Back to GetFilings.com



 

UNITED STATES SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

 


 

FORM 10-K

 

(Mark One)

ý                                 ANNUAL REPORT PURSUANT TO SECTION 13 OR 15(D) OF THE SECURITIES EXCHANGE ACT OF 1934
For the fiscal year ended December 31, 2004

 

OR

 

o                                 TRANSITION REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934
For the transition period from               to               

 

Commission file number:  333-40478

 

AES RED OAK, L.L.C.

(Exact name of registrant as specified in its charter)

 

Delaware

 

54-1889658

(State of other jurisdiction of incorporation or organization)

 

(I.R.S. Employer Identification No.)

 

 

 

832 Red Oak Lane, Sayreville, NJ

 

08872

(Address of principal executive offices)

 

(Zip Code)

 

 

 

Registrant’s telephone number, including area code: (732) 238-1462

 

Securities Registered Pursuant To Section 12(b) of The Act: None

 

Securities Registered Pursuant To Section 12(g) of The Act: None

 


 

Indicate by check mark whether the Registrant (1) has filed all reports required to be filed by Section 13 or 15(d) of the Securities Exchange Act of 1934 during the preceding 12 months (or for such shorter period that the Registrant was required to file such reports) and (2) has been subject to such filing requirements for the past 90 days.     Yes   ý   No   o

 

Indicate by check mark if disclosure of delinquent filers pursuant to Item 405 of Regulation S-K is not contained herein, and will not be contained, to the best of Registrant’s knowledge, in definitive proxy or information statements incorporated by reference in Part III of this Form 10-K, or any amendment to this Form 10K.     ý

 

Indicate by check mark whether the Registrant is an accelerated filer (as defined in Rule 12b-2 of the Act).     Yes   o   No   ý

 

As of June 30, 2004, the last business day of the registrant’s most recently completed second fiscal quarter, and as of March 30, 2005, there was one membership interest in AES Red Oak, LLC outstanding, which was held by AES Red Oak, Inc., the Company’s parent and a wholly-owned subsidiary of The AES Corporation.

 

All of the Registrant’s equity securities are indirectly owned by The AES Corporation.  Registrant meets the conditions set forth in General Instruction I(1)(a) and (b) of Form 10-K and is therefore filing this Form 10-K with the reduced disclosure format authorized by General Instruction I of Form 10-K.

 

DOCUMENTS INCORPORATED BY REFERENCE

None

 

 



 

TABLE OF CONTENTS

 

CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS

 

PART I

 

 

ITEM 1.

BUSINESS

 

ITEM 2.

PROPERTIES

 

ITEM 3.

LEGAL PROCEEDINGS

 

ITEM 4.

SUBMISSION OF MATTERS TO A VOTE OF SECURITY HOLDERS

 

PART II

 

 

ITEM 5.

MARKET FOR REGISTRANT’S COMMON EQUITY AND RELATED STOCKHOLDER MATTERS

 

ITEM 6.

SELECTED FINANCIAL DATA

 

ITEM 7.

MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS

 

ITEM 7A.

QUANTITATIVE AND QUALITATIVE DISCLOSURE ABOUT MARKET RISK

 

ITEM 8.

FINANCIAL STATEMENTS AND SUPPLEMENTAL DATA

 

ITEM 9.

CHANGES IN AND DISAGREEMENTS WITH ACCOUNTANTS ON ACCOUNTING AND FINANCIAL DISCLOSURE

 

ITEM 9A.

CONTROLS AND PROCEDURES

 

PART III

 

 

ITEM 10.

DIRECTORS AND EXECUTIVE OFFICERS OF THE REGISTRANT

 

ITEM 11.

EXECUTIVE COMPENSATION

 

ITEM 12.

SECURITY OWNERSHIP OF CERTAIN BENEFICIAL OWNERS AND MANAGEMENT

 

ITEM 13.

CERTAIN RELATIONSHIPS AND RELATED TRANSACTIONS

 

ITEM 14.

PRINCIPAL ACCOUNTING FEES AND SERVICES

 

PART IV

 

 

ITEM 15.

EXHIBITS AND FINANCIAL STATEMENT SCHEDULES

 

SIGNATURES

 

 

1



 

CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS

 

Some of the statements in this Form 10-K, as well as statements made by AES Red Oak, L.L.C. (the “Company”, “we”, “us” or “our”) in periodic press releases and other public communications, constitute “forward-looking statements” within the meaning of the Private Securities Litigation Reform Act of 1995.  Certain, but not necessarily all, of such forward-looking statements can be identified by the use of forward-looking terminology, such as “believes,” “estimates,” “plans,” “projects,” “expects,” “may,” “will,” “should,” “approximately,” or “anticipates” or the negative thereof or other variations thereof or comparable terminology, or by discussion of strategies, each of which involves risks and uncertainties. The Company has based these forward-looking statements on its current expectations and projections about future events based upon its knowledge of facts as of the date of this Form 10-K and its assumptions about future events.

