Attached files

file filename
8-K - 8-K - SCANA CORPform8-kscpsc.htm
                        


Exhibit 99.1
BEFORE

THE PUBLIC SERVICE COMMISSION

OF

SOUTH CAROLINA

DOCKET NO. 2015-__-E

In Re: Petition of South Carolina Electric & Gas Company for Updates and Revisions to Schedules Related to the Construction of a Nuclear Base Load Generation Facility at Jenkinsville, South Carolina
)
)
)
)
)
)

PETITION FOR UPDATES AND REVISIONS TO THE CAPITAL COST SCHEDULE AND THE CONSTRUCTION SCHEDULE
    South Carolina Electric & Gas Company (“SCE&G” or the “Company”) hereby petitions the Public Service Commission of South Carolina (the “Commission”) for an order approving an updated capital cost schedule and updated construction schedule for the construction of two 1,117 net megawatt nuclear units (the “Units”) to be located at the V.C. Summer Nuclear Station site near Jenkinsville, South Carolina. This petition (the “Petition”) is filed pursuant to the provisions of the Base Load Review Act (“BLRA”), S.C. Code Ann. § 58-33-270(E) (Supp. 2014). In accordance with the provisions of the BLRA, SCE&G would respectfully show to the Commission the following:
I.INTRODUCTION
1.SCE&G is a corporation duly organized and existing under the laws of the State of South Carolina, with its principal offices at 220 Operation Way, Cayce, South Carolina 29033.

1


                        


2.    SCE&G is engaged in the business of generating, transmitting, and delivering electricity and providing electric service to the public for compensation. SCE&G owns and operates an integrated electric utility system that serves approximately 688,000 customers in 24 counties in central and southern South Carolina.
3.    Corporate legal counsel for SCE&G in this proceeding are as follows:
K. Chad Burgess
Matthew W. Gissendanner
South Carolina Electric & Gas Company
Mail Code C222
220 Operation Way
Cayce, SC 29033
(803) 217-8141
chad.burgess@scana.com
matthew.gissendanner@scana.com

Private legal counsel for SCE&G in this proceeding is as follows:
Belton T. Zeigler
Pope Zeigler, LLC
P.O. Box 11509
Columbia, SC 29211
(803) 354-4949
bzeigler@popezeigler.com
All correspondence and any other matters relative to this proceeding should be addressed to these representatives.
II.PRIOR BLRA ORDERS
4.    In Docket No. 2008-196-E, SCE&G sought approval of a Combined Application for a Certificate of Environmental Compatibility and Public Convenience and Necessity and for a Base Load Review Order for the Construction and Operation of a Nuclear Facility in Jenkinsville, South Carolina for the Units. Pursuant to S.C. Code

2


                        


Ann. § 58-33-250, SCE&G provided the anticipated construction schedule and anticipated capital cost schedule for the Units.
5.    Those schedules indicated that the Units could be constructed for a total cost to SCE&G of approximately $4.5 billion in 2007 dollars. 1
6.    Following a full hearing on the Combined Application, the Commission issued Order No. 2009-104(A), in which the Commission approved the proposed construction schedule and capital cost schedule for the Units.
7.    In Order No. 2010-12, dated January 22, 2010, the Commission approved SCE&G’s request to update the construction schedule for the project and to update the capital cost schedule for the project to reflect changes in the forecasted timing of cash flow resulting from the updated construction schedule. The updated capital cost schedule did not alter the total estimated capital cost for the Units of approximately $4.5 billion in 2007 dollars.
8.    In Order No. 2011-345, the Commission approved the Company’s request to update capital cost projections for the project in response to the decision by the Supreme Court of South Carolina in South Carolina Energy Users Comm. v. South Carolina Pub. Serv. Comm’n, 388 S.C. 486, 697 S.E.2d 587 (2010). In that Opinion, the Supreme Court disallowed the inclusion in capital cost forecasts of costs that had not been itemized to specific capital cost items. In response, SCE&G removed its owner’s contingency pool from the capital cost forecasts and sought Commission approval of
_________________
1 Unless otherwise noted, all amounts reflect SCE&G's portion of the cost of the Units in 2007 dollars.

3


                        


specific costs that would otherwise have been accounted for using the contingency allowance. Order No. 2011-345 established a total estimated capital cost for the Units of approximately $4.3 billion in 2007 dollars.
9.    On March 30, 2012, the Nuclear Regulatory Commission (“NRC”) issued the Combined Operating License (“COL”) for the Units which allowed nuclear safety-related construction to begin.
10.     On July 11, 2012, SCE&G signed an agreement with the contactors for the Units, Westinghouse Electric Company (“WEC”) and the Shaw Group, now Chicago Bridge and Iron (“CB&I,” and together with WEC, “WEC/CB&I”). The agreement provided for new substantial completion dates for the Units tied to the issuance date of the COL which had been delayed by approximately nine months. That agreement also resolved claims made by WEC/CB&I under the Engineering, Procurement and Construction Contract (“EPC Contract”) for additional charges related to the delay in the issuance of the COL, design changes made to the Units during licensing, unanticipated rock conditions at the site of the Unit 2 Nuclear Island and other matters.
11.    In Order No. 2012-884, dated November 15, 2012, the Commission approved SCE&G’s request to update the construction schedule and the capital cost schedule for the project to reflect the new substantial completion dates and the settlement of claims by WEC/CB&I. The Commission also approved updates to the capital cost schedule for change orders related to cyber security costs; the effect of Federal legislation on healthcare costs for CB&I; and waste water piping; as well as changes in Owner’s costs related to schedule

4


                        


delay, changes in plant safety regulations and other changes; and changes in Transmission Costs related to changing load forecasts and power flow modeling, updated equipment loading forecasts and unanticipated construction conditions at a substation site.
12.    In Order No. 2012-884, the Commission approved an estimated capital cost for the Units of approximately $4.5 billion in 2007 dollars and a new milestone schedule tied to substantial completion dates for Units 2 and 3 of March 15, 2017, and May 15, 2018, respectively.
13.    Order No. 2012-884 was appealed to the South Carolina Supreme Court. The Supreme Court affirmed the Commission’s ruling in all respects in South Carolina Energy Users Comm. v. South Carolina Elec. & Gas, 410 S.C. 348, 764 S.E.2d 913 (2014).
III.CURRENT UPDATE REQUEST
14.    Since the issuance of Order No. 2012-884, substantial progress has been made towards the completion of the Units. As of the time of this filing:
a.    Eighty-five percent of the major equipment for Unit 2 has been received on site.
b.    Eighty-six percent of the circulating water system for both Units has been installed. Two of the Units’ four cooling water towers are complete and the third is two-thirds complete.
c.    The containment vessel bottom heads of both Units have been fabricated and set on nuclear island basemats for the two Units.

5


                        


d.    All three of the steel rings that comprise the vertical walls of the Unit 2 containment vessel have been completed or are nearing completion. Unit 2, Ring 1 has been set in place. Fabrication of Unit 3 containment vessel Ring 1 and Ring 2 is underway.
e.    Sixty-six individuals have been recruited and are in training to become licensed system operators for AP1000 units. Approximately 84 additional personnel are in training as non-licensed system operators or to become qualified in other technical, maintenance and craft areas.
f.    More than 3,800 construction personnel are working on site. A total of 23 million man-hours have been worked with an excellent safety record.
15.    When constructed, the Units will provide the State of South Carolina with 2,234 megawatts of reliable electrical generating capacity. As to greenhouse gases, generation from the Units will be emissions-free in all material respects. Because of the Units, SCE&G forecasts that its carbon emissions in 2020 will be lower than its carbon emissions in 2005 by almost 50%. When the Units come on-line, approximately 60% of SCE&G’s system electricity will come from sources without greenhouse gas emissions. The Units are anticipated to provide SCE&G’s customers with service for 60 years or more.

