Ensco plc
Fleet Status Report
2 January 2019

 
 




 
New Contracts and Extensions
       
Floaters
ENSCO DS-10 contract with Shell offshore Nigeria extended by one year to March 2020
ENSCO 5004 contract with Mellitah in the Mediterranean Sea extended by two wells, with an estimated duration of six months

Jackups
ENSCO 123 awarded a two-well contract with Premier in the North Sea that is expected to commence in July 2019
ENSCO 123 awarded a four-well contract with Premier in the North Sea that is expected to commence in June 2020 (Ensco has the right to provide any ENSCO 120 Series rig to fulfill this contract)
ENSCO 100 awarded a one-well contract with Premier in the North Sea that is expected to commence in March 2020 (Ensco has the right to provide any ENSCO 120 Series rig to fulfill this contract)
ENSCO 76 contract with Saudi Aramco offshore Saudi Arabia extended by four years to December 2022
ENSCO 67 contract with Pertamina offshore Indonesia extended by 500 days to May 2020
ENSCO 102 awarded a one-well contract with Renaissance in the U.S. Gulf of Mexico that is expected to commence in April 2019

Other
ENSCO DS-9 commenced a one-well contract with Total offshore French Guiana in December 2018
ENSCO 108 commenced a three-year contract with Saudi Aramco offshore Saudi Arabia in November 2018

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Page 1 of 10


enscologoa16.jpg
 
 
Ensco plc
Fleet Status Report
2 January 2019
 
 
 
Changes: bolded rig names and underlined text signify changes in rig status from previous report.
Segment /
Region / Rig
 
Design
 
Water
Depth'(1)
 
Customer/
Status
 
Location
 
Contract Start Date
 
Contract End Date(2)
 
Comments
Floaters
 
 
 
 
 
 
 
 
 
 
 
 
 
 
North & South America
 
 
ENSCO 8503
 
Semisubmersible DP
 
8500/10000
 
Talos

 
Mexico
 
Nov. 18
 
Feb. 19
 
Contracted for 100 days (estimated duration Nov. 18 to Feb. 19)
ENSCO 8505
 
Semisubmersible DP
 
8500/10000
 
Eni


 
U.S. GOM
 
Jan. 19
 
Oct. 19
 
Contracted for six wells in the U.S. GOM and for two wells in Mexico (estimated duration Jan. 19 to Oct. 19)






ENSCO 8500
 
Semisubmersible DP
 
8500/10000
 
Preservation Stacked(3)
 
U.S. GOM
 
 
 
 
 
 
ENSCO 8501
 
Semisubmersible DP
 
8500/10000
 
Preservation Stacked(3)

 
U.S. GOM
 
 
 
 
 
 
ENSCO 8502
 
Semisubmersible DP
 
8500/10000
 
Preservation Stacked(3)

 
U.S. GOM
 
 
 
 
 
 
ENSCO 8506
 
Semisubmersible DP
 
8500/10000
 
Preservation Stacked(3)

 
U.S. GOM
 
 
 
 
 
 
ENSCO DS-9
 
Drillship, DP3
DSME
 
12000
 
Total
 
French Guiana

 
Dec. 18

 
Mar. 19

 
Contracted for one well (estimated duration Dec. 18 to Mar. 19)

ENSCO 6002
 
Semisubmersible - DP Megathyst
 
5600
 
Petrobras
 
Brazil
 
Jul. 13
 
Dec. 19
 
Day rate of approx. $248,000, plus approx. $17,000 per day amortized through Dec. 19 for capital upgrades. Plus cost adjustments

Page 2 of 10


enscologoa16.jpg
 
 
Ensco plc
Fleet Status Report
2 January 2019
 
 
 
Changes: bolded rig names and underlined text signify changes in rig status from previous report.
Segment /
Region / Rig
 
Design
 
Water
Depth'(1)
 
Customer/
Status
 
Location
 
Contract Start Date
 
Contract End Date(2)
 