 

All statements other than of historical facts included herein, including those regarding market trends, the Company’s financial position, business strategy, projected plans and objectives of management for future operations of the facility, are forward-looking statements. Such forward-looking statements involve known and unknown risks, uncertainties and other factors outside of the Company’s control that may cause its actual results or performance to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. These risks, uncertainties and other factors include, among others, the following:

 

                  unexpected problems relating to the performance of the facility,

 

                  the financial condition of third parties on which the Company depends, including in particular, Williams Power Company, Inc., (“Williams Energy”), formerly Williams Energy Marketing & Trading Company, as fuel supplier under the Power Purchase Agreement entered into with Williams Energy for the sale of all electric energy and capacity produced by the facility, as well as ancillary and fuel conversion services (the “Power Purchase Agreement”), and The Williams Companies, Inc., as the guarantor of Williams Energy’s performance under the Power Purchase Agreement,

 

                  delays in, or disputes over, the final completion of the Company’s facility,

 

                  continued performance by Williams Energy (as guaranteed by The Williams Companies, Inc.) under the Power Purchase Agreement,

 

                  the ability of The Williams Companies, Inc. or its affiliates to avoid a default under the Power Purchase Agreement by continuing to maintain or provide adequate security to supplement their guaranty of Williams Energy’s performance under the Power Purchase Agreement,

 

                  our ability to find a replacement power purchaser on favorable or reasonable terms, if necessary,

 

                  an adequate merchant market after the expiration, or in the event of a termination, of the Power Purchase Agreement,

 

                  capital shortfalls and access to additional capital on reasonable terms, or in the event that the Power Purchase Agreement is terminated,

 

                  the possibility that Williams Energy will not request that the Company runs, or “dispatches” the facility as provided under the Power Purchase Agreement,

 

                  inadequate insurance coverage,

 

                  unexpected expenses or lower than expected revenues,

 

                  environmental and regulatory compliance,

 

                  terrorists acts and adverse reactions to United States anti-terrorism activities, and

 

                  additional factors that are unknown to the Company or beyond the Company’s control.

 

The Company has no obligation to publicly update or revise any forward-looking statement, whether as a result of new information, future events or otherwise.

 

2



 

PART I

 

ITEM 1.          BUSINESS

 

General

 

The Company is a Delaware limited liability company formed on September 13, 1998, to develop, construct, own, lease, operate and maintain a gas-fired electric generating power plant in the Borough of Sayreville, Middlesex County, New Jersey and manage the production of electric generating capacity, ancillary services and energy at the Company’s facility. The Company reached provisional acceptance on August 11, 2002, risk transfer on August 13, 2002, and took the position that the Company was commercially available on September 1, 2002.  Williams Energy disputed the September 1, 2002 commercial operation date and informed the Company that it recognized commercial availability of the facility as of September 28, 2002.  On November 4, 2003, a settlement was reached and a commercial operation date of September 28, 2002 was agreed upon.  See Item 3 “Legal Proceedings”.  Since the Company’s commercial operation date, its sole business is the ownership, leasing and operation of the project.

 

Our facility was initially designed, engineered, procured and constructed for the Company by Washington Group International, Inc. (“WGI”) (as the successor contractor) on a fixed-price, turnkey basis. On May 14, 2001, WGI filed a plan of reorganization along with voluntary petitions to restructure under Chapter 11 of the U.S. Bankruptcy Code in the U.S. Bankruptcy Court for the District of Nevada in Reno (the “Bankruptcy Court”). As a result of WGI’s bankruptcy filing, on June 20, 2001 the Company made a demand on the Raytheon Company (“Raytheon”) to perform its obligations under a guarantee which Raytheon had given the Company of WGI’s performance obligations under the construction agreement and Raytheon became responsible for the construction of the Company’s facility.  As discussed above, provisional acceptance has been granted and the facility has commenced commercial operations, however, Raytheon must perform certain agreed upon completion items in order to obtain final acceptance. Raytheon gave notice of Final Acceptance on July 22, 2003 based on its July 8, 2003 performance test.  On July 31, 2003, the Company received a letter from the project’s independent engineer stating that it could not support Raytheon’s claim of final acceptance and it did not consider the July 8, 2003 performance test valid.  In making this assessment, the independent engineer cited, among other reasons, (i) modifications made to certain equipment in performance of the July 8 performance test which would adversely impact the operations of the plant and other pieces of equipment and (ii) Raytheon’s failure to demonstrate compliance with guaranteed emissions limits.  On August 1, 2003, the Company rejected Raytheon’s claim of final acceptance.  This rejection was based upon Raytheon’s failure to meet the conditions for final acceptance provided for in the Engineering, Procurement and Construction Services Agreement (“EPC contract”). On August 7, 2003, the Company received a response from Raytheon in which Raytheon claims that the Company’s rejection of the final acceptance is invalid and improper.  The Company and Raytheon have filed complaints against each other.  See “Summary of Principal Agreements – Construction Agreement”.

 

Siemens Westinghouse Power Corporation provides combustion turbine maintenance services and spare parts with respect to the turbines for the Company’s facility under a maintenance services agreement for an initial term of 16 years from the date of execution of the agreement or after the twelfth scheduled outage for a turbine, whichever occurs first, unless the Company exercises its right to cancel the agreement after the first major outage of the turbines. The estimated timeframe for the completion of the first major outages is 2011.

 

The Company has entered into a Power Purchase Agreement for a term of 20 years under which Williams Energy has committed to purchase all of the net capacity, fuel conversion and ancillary services of its facility. Net capacity is the maximum amount of electricity generated by the Company’s facility net of electricity used at its facility. Fuel conversion services consist of the combustion of natural gas in order to generate electric energy. Ancillary services consist of services necessary to support the transmission of capacity and energy. Williams Energy is obligated to supply the Company with all natural gas necessary to provide net capacity, fuel conversion services and ancillary services under the Power Purchase Agreement. During the term of the Power Purchase Agreement, substantially all of the Company’s operating revenues will be derived from payments made under the Power Purchase Agreement. Under certain limited circumstances described herein, Williams Energy has the right to terminate the Power Purchase Agreement.

