabilities28,797 (17,331)(28,570)(2,047)15,051 
Operating cash flow before changes in working capital$41,580 $58,501 $57,378 $16,411 $30,144 

Reconciliation of Costs Applicable to Sales
for Quarter Ended March 31 2021
In thousands (except metal sales, per ounce or per pound amounts)PalmarejoRochesterKensingtonWharfSilvertipTotal
Costs applicable to sales, including amortization (U.S. GAAP)$43,047 $27,610 $44,839 $21,207 $1,086 $137,789 
Amortization(9,059)(3,577)(13,445)(2,475)(1,086)(29,642)
Costs applicable to sales$33,988 $24,033 $31,394 $18,732 $— $108,147 
Inventory Adjustments(57)(313)(151)(52)— (573)
By-product credit— — — (700)— (700)
Adjusted costs applicable to sales$33,931 $23,720 $31,243 $17,980 $— $106,874 
Metal Sales
Gold ounces25,687 6,934 31,595 18,896 83,112 
Silver ounces1,637,695 771,354 — 26,455 — 2,435,504 
Zinc pounds — — 
Lead pounds— — 
Revenue Split
Gold47 %38 %100 %100 %
Silver53 %62 %— %
Zinc— %
Lead— %
Adjusted costs applicable to sales
Gold ($/oz)$621 $1,300 $989 $952 
Silver ($/oz)$10.98 $19.07 $— 
Zinc ($/lb)$— 
Lead ($/lb)$— 











22


Reconciliation of Costs Applicable to Sales
for Three Months Ended December 31 2020
In thousands (except metal sales, per ounce or per pound amounts)PalmarejoRochesterKensingtonWharfSilvertipTotal
Costs applicable to sales, including amortization (U.S. GAAP)$48,672 $36,828 $42,486 $24,300 $— $152,286 
Amortization(12,516)(5,112)(13,179)(2,848)— (33,655)
Costs applicable to sales$36,156 $31,716 $29,307 $21,452 $— $118,631 
Inventory Adjustments(24)24 (56)(49)— (105)
By-product credit— — — (864)— (864)
Adjusted costs applicable to sales$36,132 $31,740 $29,251 $20,539 $— $117,662 
Metal Sales
Gold ounces35,359 8,672 31,830 21,539 97,400 
Silver ounces1,766,714 912,335 35,794 — 2,714,843 
Zinc pounds — — 
Lead pounds— — 
Revenue Split
Gold53 %42 %100 %100 %
Silver47 %58 %— %
Zinc— %
Lead— %
Adjusted costs applicable to sales
Gold ($/oz)$542 $1,537 $919 $954 
Silver ($/oz)$9.61 $20.18 $— 
Zinc ($/lb)$— 
Lead ($/lb)$— 

Reconciliation of Costs Applicable to Sales
for Three Months Ended September 30, 2020
In thousands (except metal sales, per ounce or per pound amounts)PalmarejoRochesterKensingtonWharfSilvertipTotal
Costs applicable to sales, including amortization (U.S. GAAP)$46,163 $22,382 $43,053 $31,887 $1,185 $144,670 
Amortization(11,912)(3,278)(11,523)(4,000)(1,185)(31,898)
Costs applicable to sales$34,251 $19,104 $31,530 $27,887 $— $112,772 
Inventory Adjustments(100)517 (141)(46)— 230 
By-product credit— — — (1,007)— (1,007)
Adjusted costs applicable to sales$34,151 $19,621 $31,389 $26,834 $— $111,995 
Metal Sales
Gold ounces27,252 6,834 27,815 33,382 95,283 
Silver ounces1,765,371 785,887 40,521 — 2,591,779 
Zinc pounds — — 
Lead pounds— — 
Revenue Split
Gold48 %40 %100 %100 %
Silver52 %60 %— %
Zinc— %
Lead— %
Adjusted costs applicable to sales
Gold ($/oz)$602 $1,148 $1,128 $804 
Silver ($/oz)$10.06 $14.98 $— 
Zinc ($/lb)$— 
Lead ($/lb)$— 
23