Comments
Floaters
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Europe & Mediterranean
 
 
 
 
 
 
 
 
 
 
ENSCO DS-7
 
Drillship, DP3 Samsung
 
10000/12000
 
Noble Energy
Available
 
Israel
Cyprus
 
Apr. 18
 
Dec. 18
 
-----
ENSCO 5004
 
Semisubmersible - Conv F & G Enhanced Pacesetter
 
1500
 
Mellitah
 
Mediterranean
 
Aug. 14
 
Oct. 19
 
Day rate of approx. $204,000 to Apr. 19, followed by undisclosed day rate for two wells (estimated duration Apr. 19 to Oct. 19)
ENSCO DS-12
 
Drillship, DP3
DSME
 
12000
 
Contract Preparations
 
Spain
 
 
 
 
 
Contracted to BP in Senegal for two wells (estimated duration Apr. 19 to Sep. 19). Plus four 1-well options
ENSCO DS-6
 
Drillship, DP3 Samsung
 
10000/12000
 
Available
 
Spain
 
 
 
 
 
 
ENSCO DS-11

 
Drillship, DP3
DSME
 
12000
 
Available
 
Spain
 
 
 
 
 
 
ENSCO DS-3
 
Drillship, DP3 Samsung
 
10000/12000
 
Preservation
Stacked(3)

 
Spain
 
 
 
 
 
 
ENSCO DS-5
 
Drillship, DP3 Samsung
 
10000/12000
 
Preservation
Stacked(3)

 
Spain
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Africa
 
 
ENSCO DS-4
 
Drillship, DP3 Samsung
 
10000/12000
 
Chevron
 
Nigeria
 
Aug. 17
 
Aug. 19
 
Plus one 1-year priced option
ENSCO DS-8
 
Drillship, DP3 Samsung GF12000
 
10000/12000
 
Total
 
Angola
 
Nov. 15
 
Nov. 20
 
Day rate of approx. $620,000, plus approx. $14,000 per day amortized through Nov. 20 for mobilization. Plus one 14-month priced option
ENSCO DS-10
 
Drillship, DP3 Samsung GF12000
 
10000/12000
 
Shell
 
Nigeria
 
Mar. 18
 
Mar. 20
 
Plus four 1-year priced options

Page 3 of 10


enscologoa16.jpg
 
 
Ensco plc
Fleet Status Report
2 January 2019
 
 
 
Changes: bolded rig names and underlined text signify changes in rig status from previous report.
Segment /
Region / Rig
 
Design
 
Water
Depth'(1)
 
Customer/
Status
 
Location
 
Contract Start Date
 
Contract End Date(2)
 
Comments
Floaters
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Asia & Pacific Rim
 
 
ENSCO DPS-1
 
Semisubmersible DP
F&G ExD Millennium
 
10000
 
Woodside
 
Australia
 
Feb. 18
 
Sep. 19
 
Contracted for 12 wells (estimated duration Feb. 18 to Sep. 19). Plus two 3-month options or one 3-month and one 6-month option
ENSCO 5006
 
Semisubmersible - Conv Bingo 8,000
 
7000/7500
 
INPEX
 
Australia
 
Jan. 15
 
Aug. 19
 
Day rate of approx. $362,000, plus approx. $125,000 per day amortized through Aug. 19 for capital upgrades and day rates during shipyard stay and mobilizations
ENSCO 8504
 
Semisubmersible DP
 
8500/10000
 
Contract Preparations
 
Malaysia
 
 
 
 
 
Contracted to JAPEX in Japan for one well (estimated duration Apr. 19 to Jul. 19)
ENSCO MS-1
 
Semisubmersible
F&G ExD Millennium
 
8200
 
Available
 
Malaysia
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Under Construction
 
 
ENSCO DS-13
 
Drillship, DP3
DSME
 
12000
 
Under Construction
 
South Korea
 
 
 
 
 