6


                        



16.    From a financial standpoint, important elements of the costs to customers from the project have been reduced from the projections that were presented when the Units were initially approved in Docket 2008-196-E.
a.    Since 2008, SCE&G has been able to obtain low-cost borrowing for project costs based on SCE&G’s favorable bond ratings and the low cost of financing available in debt markets. Compared to the projections made in the 2008 BLRA proceedings, customers are anticipated to save $1.2 billion in interest cost over the life of the debt that has been issued to date or for which rates for future issuances have been hedged. SCE&G’s ability to access debt capital at favorable rates is in part the direct result of the BLRA and how it has been administered by the Commission and the South Carolina Office of Regulatory Staff.
b.    During the period since 2008, the forecasted cost of escalation for the project has declined by $214 million even after considering the effect on escalation of proposed new substantial completion dates.
c.    Based on current construction schedules and assuming current tax law, SCE&G anticipates that additional Federal Production Tax Credits will be available for the Units that will provide customers with $1.2 billion in additional benefits compared to projections made in 2008.
17.    However, delays related to structural submodule production at the CB&I facility in Lake Charles, Louisiana; revised schedules for the production of shield building

7


                        


panels at the Newport News Industries ("NNI") facilities in Newport News, Virginia; and other changes in construction, construction oversight and operational readiness requirements have resulted in revisions to the construction and cost schedules for the project. Those revisions are the subject of this filing.
18.    Accordingly, SCE&G hereby requests adjustments to the milestone construction schedule and capital cost schedule for the project.
A.    UPDATED CONSTRUCTION SCHEDULE
19.    During the third quarter of 2013, WEC/CB&I provided SCE&G with information indicating that the substantial completion dates for Units 2 and 3 would be delayed. In the ensuing months, WEC/CB&I updated this information to include a detailed reevaluation of the engineering, procurement and construction activities necessary to complete the Units with specific emphasis on the production schedules for structural submodules and shield building panels.
20.    The result of WEC/CB&I’s effort is a revised, fully-integrated construction schedule (the “Revised, Fully-Integrated Construction Schedule”) with an associated cash flow forecast for completion of the project (the “Revised Cash Flow Forecast”).
21.    The Revised, Fully-Integrated Construction Schedule indicates new substantial completion dates for Units 2 and 3 of June 19, 2019, and June 16, 2020, respectively (the “Substantial Completion Dates”). SCE&G has not, however, accepted WEC/CB&I’s contention that the new Substantial Completion Dates are made necessary by delays that are excusable under the EPC Contract.

8


                        


22.    Attached to this filing as Exhibit 1 is an updated construction milestone schedule for the project which aligns all milestones as approved in Order No. 2009-104(A) to the new Substantial Completion Dates and to the current construction and fabrication schedules.
23.    SCE&G requests that the Commission approve Exhibit 1 as the revised construction schedule for the project. As to all matters pertaining to the schedule revisions reflected on Exhibit 1, SCE&G requests the Commission to affirm that SCE&G’s actions associated with these schedule changes have been reasonable and prudent.
24.    WEC/CB&I continues to refine and update the Revised, Fully-Integrated Construction Schedule as issued-for-construction designs are finalized and as additional information is received related to the fabrication of modules, shield building panels and equipment; construction activities on site; start-up testing requirements and other matters. For example, by letter dated March 10, 2015, WEC/CB&I provided SCE&G with preliminary information concerning an integrated project schedule update (the “March Revision”), indicating that WEC/CB&I’s current construction planning now shows a substantial completion date for Unit 2 of August 10, 2019, and June 7, 2020 for Unit 3. As of the time of the filing of this Petition, SCE&G has not analyzed or accepted the preliminary information concerning the March Revision nor has it discussed potential schedule mitigation efforts with WEC/CB&I. Considering the preliminary nature of the information contained in the March Revision, it is not part of this filing or the schedules presented here.

9


                        


SCE&G continues to review the schedule refinements and updates provided by WEC/CB&I and to explore schedule mitigation opportunities with WEC/CB&I related to them.
25.    This review and updating of construction schedules will continue as a part of the project for the foreseeable future and may result in additional schedule changes. However, the Revised, Fully-Integrated Construction Schedule and Revised Cash Flow Forecast presented here are based upon SCE&G’s most current review and analysis of the information provided.

B.    UPDATED COST FORECASTS
26.    SCE&G further requests that the Commission update the cost schedule for completion of the Units to reflect (a) the effect of the new Substantial Completion Dates on Owner’s costs, and (b) other changes in costs that have been identified since the forecasts approved in Order No. 2012-884 were prepared.
a.EPC Contract Costs
27.    The Revised Cash Flow Forecast that WEC/CB&I has provided SCE&G indicates that the estimated at completion (“EAC”) cost for the project has increased. The revisions to the EAC cost are in the EPC Contract categories of Actual Craft Wages, Non-Labor Costs, and Time and Material Costs. These cost categories are those that, under the terms of the EPC Contract, SCE&G pays WEC/CB&I’s actual costs plus contractually determined margins.


10


                        


i.Delay and Other EAC Costs
28.    The majority of the revised EAC costs are the result of delays in the project, revised projections of the labor required to accomplish previously-identified scopes of work, and revised overhead and staff ratios associated with that labor. The revised EAC costs also reflect additional Time and Materials scopes of work necessary to staff the start-up of the Units and to provide for the processing of License Amendment Requests (“LARs”) to support construction. LARs are requests for amendments to the design basis of the Units that must be approved by the NRC.
29.    SCE&G has not accepted responsibility for these costs (the “Delay and Other EAC Costs”). SCE&G has also asserted the claim that WEC/CB&I is contractually responsible for the occurrence of the delay and other factors underlying the Delay and Other EAC Costs.
30.    WEC/CB&I has not accepted responsibility for any part of SCE&G’s claim.
31.    At the time of this filing, WEC/CB&I and SCE&G are in negotiations concerning responsibility for the Delay and Other EAC Costs. However, under the EPC Contract, which was approved by this Commission in Order No. 2009-104(A), SCE&G must pay WEC/CB&I at least 90% of certain types of disputed amounts, provided that WEC/CB&I has properly invoiced those amounts to SCE&G under the EPC Contract.

11


                        



32.    Other provisions of the EPC Contract provide that SCE&G shall recoup from WEC/CB&I any payments made on disputed amounts if the dispute is resolved in SCE&G’s favor.
33.    Although SCE&G has advised WEC/CB&I that the provision concerning 90% payments does not apply to certain of WEC/CB&I’s invoices, WEC/CB&I has disagreed. WEC/CB&I has reserved its rights under a provision of the EPC Contract that permits it to cease work and treat the project as if it had been suspended at SCE&G’s request if 90% payments are contractually required but are not made within 30 days after proper invoicing.
34.    SCE&G has included in the cash flow forecasts presented here payments associated with the Delay and Other EAC Costs. By including these payments in this filing, SCE&G in no way waives any claims or defenses related to them.
35.    By including these payments in this filing, SCE&G seeks only to recover carrying costs on those payments as the BLRA envisions. As a general principle under the BLRA, until the Units go into commercial operation, the Company can recover only its carrying costs on its investment in the Units.
36.    If through negotiation or litigation, SCE&G recovers any past payments to WEC/CB&I or reduces any current payments, those amounts will be reflected as reductions to the capital cost of the project. Doing so will reduce the financing costs to be charged to customers and the reduction will be reflected in lower revised rates in subsequent revised rates proceedings.