 

3



 

Organizational Structure

 

All of the equity interests in the Company are owned by AES Red Oak, Inc., a wholly owned subsidiary of The AES Corporation (“AES”). AES is a leading global power company, with 2004 sales of $9.5 billion. AES’s generating assets include interests in 120 facilities in 27 countries totaling approximately 44 gigawatts of capacity. Its 30,000 people are committed to operational excellence and meeting the world’s growing power needs Approximately 23% of AES’s revenues come from businesses in North America, 17% from the Caribbean, 41% from South America, 11% from Europe and Africa, and 8% from Asia.

 

AES Red Oak, Inc. currently has no operations outside of its activities in connection with its project and does not anticipate undertaking any unrelated operations. AES Red Oak, Inc. also owns all of the equity interests in AES Sayreville, L.L.C., (“AES Sayreville”) which provides development, construction management, and operations and maintenance services to us. AES Sayreville has no operations outside of its activities in connection with its operations. AES Red Oak, Inc. has no assets other than its membership interests in the Company and AES Sayreville. The AES Corporation supplies AES Sayreville with personnel and services necessary to carry out its obligations to us.

 

The Company also owns all of the equity interests in AES Red Oak Urban Renewal Corporation (“AES URC”), which was organized as an urban renewal corporation under New Jersey law so that portions of its project can be designated as redevelopment areas or projects in order to provide certain real estate tax and development benefits for its project. AES URC has no operations outside of its activities in connection with the Company’s operations.

 

The AES Corporation is a public company and is subject to the informational requirements of the Securities Exchange Act of 1934 and, in accordance therewith, files reports, proxy statements and other information, including financial reports, with the SEC, which are not incorporated into and do not form a part of this Form 10-K.

 

The following organizational chart illustrates the relationship among us, AES Red Oak, Inc., AES Sayreville, The AES Corporation, and AES URC:

 

 

The Company’s principal executive offices are located at 832 Red Oak Lane, Sayreville, NJ 08872. The Company’s telephone number is (732) 238-1462.

 

Energy Revenues

 

As mentioned above, the Company generates energy revenues under the Power Purchase Agreement with Williams Energy.  During the 20-year term of the agreement, the Company expects to sell electric energy and capacity produced by the facility, as well as ancillary and fuel conversion services.  Under the Power Purchase Agreement, the Company also generates revenues from meeting (1) base electrical output guarantees and (2) heat rate rebates through efficient electrical output.

 

4



 

Upon its expiration, or in the event that the Power Purchase Agreement is terminated prior to its 20-year term or Williams Energy otherwise fails to perform, the Company would seek to generate energy revenues from the sale of electric energy and capacity into the merchant market or under new short or long-term power purchase or similar agreements.  Due to current pool prices, however, the Company would expect that even if it were successful in finding alternate revenue sources, any such alternate revenues would be substantially below the amounts that would have been otherwise payable pursuant to the Power Purchase Agreement. There can be no assurances as to the Company’s ability to generate sufficient cash flow to cover operating expenses or its debt service obligations in the absence of a long-term Power Purchase Agreement with Williams Energy.

 

After the plant reached provisional acceptance, the Company elected to confirm reliability for up to 19 days before binding with Williams Energy.  Beginning August 13, 2002 (the date of risk transfer) through August 31, 2002, the Company operated the facility as a merchant plant with electric revenues sold to Williams Energy, in its capacity as the Company’s Pennsylvania-New Jersey-Maryland (“PJM”) account representative, at spot market prices and bought gas from Williams Energy at spot market prices. Additionally, during September 2002, the Company made net electric energy available to Williams Energy during times other than receiving a Williams Energy dispatch notice.  This net electric energy is referred to as “other sales of energy” in the Power Purchase Agreement and is sold at the local marginal price commonly referred to as spot market energy.  Gas required for this energy generation was purchased from Williams Energy at spot market prices.  The Company recognized merchant revenues of approximately $.3 million, $.2 million and $11.1 million for the years ended December 31, 2004, 2003 and 2002, respectively.  Related fuel expenses were approximately $.6 million, $.9 million and $6.9 million for the years ended December 31, 2004, 2003 and 2002, respectively.

 

Competition

 

Under the Power Purchase Agreement, Williams Energy is required to purchase all of the Company’s facility’s capacity and energy for an initial term of 20 years. Therefore, during the term of the Power Purchase Agreement, competition from other capacity and energy providers will become an issue only if the Power Purchase Agreement is terminated or not performed in accordance with its terms. As current gas market prices have been high, Williams Energy has only dispatched the Company 21% of the time in 2004 and 14% in 2003. Following the term of the Power Purchase Agreement, the Company anticipates selling its facility’s net capacity, ancillary services and energy under a new Power Purchase Agreement or into the PJM power pool market. At that time, the Company will face competition from other generating facilities selling into the PJM power pool market including, possibly, other facilities owned by The AES Corporation or its affiliates.

 

Employees

 

The Company is a Delaware limited liability company and has no employees other than its 6 officers. The Company’s officers receive no compensation for the services they provide to the Company or for any transactions between the Company and its affiliates. Under the operations agreement, AES Sayreville has managed the development and construction of and now operates and maintains the Company’s facility. The direct labor personnel and the plant operations management are employees of The AES Corporation provided to AES Sayreville under a services agreement.  As of December 31, 2004, The AES Corporation provided 27 employees to work at its facility.

 

Insurance

 

As owner of the Company’s site and lessee and owner of the facility, the Company maintains a comprehensive insurance program as required under its various project contracts and the indenture governing its senior secured bonds and underwritten by recognized insurance companies. Among other insurance policies, the Company also maintains commercial general liability insurance, permanent property insurance for full replacement value of the facility and business interruption insurance covering at least 18 months of gross revenues less variable operating expenses. The Company has obtained title insurance in an amount equal to the principal amount of the bonds.