Scheduled delivery date 3Q19. Upon delivery, final milestone payment of approx. $84 million and accrued interest charges may be financed through a promissory note that will bear interest at a rate of 5% per annum with a maturity date of December 30, 2022
ENSCO DS-14
 
Drillship, DP3
DSME
 
12000
 
Under Construction
 
South Korea
 
 
 
 
 
Scheduled delivery date 2Q20. Upon delivery, final milestone payment of approx. $165 million and accrued interest charges may be financed through a promissory note that will bear interest at a rate of 5% per annum with a maturity date of December 30, 2022

Page 4 of 10



enscologoa16.jpg
 
 
Ensco plc
Fleet Status Report
2 January 2019
 
 
 
Changes: bolded rig names and underlined text signify changes in rig status from previous report.
Segment /
Region / Rig
 
Design
 
Water
Depth'(1)
 
Customer/
Status
 
Location
 
Contract Start Date
 
Contract End Date(2)
 
Comments
Jackups
 
 
 
 
 
 
 
 
 
 
 
 
 
 
North & South America
 
 
ENSCO 68
 
MLT 84-CE
  
400
 
Castex

Fieldwood



 
U.S. GOM

U.S. GOM



 
Aug. 18

Apr. 19


 
Apr. 19

Jun. 19



 
Contracted for three wells (estimated duration Aug. 18 to Apr. 19)
Contracted for one well (estimated duration Apr. 19 to Jun. 19)
ENSCO 75
 
MLT Super 116-C 
  
400
 
Talos
 
U.S. GOM


 
May 18

 
Sep. 19
 
Plus one 90-day option
ENSCO 87
 
MLT 116-C
  
350
 
Talos
ExxonMobil


 
U.S. GOM
U.S. GOM

 
 
Oct. 18
Nov. 18
 
Nov. 18
Sep. 19
 

Contracted for 13 wells (estimated duration Nov. 18 to Sep. 19)
ENSCO 102
 
KFELS MOD V-A
 
400
 
Arena
Renaissance

Fieldwood
 
U.S. GOM
U.S. GOM

U.S. GOM


 
Nov. 17
Apr. 19

May 19
 
Apr. 19
May 19

Oct. 19
 

Contracted for one well (estimated duration Apr. 19 to May 19). Plus one 1-well option
Contracted for three wells (estimated duration May 19 to Oct. 19). Plus one 2-well option

Page 5 of 10


enscologoa16.jpg
 
 
Ensco plc
Fleet Status Report
2 January 2019
 
 
 
Changes: bolded rig names and underlined text signify changes in rig status from previous report.    
Segment /
Region / Rig
 
Design
 
Water
Depth'(1)
 
Customer/
Status
 
Location
 
Contract Start Date
 
Contract End Date(2)
 
Comments
Jackups
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Europe
 
 
ENSCO 70
 
Hitachi K1032N
 
250
 
Preservation
Stacked(3)
 
UK
 
 
 
 
 
 
ENSCO 71
 
Hitachi K1032N
 
225
 
Preservation
Stacked(3)
 
UK
 
 
 
 
 
 
ENSCO 72
 
Hitachi K1025N
 
225
 
Petrofac
Corallian
 
UK
UK
 
Apr. 18
Nov. 18
 
Oct. 18
Jan. 19
 

Contracted for two wells (estimated duration Nov. 18 to Jan. 19)
ENSCO 92
 
MLT 116-C
 
225
 
ConocoPhillips
 
UK
 
Feb. 17
 
Dec. 22
 
 
ENSCO 100
 
MLT 150-88-C
 
350
 
Available
 
UK
 
 
 
 
 
Contracted to Premier in the UK for one well (estimated duration Mar. 20 to May. 20). Plus two 1-well options(4)
ENSCO 101
 
KFELS MOD V-A
 
400
 
Neptune
 
UK
 
Oct. 18
 
Mar. 19
 
Contracted for two wells (estimated duration Oct. 18 to Mar. 19). Plus unlimited unpriced options
ENSCO 111
 
