BEFORE THE PUBLIC UTILITIES COMMISSION
OF THE STATE OF CALIFORNIA


Order Instituting Investigation on the Commission’s Own Motion into the Rates, Operations, Practices, Services and Facilities of Southern California Edison Company and San Diego Gas and Electric Company Associated with the San Onofre Nuclear Generating Station Units 2 and 3.

Investigation 12-10-013
(Filed October 25, 2012)

And Related Matters.

Application 13-01-016
Application 13-03-005
Application 13-03-013
Application 13-03-014




JOINT RESPONSE OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E), SAN DIEGO GAS & ELECTRIC COMPANY (U 902-E), THE UTILITY REFORM NETWORK, THE OFFICE OF RATEPAYER ADVOCATES, FRIENDS OF THE EARTH, AND THE COALITION OF CALIFORNIA UTILITY EMPLOYEES TO ASSIGNED COMMISSIONER AND ADMINISTRATIVE LAW JUDGES’ RULING




J. ERIC ISKEN

WALKER A. MATTHEWS, III

RUSSELL A. ARCHER

Southern California Edison Company

2244 Walnut Grove Avenue
Post Office Box 800
Rosemead, CA  91770

Telephone:

(626) 302-6879

Facsimile:

(626) 302-3990

E-mail:

Walker.matthews@sce.com

HENRY WEISSMANN

EMILY B. VIGLIETTA
Munger, Tolles & Olson LLP

355 South Grand Avenue, 35th Floor
Los Angeles, CA  90071
Telephone:

(213) 683-9150
Facsimile:

(213) 683-5150
E-mail:

 Henry.Weissmann@mto.com

Attorneys for
SOUTHERN CALIFORNIA EDISON COMPANY




EMMA D. SALUSTRO

Attorney for

SAN DIEGO GAS & ELECTRIC COMPANY

101 Ash Street

San Diego, CA  92101-3017

Telephone: (619) 696-4328

Facsimile: (619) 699-5027

E-mail: esalustro@semprautilities.com




MATTHEW FREEDMAN

Attorney for

THE UTILITY REFORM NETWORK

785 Market Street, 14th floor

San Francisco, CA  94103

Telephone: (415) 929-8876 x304

E-mail:  matthew@turn.org


GREGORY HEIDEN

Attorney for

OFFICE OF RATEPAYER ADVOCATES

California Public Utilities Commission

505 Van Ness Avenue

San Francisco, CA  94102

Telephone: (415) 355-5539

Facsimile: (415) 703-2262

E-mail: gregory.heiden@cpuc.ca.gov


LAURENCE G. CHASET

Attorney for FRIENDS OF THE EARTH

Keyes, Fox & Wiedman LLP

436 14th Street, Suite 1305

Oakland, CA  94612

Telephone: (510) 314-8386

Facsimile: (510) 225-3848

E-mail: lchaset@keyesandfox.com




JAMIE L. MAULDIN

Attorney for COALITION OF CALIFORNIA UTILITY EMPLOYEES

Adams Broadwell Joseph & Cardozo

601 Gateway Boulevard, Suite 1000

South San Francisco, CA  94080

Telephone: (650) 589-1660

Facsimile: (650) 589-5062

E-mail: jmauldin@adamsbroadwell.com





Dated: September 19, 2014





Pursuant to the September 5, 2014 “Assigned Commissioner and Administrative Law Judges’ Ruling Requesting Settling Parties to Adopt Modifications to Proposed Settlement Agreement” (“Ruling”), Southern California Edison Company (“SCE”), San Diego Gas & Electric Company (“SDG&E”), the Office of Ratepayer Advocates (“ORA”),1 The Utility Reform Network (“TURN”), Friends of the Earth (“FOE”), and the Coalition of California Utility Employees (“CUE”) (collectively, the “Settling Parties”) jointly submit this Response.  

The Settling Parties have previously explained why the Settlement Agreement, as submitted to the California Public Utilities Commission (“Commission”) on April 3, 2014, meets the criteria of Rule 12.1(d) of the Commission’s Rules of Practice and Procedure.  Given the careful balancing of the relevant interests reflected in that agreement, the Settling Parties continue to adhere to that view.  

The Settling Parties also believe, however, that the public interest will best be served by expeditiously resolving this proceeding and ensuring that the benefits flow to ratepayers as soon as possible.  Accordingly, the Settling Parties accept all of the modifications and clarifications to the Settlement Agreement proposed by the Ruling.

The Settling Parties will submit an amendment to the Settlement Agreement on or before September 24, 2014 to implement the Ruling and certain other non-substantive adjustments to the Settlement Agreement.  The Settling Parties ask the Commission to approve the amended Settlement Agreement promptly.






1 Although ORA was known as the Division of Ratepayer Advocates for most of this proceeding, this Response refers to it as “ORA” throughout.  






Respectfully Submitted,


J. ERIC ISKEN

WALKER A. MATTHEWS

RUSSELL A. ARCHER

HENRY WEISSMANN

EMILY B. VIGLIETTA


/s/ Henry Weissmann

By:

Henry Weissmann


Attorneys for

SOUTHERN CALIFORNIA EDISON COMPANY

Date:

September 19, 2014

 

 

MATTHEW FREEDMAN

/s/ Matthew Freedman


Attorney for
THE UTILITY REFORM NETWORK

Date:

September 19, 2014

 

 

GREGORY HEIDEN

/s/ Gregory Heiden


Attorney for
OFFICE OF RATEPAYER ADVOCATES

Date:

September 19, 2014

 

 

EMMA D. SALUSTRO

/s/ Emma D. Salustro

By:

Emma D. Salustro

Attorney for
SAN DIEGO GAS & ELECTRIC COMPANY

Date:

September 19, 2014

 

 

LAURENCE G. CHASET

/s/ Laurence G. Chaset

By:

Laurence G. Chaset

Attorney for
FRIENDS OF THE EARTH

Date:

September 19, 2014

 

 

JAMIE L. MAULDIN

/s/ Jamie L. Mauldin

By:

Jamie L. Mauldin

Attorney for
COALITION OF CALIFORNIA UTILITY EMPLOYEES

Date:

September 19, 2014