 

The Company, or AES Sayreville as operator, maintains, among other insurance policies, workers’ compensation insurance (or evidence of self-insurance), if required, and comprehensive automobile bodily injury and property damage liability insurance.

 

5



 

Permits And Regulatory Approvals

 

AES Sayreville, as operator of the Company’s facility, and the Company, as owner of its facility, must comply with numerous federal, state and local regulatory requirements including environmental requirements in the operation of its facility.

 

On November 4, 1999, the Company received a certification from the Federal Energy Regulatory Commission (“FERC”) that the Company is an exempt wholesale generator. Certification as an exempt wholesale generator exempts the Company from regulation under the Public Utility Holding Company Act of 1935. The Company will maintain this status so long as the Company continues to make only wholesale sales of electricity, which the Company intends to do. Prior to commercial operation, the Company filed the Power Purchase Agreement with FERC and requested approval for the rates contained therein. On June 22, 2001, the Company received FERC approval at those rates. The Company may also need to obtain FERC approval for sales of electricity at market-based rates after the Power Purchase Agreement is no longer in effect.

 

On January 28, 2000, the Company received its Prevention of Significant Deterioration Permit, or “air permit,” from the New Jersey Department of Environmental Protection. The appeal period in respect of the air permit expired on February 28, 2000, and no appeal was filed. The air permit requires that the Company’s facility be constructed in a manner that will allow it to meet specified limitations on emissions of air pollutants. Under the construction agreement, originally WGI and now Raytheon, as project guarantor, are required to construct its facility to meet these requirements.  The required emission standards were met upon provisional acceptance and commercial operation and no additional modification is currently needed.

 

The Company is subject to a number of statutory and regulatory standards and required approvals relating to energy, labor and environmental laws.  The necessary environmental permits for the commencement of construction and operation of its facility have been obtained.

 

Summary of Principal Project Contracts

 

While the Company believes that the following summaries contain the material terms of the principal project contracts, such summaries may not include all of the provisions of each agreement that each individual investor may feel is important. These summaries do not restate each agreement discussed herein and exclude certain definitions and complex legal terminology that may be contained in each relevant agreement. You should carefully read each agreement discussed herein, each of which is filed as an exhibit to this Form 10- K.

 

Power Purchase Agreement

 

The Company entered into a Fuel Conversion Services, Capacity and Ancillary Services Purchase Agreement, dated as of September 17, 1999, with Williams Energy, for the sale to Williams Energy of all of the electric energy and unforced capacity produced by its facility as well as ancillary services and fuel conversion services.

 

Term

 

The Power Purchase Agreement extends for 20 years from the first contract anniversary date, which is the last day of the month in which commercial operation occurred (September 30, 2002).

 

Upon notice from Williams Energy no later than 90 days prior to the end of the initial term of the Power Purchase Agreement, the term of the Power Purchase Agreement may be extended by Williams Energy for up to a total of 24 months for each hour of the initial term during which the Company is unable to deliver energy or ancillary services because of an event of force majeure (other than an inability of the Company to obtain natural gas to operate the facility) that occurs after the commercial operation date.

 

Under the Power Purchase Agreement, the commercial operation date was required to occur by December 31, 2001, however, the Company had the right to extend the commercial operation date until June 30, 2002 by invoking its right to a free extension option which was available under the Power Purchase Agreement if certain conditions were met.  The Company exercised its right to extend the commercial operation date from December 31, 2001 to June 30, 2002, as granted under the free extension option. In addition, the Company had the right under the Power Purchase Agreement to again extend the commercial operation date from June 30, 2002 to June 30, 2003 (the

 

6



 

“Second Paid Extension Option”), upon written notification to Williams Energy no later than May 21, 2002 (which represented an agreed upon extension from the original April 30, 2002 notification deadline), by paying Williams Energy (i) an amount equal to the lesser of any actual damages Williams Energy suffered or incurred after June 30, 2002, as a result of Williams Energy’s reliance upon delivery by such date, to the extent said damages could not be mitigated fully, or $3.0 million and (ii) certain amounts of liquidated damages as calculated pursuant to the Power Purchase Agreement.  On May 21, 2002, the Company exercised the Second Paid Extension Option.  As a result of these extensions, the Company paid liquidated damages to Williams Energy at the rate of $11,000 per day for the period beginning on July 1, 2002 and ending on August 31, 2002, which amounted to $682,000.  As a result of the dispute over the commercial operation date, the Company also paid liquidated damages to Williams Energy at the rate of $22,000 per day for the period beginning on September 1, 2002 and ending on September 27, 2002, which amounted to $594,000.  This issue was resolved as part of the arbitration settlement with Williams. During the period of the Second Paid Extension Option, the Company continued to collect liquidated damages through August 10, 2002 from Raytheon under the construction agreement in the amount of $108,000 per day.  As of August 2002, the Company had received $14 million in liquidated damages from Raytheon under the construction agreement.  The Company did not receive any liquidated damages under the construction agreement in 2003 or 2004.

 

Williams Energy is currently the Company’s sole customer for purchases of capacity, ancillary services, and energy and its sole source for fuel.  Williams Energy’s payments under the Power Purchase Agreement are expected to provide all of its operating revenues during the term of the Power Purchase Agreement.  It is unlikely that the Company would be able to find another purchaser or fuel source on similar terms for the facility if Williams Energy were not performing under the Power Purchase Agreement.  Any material failure by Williams Energy to make capacity and fuel conversion payments or to supply fuel under the Power Purchase Agreement would have a severe adverse impact on the Company’s operations.