KFELS MOD V-B
 
400
 
Cold Stacked
 
Malta
 
 
 
 
 
 
ENSCO 112
 
MLT Super 116-E
 
350
 
Cold Stacked
 
Malta
 
 
 
 
 
 
ENSCO 120
 
ENSCO 120 Series
 
400
 
ConocoPhillips
 
UK
 
Jul. 17
 
Jul. 20
 
Plus two 1-year options
ENSCO 121
 
ENSCO 120 Series
 
400
 
Eni
 
UK
 
Dec. 18
 
May 19
 
Contracted for one well (estimated duration Dec. 18 to May 19)
ENSCO 122
 
ENSCO 120 Series
 
400
 
NAM
 
UK
 
Sep. 17
 
May 19
 
Contracted for five wells (estimated duration Sep. 17 to May 19). Plus various options through Dec. 20

Page 6 of 10


enscologoa16.jpg
 
 
Ensco plc
Fleet Status Report
2 January 2019
 
 
 
Changes: bolded rig names and underlined text signify changes in rig status from previous report.
Segment /
Region / Rig
 
Design
 
Water
Depth'(1)
 
Customer/
Status
 
Location
 
Contract Start Date
 
Contract End Date(2)
 
Comments
Jackups
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Middle East
 
 
ENSCO 54
 
F&G L-780 Mod II-C
 
300
 
Saudi Aramco
 
Saudi Arabia
 
Sep. 14
 
Sep. 22
 
Inspection for 70 days in 4Q18. Day rate of approx. $72,000, plus approx. $5,000 per day for upgrade costs and mobilization amortized through Sep. 22
ENSCO 76
 
MLT Super 116-C
 
350
 
Saudi Aramco
 
Saudi Arabia
 
Jan. 15
 
Dec. 22
 
Day rate of approx. $127,000 to Dec. 18, followed by undisclosed day rate from Jan. 19 to Dec. 22
ENSCO 84
 
MLT 82 SD-C
 
250
 
Saudi Aramco
 
Saudi Arabia
 
Jan. 17
 
Aug. 21
 
Day rate of approx. $72,000
ENSCO 88
 
MLT 82 SD-C
 
250
 
Saudi Aramco
 
Saudi Arabia
 
Nov. 13
 
Nov. 19
 
Day rate of approx. $65,000
ENSCO 96
 
Hitachi 250-C
 
250
 
Saudi Aramco
 
Saudi Arabia
 
Feb. 15
 
Feb. 19
 
Day rate of approx. $65,000. -----
ENSCO 97
 
MLT 82 SD-C
 
250
 
Saudi Aramco
 
Saudi Arabia
 
Jan. 15
 
Feb. 19
 
Day rate of approx. $65,000. -----
ENSCO 104
 
KFELS MOD V-B
 
400
 
ADNOC
 
UAE
 
Feb. 18
 
May 19
 
 
ENSCO 108
 
KFELS MOD V-B
 
400
 
Saudi Aramco
 
Saudi Arabia
 
Nov. 18
 
Nov. 21
 
 
ENSCO 110
 
KFELS MOD V-B
 
400
 
North Oil Company
 
Qatar
 
Sep. 17
 
Sep. 20
 
Plus one 1-year priced option
ENSCO 140
 
ENSCO 140 Series
 
340/400
 
Saudi Aramco
 
Saudi Arabia
 
Jul. 18
 
Jun. 21
 
 
ENSCO 141
 
ENSCO 140 Series
 
340/400
 
Saudi Aramco
 
Saudi Arabia
 
Aug. 18
 
Aug. 21
 
 

Page 7 of 10


enscologoa16.jpg
 
 
Ensco plc
Fleet Status Report
2 January 2019
 
 
 
Changes: bolded rig names and underlined text signify changes in rig status from previous report.
Segment /
Region / Rig
 
Design
 
Water
Depth'(1)
 
Customer/
Status
 
Location
 
Contract Start Date
 
Contract End Date(2)
 