12


                        


37.    SCE&G also forecasts that it will recover from WEC/CB&I the full amount of liquidated damages payable under the EPC Contract for delays in the substantial completion dates for the Units. The full amount of liquidated damages is $86 million and has been netted against the Delay and Other EAC Costs for the purposes of this filing.
38.    The amount of the Delay and Other EAC Costs is $411 million, or $325 million net of liquidated damages. This net amount represents approximately 47% of the total change in the capital cost schedule.
ii.Changes to the EAC Cost Due to Design Finalization
39.    WEC/CB&I continues to finalize the issued-for-construction design documents for the project. As it does so, WEC/CB&I updates its projections of the amount of commodities that must be installed to complete the project, i.e., the required units of materials and equipment such as concrete, cabling, rebar and piping that are necessary to compete the Units.
40.    As a result of design finalization, WEC/CB&I has identified additional units of commodities that must be installed.
41.    Under the fixed and firm pricing components of the EPC Contract, WEC/CB&I is responsible for the cost of the additional commodities themselves; however, SCE&G is responsible for the Actual Craft Wages and Non-Labor Costs associated with performing this work of installing these additional units of commodities.

13


                        


42.    SCE&G’s assessment of WEC/CB&I’s entitlement for payment associated with these recently identified costs is approximately $72 million, or approximately 10% of the total change in the capital cost schedule.
iii.Changes in EAC Costs Due to Change Orders
43.    SCE&G has executed or anticipates executing ten additional change orders under the EPC Contract. The forecasted costs associated with these change orders are included in the capital cost schedule submitted here.
1.Plant Layout Security
44.    SCE&G has recently conducted a review of plant layout to ensure that its physical security can be maintained. This was necessary as a final stage in the design review of the Units and their supporting structures and could not be done until design layouts and building orientations were finalized.
45.    These physical security reviews have been conducted based on NRC and nuclear industry standards that have become increasingly stringent in the years after the events of September 11, 2001.
46.    As a result of these reviews, SCE&G has determined that it is reasonable and prudent to alter the site layout in various ways to improve its physical security and has negotiated a change order to the EPC Contract for this work.
47.    The cost of the current phase of the work to increase the security of the plant through physical security alterations is forecasted to be $20.4 million.

14


                        



2.Cyber Security Upgrades
48.    In late 2011, an agreement was reached between SCE&G and WEC/CB&I on a phased approach to strengthening the Units’ defenses against cyber attacks (“Cyber-Security”). The cost of the Phase I scope of the Cyber Security plan was reviewed by the Commission and approved in Order No. 2012-884. However, the Commission determined that approval of Phase II costs should be deferred until the scope of work and associated costs were more fully defined and quantified.
49.    In mid-2013, SCE&G and WEC/CB&I agreed to divide the remaining Cyber Security plan into additional phases. The cost for Phase II of the plan is $18.8 million. The scope of work for the following phases of the plan will be determined as Phase II is completed.
3.Schedule Mitigation for Shield Building Panels
50.    WEC/CB&I has subcontracted the construction of the steel panels which will form the walls of the shield buildings to NNI in Newport News, Virginia.
51.    Schedule delays related to the finalization of design of these panels have placed the fabrication of these panels on the critical path for timely completion of the project.
52.    NNI has agreed to expand its manufacturing facility to allow for additional panels to be worked simultaneously, thus mitigating potential schedule delays.
53.    SCE&G estimates that the cost of this expansion will add $12.1 million to the EPC Contract cost.

15


                        



4.Additional Costs Related to the Federal Health Care Act
54.    Both WEC and CB&I have sought change orders to recover their increased costs of compliance with the Federal Patient Protection and Affordable Care Act and related statutes. As a change in cost caused by a change in law, these amounts are recoverable under the EPC Contract. Change Order 20 provides for the recovery of WEC’s costs for 2011-2013 in the amount of $206,589. The amount of these additional costs for WEC/CB&I over the life of the project is forecasted to be $2.2 million.
5.Plant Reference Simulator and Software Upgrade
55.    Change Order 19 provides for upgrades to the Plant Reference Simulator (“PRS”) hardware and software and associated training to enhance PRS displays and to acquire versions of the software that will be issued subsequent to the version provided under the EPC Contract. The cost of this change order is forecasted at approximately $1.1 million.

6.
Ovation and Common Q Instrumentation and Control Maintenance Training Systems

56.    Ovation and Common Q are the instrumentation and control software that will be used to operate the Units. Maintenance training systems are required to support training on the Ovation and Common Q system in a training environment without interfering with the use of the systems for operations. Maintenance training systems also allow software maintenance to be conducted off-line.

16


                        


57.    The cost of the change order associated with acquiring hardware and software for these maintenance training systems is currently forecasted at approximately $880,000.
7.Simulator Development System
58.    The PRS is a critical system necessary for training and requalifying licensed operator candidates and senior operators and for developing and validating NRC license exam simulator scenarios.
59.    SCE&G has determined that the schedule for training and scenario development on the PRS will require it to be in nearly continuous use for the balance of the project. This level of use does not allow sufficient time for the PRS to be taken out of service for upgrades, modifications and routine maintenance of its software.
60.    The new Simulator Development System will be a scaled down version of the PRS. It will include a complete copy of the PRS software which can be serviced and modified without interfering with use of the PRS. The modified software can then be uploaded to the PRS when servicing is complete. The cost of the change order to acquire the Simulator Development System is currently forecasted to be approximately $605,000.
8.ITAAC Maintenance
61.    Change Order 21 provides for the recovery of the costs of new NRC regulations requiring the review of completed Inspections, Tests, Analyses, and Acceptance Criteria (“ITAAC”) packages when work is done on the associated

17


                        


components or systems or non-conforming conditions are discovered after the ITAAC is closed.
62.    Change Order 21 reflects WEC/CB&I’s cost for 2015 of $59,400. WEC/CB&I intends to submit a new change order each year. SCE&G has forecasted the costs for 2016-2020 to be $313,000, for a total of $372,400 in additional costs over the life of the project.
9.Warehouse Fire Security
63.    To mitigate fire insurance premiums, SCE&G is upgrading the remote monitoring capabilities of the fire and security systems in the three on-site warehouses that serve the project. The cost of these upgrades will be $121,000.
10.Perch Guards
64.    Change Order 18 provides for the installation of perch guards on transmission structures on site to prevent avian interference with system reliability. The forecasted cost of this change order is $14,056.
Total for Change Orders
65.        The costs associated with these ten change orders is $56.5 million or approximately 8% of the total request.
iv.Switchyard Cost Re-Allocation
66.    The Unit 2-3 Switchyard is an asset belonging to the project and its costs were originally allocated between SCE&G and Santee Cooper based on their percentages of ownership in the project.