 

Purchase and Sale of Capacity

 

During the term of the Power Purchase Agreement, the Company will perform for Williams Energy on an exclusive basis, and Williams Energy will purchase and pay for fuel conversion services. Fuel conversion services include the operation of the Company’s facility by the Company to combust natural gas delivered by Williams Energy in order to generate and deliver energy or to provide ancillary services. The Company will sell and make available to Williams Energy on an exclusive basis, and Williams Energy will purchase and pay for, its facility’s net capacity and ability to generate electric energy. The Company may not sell, without the consent of Williams Energy in its sole discretion, capacity generated on the site but not from its facility.

 

Fuel Conversion and Other Services

 

Williams Energy must deliver or cause to be delivered to the Company at the natural gas delivery point on an exclusive basis all quantities of natural gas required by the Company to:

 

                  generate net electric energy and/or ancillary services;

 

                  perform start-ups;

 

                  perform shutdowns; and

 

                  operate its facility during any period other than a start-up, shutdown or dispatch period for any reason.

 

Williams Energy at all times retains title to the natural gas delivered to the Company except that when the Company’s facility is operated during any period other than a start-up, shutdown or dispatch period title is transferred to the Company at the natural gas delivery point.

 

Williams Energy is solely responsible for all costs and expenses related to the supply and transportation of natural gas to the natural gas delivery point. The Company is responsible for all costs and expenses related to the transportation, gathering or taxation of natural gas or its use or possession at and after the natural gas delivery point.

 

Upon the expiration of the Power Purchase Agreement or any termination of the Power Purchase Agreement as the result of Williams Energy’s default thereunder, the Company will have the right to purchase the gas interconnection facilities from Williams Energy, or if Williams Energy does not own the gas interconnection

 

7



 

facilities, Williams Energy will assign to the Company all of its rights to transportation services using the gas interconnection facilities.

 

Pricing and Payments

 

For each month of the term after the commercial operation date, Williams Energy must pay the Company for its facility’s net capacity, successful start-ups and associated shutdowns, ancillary services and fuel conversion services at the applicable rates set forth in the Power Purchase Agreement. Each monthly payment by Williams Energy consists of a total fixed payment, a variable operations and maintenance payment and an energy exercise fee. The total fixed payment, which is payable regardless of facility dispatch by Williams Energy but is subject to adjustment based on facility availability, is calculated by multiplying an unforced capacity rate for each contract year by the temperature adjusted unforced capacity in the billing month and adding to that the product of the fuel conversion option demand charge and the average facility capacity for that month. The total fixed payment is anticipated to be sufficient to cover the Company’s debt service and fixed operating and maintenance costs and to provide the Company a return on equity. The variable operations and maintenance payment is intended to cover its variable operating and maintenance costs and escalates annually based on an escalation index set forth in the Power Purchase Agreement. The energy exercise fee is intended to compensate the Company for each successful start-up. The Company may receive heat rate bonuses or be required to pay heat rate penalties.

 

Prior to the commercial operation date, and during some facility tests thereafter, the Company purchased natural gas from Williams Energy. Williams Energy sold the Company the natural gas at prices specified in the Power Purchase Agreement, and the Company sold to Williams Energy at the electric delivery point any net electric energy produced during the periods at the hourly integrated market clearing marginal price for electric energy at the location where it was delivered or received, calculated pursuant to the terms of the operating agreement of PJM Interconnection, LLC, which is the independent system operator that operates the transmission system to which its facility interconnects. The Company is solely responsible for any fines or penalties resulting from the delivery of the net electric energy at the electric delivery point when the delivery is made without the authorization of PJM, JCP&L, which is the host utility, or FERC. The Company has not incurred any such fine or penalty to date.

 

Williams Energy is entitled to an annual fuel conversion volume rebate if its dispatch of the Company’s facility exceeds specified levels and monthly non-dispatch payments if, under some circumstances, its facility does not deliver, in whole or in part, the requested net electric energy requested by Williams Energy. All fuel conversion volume rebate payments and non-dispatch payments must be made to Williams Energy after debt service and certain other payments but prior to any distribution to holders of equity interests in the Company. Fuel conversion volume rebate payments and any non-dispatch payments owed to Williams Energy and not paid when due will be paid, together with interest thereon, when funds become available to the Company at the priority level described above. A separate reserve account must be maintained by the Company and the Company’s lenders and the Company must deposit to that account on a monthly basis, from its cash flow, any applicable and unpaid non-dispatch payment plus a ratable amount of the maximum fuel conversion volume rebate amount that Williams Energy may have earned. Amounts held in that reserve account will be used to pay, to the extent owed, the fuel conversion volume rebate and non-dispatch payments.

 

Required Authorizations

 

During the term of the Power Purchase Agreement, the Company must, at its own cost and expense, obtain as and when required all approvals, permits, licenses and other authorizations from governmental authorities as may be required for the Company to operate and maintain its facility, the interconnection facilities and protective gas apparatus and to perform its obligations under the Power Purchase Agreement.  The Company plans to obtain all additional governmental approvals, permits, licenses and authorizations as may be required with respect to its facility as soon as practicable.

 

Interconnection and Metering Equipment

 

At the Company’s sole cost and expense, the Company designed, constructed and installed and currently maintains interconnection facilities and protective gas apparatus needed to generate and deliver net electric energy and/or ancillary services to the electric delivery point in order to fulfill its obligations under the Power Purchase Agreement, including all interconnection facilities and protective gas apparatus that are located at the switchyards and/or substations at the its facility. The Generation Facility and Transmission Interconnection Agreement is with

 

8



 

Jersey Central Power & Light Company (“JCP&L”) d/b/a GPU Energy (“GPU”), and is dated April 27, 1999. GPU has since been merged with, and into, FirstEnergy, and JCP&L is now a subsidiary of FirstEnergy.  The Company’s facility, interconnection facilities and protective gas apparatus have been designed, constructed and completed in a good and workmanlike manner and in accordance with accepted electrical practices (with respect to its facility and interconnection facilities) or in accordance with standard gas industry practices (with respect to protective gas apparatus), so that the expected useful life of the Company’s facility, the interconnection facilities and protective gas apparatus will be not less than the term of the Power Purchase Agreement.