Comments
Jackups
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Africa
 
 
ENSCO 109
 
KFELS MOD V-Super B
 
350
 
Chevron
 
Angola
 
Dec. 14
 
Jul. 19
 
Day rate of approx. $172,000 from mid Apr. 18 to Jul. 18, followed by undisclosed day rate from Aug. 18 to Jul. 19
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Asia & Pacific Rim
 
 
ENSCO 67
 
MLT 84-CE
 
400
 
Pertamina
 
Indonesia
 
Dec. 16
 
May 20
 
Rig idled from late Feb. 18 to Dec. 18. Contracted for 500 days (estimated duration Jan. 19 to May 20)
ENSCO 105
 
KFELS MOD V-B
 
400
 
Preservation
Stacked
(3)
 
Singapore
 
 
 
 
 

ENSCO 106
 
KFELS MOD V-B
 
400
 
BP
 
Indonesia
 
Jan. 18
 
Jan. 23
 
Plus 13 1-well priced options
ENSCO 107
 
KFELS MOD V-B
 
400
 
Quadrant Energy/ Vermilion Energy
 
Australia
 
May 18
 
Jan. 19
 
Contracted for 160 days with Quadrant (estimated duration May 18 to Oct. 18). Assigned to Vermilion for two wells (estimated duration Oct. 18 to Jan. 19). Plus two 1-well options with Quadrant thereafter
ENSCO 113
 
Pacific Class 400
 
400
 
Cold Stacked

 
Philippines
 
 
 
 
 
 
ENSCO 114
 
Pacific Class 400
 
400
 
Cold Stacked

 
Philippines
 
 
 
 
 
 
ENSCO 115
 
Pacific Class 400
 
400
 
Contract Preparations
 
Malaysia
 
 
 
 
 
Contracted to Mubadala Petroleum in Thailand from 1Q19 to 4Q19. Plus one 2-month option and three 4-month options

Page 8 of 10


enscologoa16.jpg
 
 
Ensco plc
Fleet Status Report
2 January 2019
 
 
 
Changes: bolded rig names and underlined text signify changes in rig status from previous report.
Segment /
Region / Rig
 
Design
 
Water
Depth'(1)
 
Customer/
Status
 
Location
 
Contract Start Date
 
Contract End Date(2)
 
Comments
Jackups
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Under Construction
 
 
ENSCO 123
 
ENSCO 120 Series
 
400
 
Contract Preparations
 
Singapore
 
 
 
 
 
Contracted to Premier in the UK for two wells (estimated duration Jul. 19 to Oct. 19). Plus one 1-well option
Contracted to Premier in the UK for four wells (estimated duration (Jun. 20 to Jul. 21). Plus three 1-well options(4)
 
 
 
Other
 
 
Drilling Management
 
 
Thunder Horse
 
Deepwater Semisubmersible
 
6000
 
BP
 
U.S. GOM
 
Jan. 17
 
Jan. 22
 
Day rate of approx. $95,000, plus cost adjustments and five 1-year options
Mad Dog
 
Deepwater Spar Drilling Rig
 
4500
 
BP
 
U.S. GOM
 
Jan. 17
 
Jan. 22
 
Day rate of approx. $57,000, plus cost adjustments and five 1-year options
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

(1) For rigs that may be modified to drill in deeper water depths, both the currently outfitted and maximum upgrade capabilities are shown.
(2) Contract duration does not include any unexercised optional extensions. Contract end dates can vary based on how long it takes to complete the wells subject to the contract.
(3) Prior to stacking, upfront steps are taken to preserve the rig. This may include a quayside power source to dehumidify key equipment and/or provide electrical current to the hull to prevent corrosion. Also, certain equipment may be removed from the rig for storage in a temperature-controlled environment. While stacked, large equipment that remains on the rig is periodically inspected and maintained by Ensco personnel. These steps are designed to reduce the time and lower cost to reactivate the rig when market conditions improve.
(4) Ensco has the right to provide any ENSCO 120 Series rig to fulfill this contract.