18


                        


67.    However, both Santee Cooper and SCE&G are also constructing certain transmission lines and other facilities at their individual expense to transmit power from the project to their customers. As a result, they will use shared transmission assets like the Switchyard in proportions that are different from their ownership of the Units.
68.    To account for this fact, Santee Cooper and SCE&G agreed that the transmission assets constructed as part of the project would be allocated among themselves based on engineering studies of how intensively each party would use specific project assets.
69.    These studies have resulted in a $107,000 decrease in the allocation of Switchyard costs to SCE&G.
b.Owner’s Cost Revisions Associated With Delay
i.Owner’s Labor Cost Revisions Associated with Delay
70.    SCE&G’s New Nuclear Deployment (“NND”) team is primarily responsible for meeting SCE&G’s obligations as owner of the project and as the holder of active NRC licenses to construct and operate the Units.
71.    As owner and licensee of the project, SCE&G’s obligations include responsibility for (a) quality assurance/quality control (“QA/QC”) oversight both on site and at suppliers’ locations worldwide; (b) the training and licensing of all personnel required for Unit operations; (c) the auditing of invoices from WEC/CB&I and other suppliers and the resolution of contractual and payment disputes with WEC/CB&I; (d) oversight and accounting for all commercial aspects of the project; (e) acceptance testing

19


                        


and maintenance of plant systems as they are completed and turned over to SCE&G; (f) accepting the handover and maintenance of engineering, QA/QC and other data necessary for operating the Units; (g) drafting the procedures for plant operations and safety; (h) conducting plant start-up and start-up testing; and (i) providing the administrative support, IT systems and software necessary to sustain these functions. The operational readiness group comprises all personnel necessary to operate and maintain the Units when in service. In addition to their training, they also take a lead role in developing programs and procedures for operation and maintenance of the Units and in overseeing start-up and testing.
72.    SCE&G’s NND team is comprised of 507 individuals. Many are highly-skilled professionals in engineering, nuclear construction management, QA/QC, training, operational readiness, and other disciplines.
73.    Extending the duration of the construction project will require SCE&G to maintain its NND team in place to support the completion of Units 2 and 3 for an additional 27 months and 25 months, respectively.
74.    In response to the new Substantial Completion Dates, SCE&G has taken reasonable steps to delay NND hiring and to revise work assignments. However, SCE&G forecasts that the extension of the project will increase Owner’s labor costs by approximately $125.3 million to allow SCE&G to support the NND team’s role in the project for a longer period.

20


                        



ii.Owner’s Risk Insurance and Workers Compensation Insurance
75.    As project owner, SCE&G is responsible for owner’s risk insurance and workers compensation insurance on the project. In spite of diligent efforts to minimize these costs, SCE&G forecasts that extending the project will result in an increase in Owner’s costs of approximately $30.1 million.
iii.Additional Information Technology ("IT") Costs Associated with Delay
76.    As project owner, SCE&G is obligated to supply the software and other IT resources required to support operational readiness and the work of the NND team during construction. SCE&G must also ensure that the engineering data, QA/QC documentation and other data that are necessary for testing, start-up, and the operation of Units are properly maintained in SCE&G’s IT system and are available at all times to the Units’ operating staff.
77.    Extending the project schedule will increase the cost of IT support for the project because software licenses and maintenance fees, equipment maintenance costs and other IT support costs must be paid for longer periods of time.
78.    SCE&G forecasts that extending the schedule of the project will increase the IT component of Owner’s costs by $6.5 million.
iv.Facilities Cost Increases Associated with Delay
79.    SCE&G is responsible for the warehouse and storage space for materials and equipment necessary to operate the Units.

21


                        


80.    SCE&G is also required to pay for the office space and related support facilities for its NND team personnel while they are on site.
81.    Because of delays in the project schedule, construction teams and operational readiness teams will overlap more, requiring more space. In addition, the maintenance, upkeep and other costs of office space and related support facilities will have to be borne by the project for a longer period of time.
82.    SCE&G has taken reasonable steps to reduce the scope and cost of the additional warehouse, storage, office and other support facilities. Nevertheless, SCE&G forecasts that additional facilities and facilities costs associated with the new Substantial Completion Dates will increase Owner’s cost by $6.1 million.
v.Other Owner’s Costs Associated with Delay
83.    Extending the duration of the project will also increase Owner’s costs across a broad range of cost centers related to technical, administrative and other support for the project as well as increasing non-labor costs associated with NND centers. These cost centers include V.C. Summer Unit 1 cost centers and SCANA and SCE&G cost centers such as Licensing, Construction, Engineering, and Maintenance. The cumulative effect of these increases is forecasted to total $46.4 million.
c.
Owner’s Cost Increases Not Associated with Delay
i.Additional NND Staff
84.    SCE&G has identified the need to add approximately 64 employees to its NND staff.

22


                        


a.Approximately 43 of these additional personnel will be devoted to developing operating and safety procedures for AP1000 units. These additional personnel are required because experience has shown that the volume of work to be done in preparing procedures is greater than anticipated due in large part to increasingly demanding operating standards imposed by the NRC and the nuclear industry.
b.Ten of these additional personnel are necessary to staff the project’s expanded cyber security program;
c.Six of these additional personnel are needed to meet the need to hire and train new members of the training department in anticipation of retirements that are now expected to occur before the completion of the project; and
d.Three of these additional personnel are for assignments principally involving the coordination of project activities with industry standards groups and two are in other areas.
85.    The cost of these additional 64 individuals is approximately $7.5 million.
ii.NRC Fees
86.    The NRC has updated its estimate of the fees that SCE&G must pay for NRC inspection and oversight of the project. The new estimate includes additional expenses for pre-inspection preparation and off-site work following up on inspections.
87.    The new NRC fee estimate will increase Owner’s cost for the project by $7.1 million.

23


                        


iii.Other IT Costs
88.    SCE&G has identified additional software and other IT resources, not related to the delay, that are necessary costs of the project. Included in these IT resources are additional cyber security resources for NND project personnel, fatigue and stress modeling software to diagnose and monitor the condition of equipment in the Units, and additional software to capture and monitor plant operating data.
89.    SCE&G has exercised care and diligence to mitigate or avoid additional IT costs. However, in spite of these efforts, SCE&G has determined that additional IT costs are prudent and necessary and forecasts that they will add $3.3 million to Owner’s costs.
iv.Other Owner’s Costs Not Associated with Delay
90.    SCE&G’s forecast of Owner’s costs has also increased in other areas including increased facilities cost, the cost of additional contractors for oversight of construction and component fabrication, increased fees for participation in the AP1000 Users Group, increased costs for updating Probability Risk Assessments related to the Units, and the cost of maintenance equipment needed to support the project during systems testing and when in operation.
91.    The amount of other Owner’s costs not associated with the delay is $12.9 million.
C.    REVISED CAPITAL COST SCHEDULES
92.    Exhibit 2 attached to this filing provides the Commission with an updated capital cost schedule for the Units.

24


                        


93.    As set forth in Exhibit 2, the revised capital cost schedule reflects a cost in 2007 dollars of the Units of $5.2 billion, which reflects an increase of approximately $698 million in the costs approved in Order No. 2012-884.
94.    For ease of reference, Exhibit 3 provides information showing the variation between the capital cost schedule approved by the Commission in Order No. 2012-884 and the capital cost schedule contained in Exhibit 2.
95.    The updated capital cost schedule set forth in Exhibit 2 also reflects the most current inflation indices applied as mandated by the Commission in Order No. 2009-104(A). The updated capital cost schedule in future dollars, including Allowance for Funds Used During Construction, is approximately $6.8 billion which is approximately $1.1 billion more than the similar forecast of costs and escalation reflected in Order No. 2012-884.
96.    Exhibit 4 provides a summary reconciliation of the changes in forecasted costs shown on Exhibit 2 to those approved in Order No. 2012-884. Also shown is a comparison of the escalation indices in effect under Order No. 2012-884 to those currently in effect.