 

Public Service Electric and Gas (“PSE&G”), under contract with Williams Energy, has installed the natural gas interconnection facilities and natural gas metering equipment to the Company’s satisfaction.  PSE&G has also installed gas metering equipment, although the Company is currently involved in a dispute with Williams Energy over the location of such equipment.  All electric metering equipment and gas metering equipment, whether owned by the Company or by a third party, must be operated, maintained and tested in accordance with accepted electrical practices, in the case of the electric metering equipment, and in accordance with applicable industry standards, in the case of the gas metering equipment. Except under limited circumstances, the Company may not enter into any modification or amendment of the interconnection agreement with JCP&L without the prior written consent of Williams Energy.

 

As of December 31, 2002, all electrical interconnection and metering equipment had been installed and accepted by JCP&L — See “Interconnection Agreement - JCP&L’s Obligations”.

 

Operation and Dispatch

 

Our facility and the interconnection facilities must be operated in accordance with accepted electrical practices and applicable requirements and guidelines of JCP&L pursuant to the interconnection agreement. The protective gas apparatus must be operated in accordance with standard gas industry practices. If there is a conflict between the terms and conditions of the Power Purchase Agreement and JCP&L requirements, the JCP&L requirements control. The Company must operate the facility in parallel with JCP&L’s electrical system in accordance with the interconnection agreement. When dispatched by Williams Energy, the Company must operate its facility and each unit thereof with automatic regulation equipment in service.

 

The Power Purchase Agreement acknowledges that JCP&L has the right to require the Company to disconnect the Company’s facility from its electrical system, or otherwise curtail, interrupt or reduce deliveries of net electric energy, in accordance with the terms of the interconnection agreement. If the Company’s facility has been disconnected for these reasons, Williams Energy will continue to be obligated to make total fixed payments for at least 24 hours after the occurrence of disconnection of its facility by JCP&L.

 

The Company must use commercially reasonable efforts to correct promptly any condition at its facility which necessitates the disconnection of its facility from JCP&L’s electrical system or the reduction, curtailment or interruption of electrical output of its facility.

 

Williams Energy has the exclusive right to use the net electric energy and ancillary services and to schedule the operation of the Company’s facility or a unit thereof in accordance with the provisions of the Power Purchase Agreement; however, the scheduling must be consistent with the design limitations of its facility, applicable law, regulations and permits, and the agreements and the manuals of PJM.

 

Williams Energy and the Company must perform each of its respective obligations in a manner that avoids the creation of cashout obligations or imbalance penalties imposed by the natural gas transporter. Williams Energy must try to minimize any imbalance charges under a transporter’s tariff and thereafter the Company will be responsible for imbalance charges levied by the natural gas transporter to the extent that the charges result from: (i) an imbalance caused by the Company greater than the allocable tolerance in the transporter’s tariff or (ii) the Company’s failure to promptly notify Williams Energy of a change in the operation of the Company’s facility that would cause any imbalance.

 

Force Majeure

 

A party will be excused from performing its obligations under the Power Purchase Agreement and will not be liable for damages or otherwise to the other party if and to the extent the party declares that it is unable to perform or

 

9



 

is prevented from performing an obligation under the Power Purchase Agreement by a force majeure condition, except for any obligations and/or liabilities under the Power Purchase Agreement to pay money, which will not be excused, and except to the extent an obligation accrues prior to the occurrence or existence of a force majeure condition as long as:

 

                  the party declaring its inability to perform by virtue of force majeure, as promptly as practicable after the occurrence of the force majeure condition, but in no event later than 5 days thereafter, gives the other party written notice describing, in detail, the nature, extent and expected duration of the force majeure condition;

 

                  the suspension of performance is of no greater scope and of no longer duration than is reasonably required by the force majeure condition;

 

                  the party declaring force majeure uses all commercially reasonable efforts to remedy its inability to perform; and

 

                  as soon as the party declaring force majeure is able to resume performance of its obligations excused as a result of the force majeure condition, it must give prompt written notification thereof to the other party.

 

Irrespective of whether the force majeure condition is declared by Williams Energy or us, the time period of a force majeure will be excluded from the calculation of all payments under the Power Purchase Agreement and Williams Energy will be under no obligation to pay the Company any of the payments described in the Power Purchase Agreement. If Williams Energy declares a force majeure, however, it will continue to pay the Company only the applicable monthly total fixed payment as described in the Power Purchase Agreement until the earlier of (i) the termination of the force majeure condition or (ii) the termination of the Power Purchase Agreement. Furthermore, if a force majeure is declared by the Company due to an action or inaction of JCP&L that prevents the Company from delivering net electric energy to the electric delivery point, Williams Energy will continue to pay the applicable portion of the total fixed payment for the first 24 hours of the period.