Page 9 of 10


enscologoa16.jpg
 
 
Ensco plc
Fleet Status Report
2 January 2019
 
 
 
 
Additional Information Regarding this Fleet Status Report
 
Day Rate and Terms. The day rates reflected in this Fleet Status Report are stated in U.S. dollars and are the operating day rates charged to customers, which may include estimated contractual adjustments for changes in operating costs and/or reimbursable cost adjustments for ongoing expenses such as crew, catering, insurance and taxes. The day rates, however, do not include certain types of non-recurring revenues such as lump sum mobilization payments, revenues earned during mobilizations, revenues associated with contract preparation and other non-recurring reimbursable items such as mobilizations and capital enhancements, and the impact of the fair market value adjustments to previously acquired drilling contracts. Routine and non-routine downtime may reduce the actual revenues recognized during the contract term. Additionally, we sometimes negotiate special rates and/or day rate adjustments with customers that may reduce revenues recognized. Ensco announced in its Fleet Status Report dated 22 February 2017 that going forward it does not expect to release day rates for new contracts in its Fleet Status Reports. Significant zero rate estimates are reflected in the comments section for 2018 and 2019.
 
Forward Looking Statements. Statements contained in this Fleet Status Report that are not historical facts are forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. Forward-looking statements include words or phrases such as “anticipate,” “believe,” “estimate,” “expect,” “intend,” “plan,” “project,” “could,” “may,” “might,” “should,” “will” and similar words and specifically include statements involving future rig day rates including adjustments with the customer; discussions with the customer; backlog; cost adjustments; utilization; estimated rig availability; expected work commitments and contracts; contract duration, status, terms and other contract commitments; letters of intent, letters of award or other correspondence indicating an award; rig enhancement projects; new rig commitments; the expected period of time and number of rigs that will be in a shipyard for repairs, maintenance, enhancement or construction; sale leaseback transactions; scheduled delivery dates for new rigs; and the timing of delivery, mobilization, contract commencement, relocation or other movement of rigs. Such statements are subject to numerous risks, uncertainties and assumptions that may cause actual results to vary materially from those indicated, including commodity price fluctuations, customer demand, new rig supply, downtime and other risks associated with offshore rig operations; relocations; costs and difficulties related to the integration of Atwood Oceanics, Inc. and Rowan Companies plc; severe weather or hurricanes; changes in worldwide rig supply and demand, competition and technology; future levels of offshore drilling activity; governmental action, civil unrest and political and economic uncertainties; terrorism, piracy and military action; risks inherent to shipyard rig construction, repair, maintenance or enhancement; possible cancellation, suspension, repudiation, or termination of drilling contracts, including termination for convenience (without cause), as a result of mechanical difficulties, performance, customer liquidity and finances, the decline or the perceived risk of a further decline in oil and/or natural gas prices, or other reasons; our ability to enter into, and the terms of, future drilling contracts; the cancellation of letters of intent or any failure to execute definitive contracts following announcements of letters of intent, letters of award or other expected work commitments or awards; the outcome of litigation, legal proceedings, investigations or other claims or contract disputes; governmental regulatory, legislative and permitting requirements affecting drilling operations; our ability to attract and retain skilled personnel on commercially reasonable terms; environmental or other liabilities, risks or losses; debt restrictions that may limit our liquidity and flexibility; and cybersecurity risks and threats. In addition to the numerous factors described above, you should also carefully read and consider “Item 1A. Risk Factors” in Part I and “Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations” in Part II of our most recent annual report on Form 10-K, as updated in our subsequent quarterly reports on Form 10-Q, which are available on the SEC’s website at www.sec.gov or on the Investor Relations section of our website at www.enscoplc.com.  Each forward-looking statement contained herein speaks only as of the date of this Fleet Status Report, and we undertake no obligation to publicly update or revise any forward looking statements, except as required by law.

Page 10 of 10