D.    CONCLUSION AS TO UPDATED CONSTRUCTION AND CAPITAL COST SCHEDULES

97.    Pursuant to S.C. Code Ann. § 58-33-270(E), when a utility petitions for adjustments in the construction schedule or capital cost schedule for a project being constructed under the BLRA, the Commission “shall grant the relief requested if, after a hearing, the commission finds: (1) as to the changes in the schedules, estimates, findings,

25


                        


or conditions, that the evidence of record justifies a finding that the changes are not the result of imprudence on the part of the utility . . . .”
98.    SCE&G’s actions associated with the changes in the construction schedule and capital costs reflected in Exhibit 1 and Exhibit 2 have been reasonable and prudent.
99.    The capital cost schedule contained in Exhibit 2 contains no contingencies or other provisions for the additional capital costs that may be identified to specific items of cost in the future as construction of the Units proceeds. For that reason, SCE&G reserves the right to update this schedule during the pendency of this proceeding as cost forecasts are updated and supplemented.
100.    SCE&G will continue to monitor and evaluate the construction schedule and schedule of capital costs. To the extent future revisions or updating of Exhibit 1 or Exhibit 2 or other revisions under S.C. Code Ann. § 58-33-270(E) are required, SCE&G will propose such changes for review by the Commission, either through updating Exhibit 1 and Exhibit 2 during this proceeding or through future filings and proceedings.
IV.REQUEST FOR RELIEF
WHEREFORE, South Carolina Electric & Gas Company respectfully requests that the Commission set the current matter for hearing and thereafter, pursuant to S.C. Code Ann. § 58-33-270(E),
A.
Approve the updated construction schedule attached as Exhibit 1, and the updated capital cost schedule attached as Exhibit 2, as they may be amended during the

26


                        


pendency of this proceeding, to be the operative schedules for construction of the Units under S.C. Code Ann. § 58-33-275(A).
B.
Grant other relief as may be appropriate.


Respectfully submitted,

_______________________________
K. Chad Burgess
Matthew W. Gissendanner
South Carolina Electric & Gas Company
Mail Code C222
220 Operation Way
Cayce, SC 29033
(803) 217-8141
chad.burgess@scana.com
matthew.gissendanner@scana.com

Belton T. Zeigler
Pope Zeigler, LLC
P.O. Box 11509
Columbia, SC 29211
(803) 354-4949
bzeigler@popezeigler.com


Attorneys for South Carolina Electric & Gas Company

Cayce, South Carolina
March 12, 2015






27


                        


LIST OF EXHIBITS
EXHIBIT 1 –
An updated milestone schedule for the Units.
EXHIBIT 2 –
An updated capital cost schedule for the Units, which if approved, will replace Exhibit F of the original Combined Application for a Certificate of Environmental Compatibility and Public Convenience and Necessity and for a Base Load Review Order for the Construction and Operation of a Nuclear Facility in Jenkinsville, South Carolina, as approved in Order No. 2009-104(A) and as updated in Order Nos. 2010-12, 2011-345, and 2012-884.
EXHIBIT 3 –
A schedule showing the variation between the capital cost schedule approved by the Commission in Order No. 2012-884 and the capital cost schedule contained in Exhibit 2.
EXHIBIT 4 –
A schedule showing the reconciliation of the gross construction dollars shown in Exhibit 2 to those approved by the Commission in Order No. 2012-884. Also shown is a comparison of the escalation indices in effect under Order No. 2012-884 to those currently in effect.





28


                        


 
Exhibit 1 Page 1 of 3
 
 
 
Tracking
ID
Order No. 2012-884 Description
Order No.
2012-884 Date
Revised Completion
Date
Unit

 
 
 
 
 
1
Approve Engineering Procurement and Construction Agreement
Complete
Complete
 
2
Issue POs to nuclear component fabricators for Units 2 & 3 Containment Vessels
Complete
Complete
 
3
Contractor Issue PO to Passive Residual Heat Removal Heat Exchanger Fabricator - First Payment - Unit 2
Complete
Complete
 
4
Contractor Issue PO to Accumulator Tank Fabricator - Unit 2
Complete
Complete
 
5
Contractor Issue PO to Core Makeup Tank Fabricator - Units 2 & 3
Complete
Complete
 
6
Contractor Issue PO to Squib Valve Fabricator - Units 2 & 3
Complete
Complete
 
7
Contractor Issue PO to Steam Generator Fabricator - Units 2 & 3
Complete
Complete
 
8
Contractor Issue Long Lead Material PO to Reactor Coolant Pump Fabricator - Units 2 & 3
Complete
Complete
 
9
Contractor Issue PO to Pressurizer Fabricator - Units 2 & 3
Complete
Complete
 
10
Contractor Issue PO to Reactor Coolant Loop Pipe Fabricator - First Payment - Units 2 & 3
Complete
Complete
 
11
Reactor Vessel Internals - Issue Long Lead Material PO to Fabricator - Units 2 & 3
Complete
Complete
 
12
Contractor Issue Long Lead Material PO to Reactor Vessel Fabricator - Units 2 & 3
Complete
Complete
 
13
Contractor Issue PO to Integrated Head Package Fabricator - Units 2 & 3
Complete
Complete
 
14
Control Rod Drive Mechanism Issue PO for Long Lead Material to Fabricator - Units 2 & 3 - first payment
Complete
Complete
 
15
Issue POs to nuclear component fabricators for Nuclear Island structural CA20 Modules
Complete
Complete
 
16
Start Site Specific and balance of plant detailed design
Complete
Complete
 
17
Instrumentation & Control Simulator - Contractor Place Notice to Proceed - Units 2 & 3
Complete
Complete
 
18
Steam Generator - Issue Final PO to Fabricator for Units 2 & 3
Complete
Complete
 
19
Reactor Vessel Internals - Contractor Issue PO for Long Lead Material (Heavy Plate and Heavy Forgings) to Fabricator - Units 2 & 3
Complete
Complete
 
20
Contractor Issue Final PO to Reactor Vessel Fabricator - Units 2 & 3
Complete
Complete
 
21
Variable Frequency Drive Fabricator Issue Transformer PO - Units 2 & 3
Complete
Complete
 
22
Start clearing, grubbing and grading
Complete
Complete
 
23
Core Makeup Tank Fabricator Issue Long Lead Material PO - Units 2 & 3
Complete
Complete
 
24
Accumulator Tank Fabricator Issue Long Lead Material PO - Units 2 & 3
Complete
Complete
 
25
Pressurizer Fabricator Issue Long Lead Material PO - Units 2 & 3
Complete
Complete
 
26
Reactor Coolant Loop Pipe - Contractor Issue PO to Fabricator - Second Payment - Units 2 & 3
Complete
Complete
 
27
Integrated Head Package - Issue PO to Fabricator - Units 2 and 3 - second payment
Complete
Complete
 
28
Control Rod Drive Mechanisms - Contractor Issue PO for Long Lead Material to Fabricator - Units 2 & 3
Complete
Complete
 