 

Notwithstanding anything to the contrary contained in the Power Purchase Agreement, except as may expressly be provided in the Power Purchase Agreement, the term force majeure will not include or excuse a party’s performance in the following circumstances:

 

                  Any reduction, curtailment or interruption of generation or operation of the Company’s facility, or of the ability of Williams Energy to accept or transmit net electric energy, whether in whole or in part, which reduction, curtailment or interruption is caused by or arises from the acts or omissions of any third party providing services or supplies to the party claiming force majeure, including any vendor or supplier to either party of materials, equipment, supplies or services, or any inability of JCP&L to deliver net electric energy to Williams Energy, unless, and then only to the extent that, any act or omission would itself be excused under the Power Purchase Agreement as a force majeure;

 

                  Any outage, whether or not due to the Company’s fault or negligence, attributable to a defect or inadequacy in the manufacture, design or installation of its facility that prevents, curtails, interrupts or reduces the ability of its facility to generate net electric energy or the Company’s ability to perform its obligations under the Power Purchase Agreement;

 

                  To the extent that the party claiming force majeure failed to prevent or remedy the force majeure condition by taking all commercially reasonable acts (short of litigation, if the remedy requires litigation) and, except as otherwise provided in the Power Purchase Agreement, failed to resume performance under the Power Purchase Agreement with reasonable dispatch after the termination of the force majeure condition;

 

                  To the extent that the claiming party’s failure to perform was caused by lack of funds;

 

                  To the extent Williams Energy is unable to perform due to a shortage of natural gas supply not caused by an event of force majeure; or

 

                  Because of an increase or decrease in the market price of electric energy/capacity or natural gas or because it is uneconomic for the party to perform its obligations under the Power Purchase Agreement.

 

10



 

Neither party will be required to settle any strike, walkout, lockout or other labor dispute on terms which, in the sole judgment of the party involved in the dispute, are contrary to its interest.

 

Williams Energy will have the right to terminate the Power Purchase Agreement if the Company has declared a force majeure and the effect of said force majeure has not been fully corrected or alleviated within 18 months after the date said force majeure was declared. Williams Energy, however, will not have the right to terminate the Power Purchase Agreement if (i) the force majeure was caused by Williams Energy or (ii) the force majeure event does not prevent or materially limit Williams Energy’s ability to sell the Company’s facility net capacity into or through the PJM power pool market or to a third party.

 

Events of Default; Termination; Remedies

 

The following will constitute events of default under the Power Purchase Agreement:

 

                  breach of any term or condition of the Power Purchase Agreement, including, but not limited to, (i) any failure to maintain or to renew any security, (ii) any breach of a representation, warranty or covenant or (iii) failure of either party to make a required payment to the other party;

 

                  our facility is not available to provide fuel conversion services or ancillary services to Williams Energy during any period of 180 consecutive days after the occurrence of the commercial operation date, except as may be excused by force majeure or the absence of available natural gas, or if non-availability is caused by an act or failure to act by Williams Energy where the action is required by the Power Purchase Agreement;

 

                  the Company sells or supplies net electric energy, ancillary services or capacity from the Company’s facility, or agrees to do the same, to any person or entity other than Williams Energy, without the prior approval of Williams Energy;

 

                  our failure for 30 consecutive days to perform regular and required maintenance, testing or inspection of the interconnection facilities, the Company’s facility and/or other electric equipment and facilities where the failure is material;

 

                  our failure for 30 consecutive days to correct or resolve a material violation of any code, regulation and/or statute applicable to the construction, installation, operation or maintenance of the Company’s facility, the interconnection facilities, protective gas apparatus or any other electric equipment and facilities required to be constructed and operated under the Power Purchase Agreement when the violation impairs the Company’s continued ability to perform its obligations under the Power Purchase Agreement;

 

                  involuntary bankruptcy or insolvency of either party that continues for more than 60 days;

 

                  voluntary bankruptcy or insolvency by either party;

 

                  any modifications, alterations or other changes to the Company’s facility by or on its behalf which prevent the Company from fulfilling, or materially diminish its ability to fulfill, its obligations, duties, rights and responsibilities under the Power Purchase Agreement and which after reasonable notice and opportunity to cure, are not corrected;

 

                  there will be outstanding for more than 60 days any unsatisfied final, non-appealable judgment against the Company in an amount exceeding $500,000, unless the existence of the unsatisfied judgment will not materially affect its ability to perform its obligations under the Power Purchase Agreement; and

 

                  The AES Corporation will cease to own, directly or indirectly, beneficially and of record, at least 50 percent of the equity interests in the Company, or will cease to possess the power to direct or cause the direction of its company’s management or policies, or any person, other than The AES Corporation or an affiliate, authorized to act as a power marketer by FERC or any affiliate of the person will own, directly or indirectly, beneficially or of record, any of the equity interests in its company.

 

Upon the occurrence of any event of default, other than a bankruptcy-related event of default, for which no notice will be required or opportunity to cure permitted, the party not in default, to the extent the party has actual knowledge of the occurrence of the event of default, will give prompt written notice of the default to the defaulting

 

11



 

party. The notice will set forth, in reasonable detail, the nature of the default and, where known and applicable, the steps necessary to cure the default. The defaulting party will have 30 days, two business days in the case of a default related to the breach of a representation, warranty or covenant, following receipt of the notice either to cure the default or commence in good faith all the steps as are necessary and appropriate to cure the default if the default cannot be completely cured within the 30-day period.

 

If the defaulting party fails to cure the default or take the steps as provided under the preceding paragraph, and immediately upon the occurrence of insolvency or the filing of a voluntary petition for bankruptcy, the Power Purchase Agreement may be terminated by the non-defaulting party, without any liability or responsibility whatsoever, by written notice to the party in default thereof. The Power Purchase Agreement will then terminate and the non-defaulting party may exercise all rights and remedies as are available to it to recover damages caused by the default, seek specific performance or exercise other rights and remedies that it may have in equity or at law.

