January 1, 2011
To: Amerilithium Corp.
Attn: Matthew Worrall, President
Robert Allender, Geologist, Exploration Manager
Budget, Phase 1 Drill Program, Paymaster Property, Nevada
Phase 1 Three holes
Sub Contracting*:
Skytech Drilling, Inc; Mobilization-demobilization $9,000.00
To include; Drill truck, pipe truck, water truck,
mud cleaning system, Dog house, 2 pick-ups,
consumables, room and board
Mud Pit construction; $5,000/pit x 3 pits $15,000.00
Drill Costs/hole; $23,000 x 3 holes $69,000.00
Reclamation of drill sites; $15,000.00
Analytical and sampling costs; $10,000.00
-----------
Total: $118,000.00
GeoXplor Corp Support:
On Site Geologist: $0 (supplied by AMEL)
Truck: $0 (supplied by AMEL)
Gas: $0 (supplied by AMEL)
Equip & Supplies: $1,000
John Rud x 6 days $5,400
Mob-Demob; $3,000
Total $127,400.00
Disbursements@10% $11,800.00
Admin @ 12.5% $15,925.00
-----------
Grand Total $155,125.00
Signed: /s/ Clive Ashworth Date: Feb 1/11
-----------------------
Clive Ashworth, GeoXplor Corp.
Signed: /s/Matthew Worrall Date: Feb 17, 2011
-------------------
Matthew Worrall, AmeriLithium Corp