29
Contractor Issue PO to Passive Residual Heat Removal Heat Exchanger Fabricator - Second Payment - Units 2 & 3
Complete
Complete
 
30
Start Parr Road intersection work
Complete
Complete
 
31
Reactor Coolant Pump - Issue Final PO to Fabricator - Units 2 & 3
Complete
Complete
 
32
Integrated Heat Packages Fabricator Issue Long Lead Material PO - Units 2 & 3
Complete
Complete
 
33
Design Finalization Payment 3
Complete
Complete
 
34
Start site development
Complete
Complete
 
35
Contractor Issue PO to Turbine Generator Fabricator - Units 2 & 3
Complete
Complete
 
36
Contractor Issue PO to Main Transformers Fabricator - Units 2 & 3
Complete
Complete
 
37
Core Makeup Tank Fabricator Notice to Contractor Receipt of Long Lead Material - Units 2 & 3
Complete
Complete
 
38
Design Finalization Payment 4
Complete
Complete
 
39
Turbine Generator Fabricator Issue PO for Condenser Material - Unit 2
Complete
Complete
 
40
Reactor Coolant Pump Fabricator Issue Long Lead Material Lot 2 - Units 2 & 3
Complete
Complete
 
41
Passive Residual Heat Removal Heat Exchanger Fabricator Receipt of Long Lead Material - Units 2 & 3
Complete
Complete
 
42
Design Finalization Payment 5
Complete
Complete
 
43
Start erection of construction buildings, to include craft facilities for personnel, tools, equipment; first aid facilities; field offices for site management and support personnel; temporary warehouses; and construction hiring office
Complete
Complete
 
44
Reactor Vessel Fabricator Notice to Contractor of Receipt of Flange Nozzle Shell Forging - Unit 2
Complete
Complete
 
45
Design Finalization Payment 6
Complete
Complete
 
46
Instrumentation and Control Simulator - Contractor Issue PO to Subcontractor for Radiation Monitor System - Units 2 & 3
Complete
Complete
 
47
Reactor Vessel Internals - Fabricator Start Fit and Welding of Core Shroud Assembly - Unit 2
Complete
Complete
 
48
Turbine Generator Fabricator Issue PO for Moisture Separator Reheater/Feedwater Heater Material - Unit 2
Complete
Complete
 
49
Reactor Coolant Loop Pipe Fabricator Acceptance of Raw Material - Unit 2
Complete
Complete
 
South Carolina Electric & Gas Company

29


                        


 
Exhibit 1 Page 2 of 3
 
 
 
Tracking
ID
Order No. 2012-884 Description
Order No.
2012-884 Date
Revised Completion
Date
Unit

 
 
 
 
 
50
Reactor Vessel Internals - Fabricator Start Weld Neutron Shield Spacer Pads to Assembly - Unit 2
Complete
Complete
 
51
Control Rod Drive Mechanisms - Fabricator to Start Procurement of Long Lead Material - Unit 2
Complete
Complete
 
52
Contractor Notified that Pressurizer Fabricator Performed Cladding on Bottom Head - Unit 2
Complete
Complete
 
53
Start excavation and foundation work for the standard plant for Unit 2
Complete
Complete
 
54
Steam Generator Fabricator Notice to Contractor of Receipt of 2nd Steam Generator Tubesheet Forging - Unit 2
Complete
Complete
 
55
Reactor Vessel Fabricator Notice to Contractor of Outlet Nozzle Welding to Flange Nozzle Shell Completion - Unit 2
Complete
Complete
 
56
Turbine Generator Fabricator Notice to Contractor Condenser Fabrication Started - Unit 2
Complete
Complete
 
57
Complete preparations for receiving the first module on site for Unit 2
Complete
Complete
 
58
Steam Generator Fabricator Notice to Contractor of Receipt of 1st Steam Generator Transition Cone Forging - Unit 2
Complete
Complete
 
59
Reactor Coolant Pump Fabricator Notice to Contractor of Manufacturing of Casing Completion - Unit 2
Complete
Complete
 
60
Reactor Coolant Loop Pipe Fabricator Notice to Contractor of Machining, Heat Treating & Non-Destructive Testing Completion - Unit 2
Complete
Complete
 
61
Core Makeup Tank Fabricator Notice to Contractor of Satisfactory Completion of Hydrotest - Unit 2
Complete
Complete
 
62
Polar Crane Fabricator Issue PO for Main Hoist Drum and Wire Rope - Units 2 & 3
Complete
Complete
 
63
Control Rod Drive Mechanisms - Fabricator to Start Procurement of Long Lead Material - Unit 3
Complete
Complete
 
64
Turbine Generator Fabricator Notice to Contractor Condenser Ready to Ship - Unit 2
Complete
Complete
 
65
Start placement of mud mat for Unit 2
Complete
Complete
 
66
Steam Generator Fabricator Notice to Contractor of Receipt of 1st Steam Generator Tubing - Unit 2
Complete
Complete
 
67
Pressurizer Fabricator Notice to Contractor of Welding of Upper and Intermediate Shells Completion - Unit 2
Complete
Complete
 
68
Reactor Vessel Fabricator Notice to Contractor of Closure Head Cladding Completion - Unit 3
Complete
Complete
 
69
Begin Unit 2 first nuclear concrete placement
Complete
Complete
 
70
Reactor Coolant Pump Fabricator Notice to Contractor of Stator Core Completion - Unit 2
Complete
Complete
 
71
Fabricator Start Fit and Welding of Core Shroud Assembly - Unit 2
Complete
Complete
 
72
Steam Generator Fabricator Notice to Contractor of Completion of 1st Steam Generator Tubing Installation - Unit 2
Complete
Complete
 
73
Reactor Coolant Loop Pipe - Shipment of Equipment to Site - Unit 2
Complete
Complete
 
74
Control Rod Drive Mechanism - Ship Remainder of Equipment (Latch Assembly & Rod Travel Housing) to Head Supplier - Unit 2
Complete
Complete
 
75
Pressurizer Fabricator Notice to Contractor of Welding of Lower Shell to Bottom Head Completion - Unit 2
Complete
Complete
 
76
Steam Generator Fabricator Notice to Contractor of Completion of 2nd Steam Generator Tubing Installation - Unit 2
Complete
Complete
 
77
Design Finalization Payment 14
Complete
Complete
 
78
Set module CA04 for Unit 2
Complete
Complete
 
79
Passive Residual Heat Removal Heat Exchanger Fabricator Notice to Contractor of Final Post Weld Heat Treatment - Unit 2
Complete
Complete
 
80
Passive Residual Heat Removal Heat Exchanger Fabricator Notice to Contractor of Completion of Tubing - Unit 2
Complete
Complete
 
81
Polar Crane Fabricator Notice to Contractor of Girder Fabrication Completion - Unit 2
Complete
Complete
 
82
Turbine Generator Fabricator Notice to Contractor Condenser Ready to Ship - Unit 3
Complete
Complete
 
83
Set Containment Vessel ring #1 for Unit 2
Complete
Complete
 
84
Reactor Coolant Pump Fabricator Delivery of Casings to Port of Export - Unit 2
Complete
Complete
 
85
Reactor Coolant Pump Fabricator Notice to Contractor of Stator Core Completion - Unit 3
Complete
Complete
 
86
Reactor Vessel Fabricator Notice to Contractor of Receipt of Core Shell Forging - Unit 3
Complete
Complete
 
87
Contractor Notified that Pressurizer Fabricator Performed Cladding on Bottom Head - Unit 3
Complete
Complete
 
88
Set Nuclear Island structural module CA03 for Unit 2
6/26/2013
12/28/2015
Unit 2
89
Squib Valve Fabricator Notice to Contractor of Completion of Assembly and Test for Squib Valve Hardware - Unit 2
Complete
Complete
 