Reconciliation of Costs Applicable to Sales
for Three Months Ended June 30, 2020
In thousands (except metal sales, per ounce or per pound amounts)PalmarejoRochesterKensingtonWharfSilvertipTotal
Costs applicable to sales, including amortization (U.S. GAAP)$26,095 $21,348 $43,235 $25,653 $1,231 $117,562 
Amortization(7,270)(3,012)(12,853)(3,181)(1,231)(27,547)
Costs applicable to sales$18,825 $18,336 $30,382 $22,472 $— $90,015 
Inventory Adjustments(106)(566)(139)(3,304)— (4,115)
By-product credit— — — (385)— (385)
Adjusted costs applicable to sales$18,719 $17,770 $30,243 $18,783 $— $85,515 
Metal Sales
Gold ounces16,924 5,278 32,367 23,364 77,933 
Silver ounces874,642 723,679 22,707 — 1,621,028 
Zinc pounds — — 
Lead pounds— — 
Revenue Split
Gold62 %44 %100 %100 %
Silver38 %56 %— %
Zinc— %
Lead— %
Adjusted costs applicable to sales
Gold ($/oz)$686 $1,481 $934 $804 
Silver ($/oz)$8.13 $13.75 $— 
Zinc ($/lb)$— 
Lead ($/lb)$— 

Reconciliation of Costs Applicable to Sales
for Three Months Ended March 31, 2020
In thousands (except metal sales, per ounce or per pound amounts)PalmarejoRochesterKensingtonWharfSilvertipTotal
Costs applicable to sales, including amortization (U.S. GAAP)$49,149 $19,860 $42,429 $20,267 $23,002 $154,707 
Amortization(13,175)(2,904)(11,922)(2,444)(5,345)(35,790)
Costs applicable to sales$35,974 $16,956 $30,507 $17,823 $17,657 $118,917 
Inventory Adjustments73 (422)(101)(25)(10,381)(10,856)
By-product credit— — — (248)— (248)
Adjusted costs applicable to sales$36,047 $16,534 $30,406 $17,550 $7,276 $107,813 
Metal Sales
Gold ounces31,287 5,473 32,781 16,094 85,635 
Silver ounces1,894,789 632,237 14,768 158,984 2,700,778 
Zinc pounds 3,203,446 3,203,446 
Lead pounds2,453,485 2,453,485 
Revenue Split
Gold56 %45 %100 %100 %
Silver44 %55 %26 %
Zinc48 %
Lead26 %
Adjusted costs applicable to sales
Gold ($/oz)$645 $1,359 $928 $1,090 
Silver ($/oz)$8.37 $14.38 $11.79 
Zinc ($/lb)$1.12 
Lead ($/lb)$0.74 
24


Reconciliation of Costs Applicable to Sales for 2021 Guidance
In thousands (except metal sales, per ounce or per pound amounts)PalmarejoRochesterKensingtonWharf
Costs applicable to sales, including amortization (U.S. GAAP)$196,255 $105,557 $188,349 $99,746 
Amortization(39,208)(15,899)(59,756)(11,524)
Costs applicable to sales$157,047 $89,658 $128,593 $88,222 
By-product credit— — — (2,255)
Adjusted costs applicable to sales$157,047 $89,658 $128,593 $85,967 
Metal Sales
Gold ounces107,900 27,200 127,000 89,000 
Silver ounces7,128,000 3,807,000 93,000 
Revenue Split
Gold49%36%100%100%
Silver51%64%
Adjusted costs applicable to sales
Gold ($/oz)$710 - $810$1,180 - $1,330$1,010 - $1,110$960 - $1,060
Silver ($/oz)$11.00 - $12.00$15.00 - $17.00


25