90
Accumulator Tank Fabricator Notice to Contractor of Satisfactory Completion of Hydrotest - Unit 3
Complete
Complete
 
91
Polar Crane Fabricator Notice to Contractor of Electric Panel Assembly Completion - Unit 2
Complete
Complete
 
92
Start containment large bore pipe supports for Unit 2
Complete
Complete
 
93
Integrated Head Package - Shipment of Equipment to Site - Unit 2
Complete
Complete
 
94
Reactor Coolant Pump Fabricator Notice to Contractor of Final Stator Assembly Completion - Unit 2
Complete
Complete
 
95
Steam Generator Fabricator Notice to Contractor of Completion of 2nd Steam Generator Tubing Installation - Unit 3
Complete
Complete
 
96
Steam Generator Fabricator Notice to Contractor of Satisfactory Completion of 1st Steam Generator Hydrotest - Unit 2
Complete
Complete
 
97
Start concrete fill of Nuclear Island structural modules CA01 and CA02 for Unit 2
4/3/2014
7/18/2016
Unit 2
98
Passive Residual Heat Removal Heat Exchanger - Delivery of Equipment to Port of Entry - Unit 2
Complete
Complete
 
99
Refueling Machine Fabricator Notice to Contractor of Satisfactory Completion of Factory Acceptance Test - Unit 2
Complete
Complete
 
South Carolina Electric & Gas Company

30


                        


 
Exhibit 1 Page 3 of 3
 
 
 
Tracking
ID
Order No. 2012-884 Description
Order No.
2012-884 Date
Revised Completion
Date
Unit
 
 
 
 
 
100
Deliver Reactor Vessel Internals to Port of Export - Unit 2
1/31/2014
7/30/2015
Unit 2
101
Set Unit 2 Containment Vessel #3
4/24/2014
8/23/2016
Unit 2
102
Steam Generator - Contractor Acceptance of Equipment at Port of Entry - Unit 2
Complete
Complete
 
103
Turbine Generator Fabricator Notice to Contractor Turbine Generator Ready to Ship - Unit 2
Complete
Complete
 
104
Pressurizer Fabricator Notice to Contractor of Satisfactory Completion of Hydrotest - Unit 3
3/31/2014
3/28/2015
Unit 3
105
Polar Crane - Shipment of Equipment to Site - Unit 2
1/31/2014
12/31/2015
Unit 2
106
Receive Unit 2 Reactor Vessel on site from fabricator
Complete
Complete
 
107
Set Unit 2 Reactor Vessel
6/23/2014
8/9/2016
Unit 2
108
Steam Generator Fabricator Notice to Contractor of Completion of 2nd Channel Head to Tubesheet Assembly Welding - Unit 3
12/31/2013
3/30/2015
Unit 3
109
Reactor Coolant Pump Fabricator Notice to Contractor of Final Stator Assembly Completion - Unit 3
8/31/2014
10/30/2015
Unit 3
110
Reactor Coolant Pump - Shipment of Equipment to Site (2 Reactor Coolant Pumps) - Unit 2
10/31/2013
5/30/2016
Unit 2
111
Place first nuclear concrete for Unit 3
Complete
Complete
 
112
Set Unit 2 Steam Generator
10/23/2014
10/10/2016
Unit 2
113
Main Transformers Ready to Ship - Unit 2
Complete
Complete
 
114
Complete Unit 3 Steam Generator Hydrotest at fabricator
2/28/2014
7/30/2015
Unit 3
115
Set Unit 2 Containment Vessel Bottom Head on basemat legs
Complete
Complete
 
116
Set Unit 2 Pressurizer Vessel
5/16/2014
8/23/2016
Unit 2
117
Reactor Coolant Pump Fabricator Notice to Contractor of Satisfactory Completion of Factory Acceptance Test - Unit 3
2/28/2015
1/31/2017
Unit 3
118
Deliver Reactor Vessel Internals to Port of Export - Unit 3
6/30/2015
12/31/2016
Unit 3
119
Main Transformers Fabricator Issue PO for Material - Unit 3
Complete
Complete
 
120
Complete welding of Unit 2 Passive Residual Heat Removal System piping
2/5/2015
1/16/2017
Unit 2
121
Steam Generator - Contractor Acceptance of Equipment at Port of Entry - Unit 3
4/30/2015
1/30/2016
Unit 3
122
Refueling Machine - Shipment of Equipment to Site - Unit 3
2/28/2015
3/27/2016
Unit 3
123
Set Unit 2 Polar Crane
1/9/2015
12/19/2016
Unit 2
124
Reactor Coolant Pumps - Shipment of Equipment to Site - Unit 3
6/30/2015
4/30/2017
Unit 3
125
Main Transformers Ready to Ship - Unit 3
7/31/2015
12/30/2015
Unit 3
126
Spent Fuel Storage Rack - Shipment of Last Rack Module - Unit 3
7/31/2014
5/31/2015
Unit 3
127
Start electrical cable pulling in Unit 2 Auxiliary Building
8/14/2013
11/29/2016
Unit 2
128
Complete Unit 2 Reactor Coolant System cold hydro
1/22/2016
2/19/2018
Unit 2
129
Activate class 1E DC power in Unit 2 Auxiliary Building
3/15/2015
6/22/2017
Unit 2
130
Complete Unit 2 hot functional test
5/3/2016
5/23/2018
Unit 2
131
Install Unit 3 ring 3 for containment vessel
8/25/2015
2/27/2017
Unit 3
132
Load Unit 2 nuclear fuel
9/15/2016
12/21/2018
Unit 2
133
Unit 2 Substantial Completion
3/15/2017
6/19/2019
Unit 2
134
Set Unit 3 Reactor Vessel
10/22/2015
5/26/2017
Unit 3
135
Set Unit 3 Steam Generator #2
2/25/2016
9/22/2017
Unit 3
136
Set Unit 3 Pressurizer Vessel
7/16/2015
11/27/2017
Unit 3
137
Complete welding of Unit 3 Passive Residual Heat Removal System piping
6/16/2016
1/29/2018
Unit 3
138
Set Unit 3 polar crane
5/9/2016
12/18/2017
Unit 3
139
Start Unit 3 Shield Building roof slab rebar placement
5/26/2016
5/11/2018
Unit 3
140
Start Unit 3 Auxiliary Building electrical cable pulling
11/7/2014
6/23/2017
Unit 3
141
Activate Unit 3 Auxiliary Building class 1E DC power
5/15/2016
3/13/2018
Unit 3
142
Complete Unit 3 Reactor Coolant System cold hydro
3/22/2017
2/26/2019
Unit 3
143
Complete Unit 3 hot functional test
7/3/2017
5/26/2019
Unit 3
144
Complete Unit 3 nuclear fuel load
11/15/2017
12/19/2019
Unit 3
145
Begin Unit 3 full power operation
4/8/2018
5/20/2020
Unit 3
146
Unit 3 Substantial Completion
5/15/2018
6/16/2020
Unit 3
 
South Carolina Electric & Gas Company


31


                        


Exhibit 2

RESTATED and UPDATED CONSTRUCTION EXPENDITURES
(Thousands of $)

V.C. Summer Units 2 and 3 - Summary of SCE&G Capital Cost Components


Actual through December 2014* plus
Projected
 
 
Actual
Projected
Plant Cost Categories    
Total
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
Fixed with No Adjustment
 
 
Firm with Fixed Adjustment A
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Firm with Fixed Adjustment B
 
 
 
 
 
 
CONFIDENTIAL
 
 
 
 
 
Firm with Indexed Adjustment
 
 
 
 
 
 
 
 
 
 
 
Actual Craft Wages
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Non-Labor Costs
 
 
Time & Materials

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Owners Costs

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Transmission Costs

329,512


26

724

927

11,964

51,677

56,593

47,207

64,576

64,794

30,314

710



Total Base Project Costs(2007 $)
5,246,638

21,723

97,386

319,073

374,810

314,977

488,461

448,947

422,076

742,980

759,311

658,948

389,817

169,840

38,289

Total Project Escalation
1,300,486


3,519

20,930

23,741

34,084

74,485

88,622

89,890

196,694

247,926

240,312

151,548

92,670

36,065

Total Revised Project Cash Flow
6,547,124

21,723

100,905

340,003

398,551

349,061

562,946

537,569

511,966

939,674

1,007,237

899,260

541,365

262,510

74,354

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Cumulative Project Cash Flow(Revised)
 
21,723

122,629

462,632

861,183

1,210,244

1,773,190

2,310,759

2,822,725

3,762,398

4,769,635

5,668,895

6,210,260

6,472,770

6,547,124

AFUDC(Capitalized Interest)
279,790
645
3,497
10,564
17,150
14,218
18,941
27,722
26,131
30,502
44,426
39,884
30,984
11,529
3,599
Gross Construction
6,826,914
22,368
104,403
350,567
415,701
363,278
581,886
565,291
538,097
970,176
1,051,663
939,143
572,349
274,039
77,953
Construction Work in Progress
 
22,368
126,771
477,338
893,039
1,256,317
1,838,203
2,403,495
2,941,591
3,911,767
4,963,430
5,902,573
6,474,923
6,748,962
6,826,914

*Applicable index escalation rates for 2014 are estimated. Escalation is subject to restatement when actual indices for 2014 are final.

Notes:
Current Period AFUDC rate applied    5.68%

Escalation rates vary from reporting period to reporting period according to the terms of Commission Order 2009-104(A).
These projections reflect current escalation rates. Future changes in escalation rates could substatially change these projections. The AFUDC rate applied is the current SCE&G rate. AFUDC rates can vary with changes in market interest rates,
SCE&G's embedded cost of capital, capitalization ratios, construction work in process, and SCE&G's short-term debt outstanding.



32


                        


 
Exhibit 3
 
Change from SCPSC Order 2012-884
 
 
 
 
 
(Thousands of $)
 
V.C. Summer Units 2 and 3 - Summary of SCE&G Capital Cost Components
 
 
 
 
 
Actual through December 2014* plus Projected
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Actual
Projected
 
Plant Cost Categories
Total
2,007
2,008
2,009
2,010
2,011
2,012
2,013
2,014
2,015
2,016
2,017
2,018
2,019
2,020
 
Fixed with No Adjustment
(85,360
)





(14,226
)
(23,624
)
(12,485
)
20,064

20,823

9,558

56

(42,763
)
(42,763
)
 
Firm with Fixed Adjustment A






12,925

(12,925
)







 
Firm with Fixed Adjustment B
52,971






(1,580
)
(15,028
)
(31,967
)
20,877

25,935

7,721

22,137

19,537

5,339

 
Firm with Indexed Adjustment
17,998






(90,039
)
(172,221
)
(109,468
)
84,056

124,876

82,924

19,196

51,832

26,842

 
Actual Craft Wages
198,626






(19,028
)
(38,621
)
(71,553
)
(18,150
)
71,542

156,910

94,873

22,652


 
Non-Labor Costs
288,327






16,149

(24,678
)
(61,982
)
(8,616
)
91,813

157,787

94,851

22,781

223

 
Time & Materials
(19,425
)





(846
)
(16,941
)
(30,076
)
(10,297
)
11,288

16,393

8,535

2,384

136

 
Owners Costs
245,096






(23,042
)
(27,458
)
(42,485
)
21,164

26,430

55,879

92,679

93,417

48,512

 
Transmission Costs






(5,529
)
(310
)
(10,301
)
(13,414
)
67

28,777

710



 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Total Base Project Costs(2007 $)
698,233






(125,217
)
(331,806
)
(370,318
)
95,685

372,774

515,949

333,037

169,840

38,289

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Total Project Escalation
332,042






(25,145
)
(80,804
)
(125,285
)
12,708

113,112

181,903

126,818

92,670

36,065

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Total Revised Project Cash Flow
1,030,275






(150,362
)
(412,609
)
(495,603
)
108,393

485,885

697,852

459,855

262,510

74,354

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Cumulative Project Cash Flow(Revised)
 





(150,362
)
(562,971
)
(1,058,574
)
(950,181
)
(464,296
)
233,556

693,410

955,921

1,030,275

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
AFUDC(Capitalized Interest)
42,075






(1,509
)
(10,663
)
(16,737
)
(10,386
)
16,907

24,493

24,841

11,529

3,599

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Gross Construction
1,072,349






(151,870
)
(423,272
)
(512,340
)
98,007

502,793

722,345

484,696

274,039

77,953

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Construction Work in Progress
 





(151,870
)
(575,142
)
(1,087,482
)
(989,476
)
(486,683
)
235,662

720,358

994,397

1,072,349

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
*Applicable index escalation rates for 2014 are estimated. Escalation is subject to restatement when actual indices for 2014 are final.
 
 
 
 
 
 
 
These projections reflect current escalation rates. Future changes in escalation rates could substatially change these projections.
 
 
 
 
 
 
 

33


                        


Exhibit 4


RECONCILIATION TO ORDER No. 2012-884 AND BLRA INDICES COMPARISON


RECONCILIATION TO ORDER No. 2012-884(Thousands of $)

Revised Forecast Current Filing
$ 6,826,914
Forecast Order No. 2012-884
$ 5,754,565
                                      Change
$ 1,072,349

Reconciliation:
 
Change in Base Project Costs(2007 $)
$ 698,233
Change in Project Escalation
$ 332,042
Change in AFUDC
$ 42,075
Net
$ 1,072,349

BLRA ESCALATION INDICES COMPARISON

BLRA Indices
Order No. 2012-884
 
Jul 2014 Update
 
Escalation Rates
Escalation Rates
HW All Steam Index:
 
 
One Year Rate
4.51%
2.52%
Five Year Average
3.91%
3.21%
Ten Year Average
4.71%
4.35%
HW All Steam/Nuclear Index:
 
 
One Year Rate
4.52%
2.52%
Five Year Average
3.87%
3.21%
Ten Year Average
4.72%
4.38%
HW All Transmission Plant Index:
 
 
One Year Rate
2.48%
1.68%
Five Year Average
3.00%
2.63%
Ten Year Average
4.55%
4.05%
GDP Chained Price Index:
 
 
One Year Rate
2.11%
1.55%
Five Year Average
1.69%
1.55%


34