 

Security

 

The Power Purchase Agreement required the Company to provide $30 million of financial security for the Company’s performance and payment obligations prior to commercial operation and $10 million of financial security for its performance and payment obligations subsequent to the commercial operation date.  The Company may, at any time at its option, elect to either provide the financial security in the form of a guaranty of The AES Corporation or in the form of a single letter of credit, satisfactory to Williams Energy in form and substance, upon which Williams Energy may draw as specified in the Power Purchase Agreement.  If the financial security contains an expiration date, either express or implied, the Company will renew the financial security not later than 10 days prior to the expiration date and will provide written notice of the renewal to Williams Energy at the same time. If the Company fails to renew the financial security as set forth above, Williams Energy is entitled to demand and receive payment thereunder on or after three days after written notice of the failure is provided to us, and the amount drawn will be deposited in an interest-bearing escrow account.

 

The letter of credit referred to above must be issued by a financial institution that at all times during the term of the letter of credit meets and maintains the following criteria: (i) a U.S. or foreign bank rated “C” or better by Thompson Bankwatch; or (ii) a U.S. or foreign bank, surety company or financial institution whose senior debt has the rating listed below by two of the three rating agencies: Standard & Poor’s (“S&P”): “A-” or better; Moody’s: “A3” or better; Duff & Phelps: “A-” or better.  If the bank, surety company or financial institution fails to maintain the ratings criteria, then upon 30 days’ written notice from Williams Energy, the Company is required to obtain equivalent security from another bank, surety company or financial institution meeting the above stated criteria.

 

In order to satisfy this obligation, prior to the commercial operation date the Company provided a $30 million letter of credit which was reduced to $10 million on the commercial operation date.  This letter of credit will remain in effect during the term of the Power Purchase Agreement.

 

The payment obligations of The Williams Companies, Inc. under the guaranty were originally capped at an amount equal to approximately $510 million.  Beginning on January 1 of the first full year after the commercial operation date, this guaranty cap is reduced semiannually by a fixed amount which is based on the amortization of the company’s senior secured bonds during the applicable semiannual period.  As of December 31, 2004 the guaranty was capped at $501.4 million.  Pursuant to Section 18.3 of the Power Purchase Agreement, in the event that S&P or Moody’s rates the long-term senior unsecured debt of The Williams Companies, Inc. lower than investment grade, The Williams Companies, Inc. is required to supplement The Williams Companies, Inc. guaranty with additional alternative security that is acceptable to the Company within 90 days after the loss of such investment grade rating.  According to published sources, The Williams Companies, Inc.’s long term senior unsecured debt has been rated below investment grade since 2002 by both S&P and Moody’s.

 

Due to the downgrade of The Williams Companies, Inc. to below investment grade, the Company and Williams Energy entered into a letter agreement dated November 7, 2002 (the “Letter Agreement”), under which Williams Energy agreed to provide the Company (a) a prepayment of $10 million within five business days after execution of the Letter Agreement (the “Prepayment”); (b) alternative credit support equal to $35 million on or before January 6, 2003 in any of the following forms: (i) cash, (ii) letter(s) of credit with the Company as the sole beneficiary substantially in the form of the Power Purchase Agreement Letter of Credit, unless mutually agreed to otherwise, or (iii) a direct obligation of the United States Government delivered to a custodial securities account as designated by the Company with a maturity of not more than three years; and (c) replenish any portion of the alternative credit

 

12



 

support that is drawn, reduced, cashed, or redeemed, at any time, with an equal amount of alternative credit support.  In the Letter Agreement, the Company and Williams Energy acknowledged that the posting of such alternative credit support and Williams Energy’s agreement and performance of the requirements of (a), (b), and (c), as set forth in the immediately preceding sentence, would be in full satisfaction of Williams Energy’s obligations contained in Section 18.3 of the Power Purchase Agreement.  In the Letter Agreement, the Company and Williams Energy expressly agreed that the posting of the Prepayment or any alternative credit support either now or in the future or any other terms set forth in the Letter Agreement is not intended to and did not modify, alter, or amend in any way, the terms and conditions or relieve The Williams Company, Inc. from any obligations it has under its guaranty of the payment obligations of Williams Energy under the Power Purchase Agreement.  The guaranty remains in full force and effect and the Company retains all of its rights and remedies provided by that guaranty.

 

Under the terms of the Letter Agreement, the Company is obligated to return the Prepayment to Williams Energy upon the earlier of (i) The Williams Companies, Inc. regaining its investment grade rating or Williams Energy providing a substitute guaranty of investment grade rating; (ii) the beginning of Contract Year 20; or (iii) the posting of alternative credit support by Williams Energy as set forth below.  In the case of items (i) and (iii) above, except to the extent, in the case of item (iii), Williams Energy elects to have all or a portion of the Prepayment make up a combination of the alternative credit support required to be posted pursuant to Section 18.3(b) of the Power Purchase Agreement, Williams Energy shall have the right to recoup the Prepayment by set-off of any and all amounts owing to the Company under the Power Purchase Agreement beginning no earlier than the June in the calendar year after the occurrence of item (i) or (iii) and continuing thereafter until the Prepayment has been fully recovered.  In the case of item (ii) above, Williams Energy shall have the right to immediately set-off all amounts owing to the Company under the Power Purchase Agreement after the occurrence of item (ii) and continuing thereafter until the Prepayment has been fully recovered.  Except to the extent Williams Energy elects to include the Prepayment as part of the alternative credit support, the amount of alternative credit support posted by Williams Energy pursuant to the Letter Agreement shall be initially reduced by the amount of the Prepayment, and Williams Energy shall thereafter increase the alternative credit support proportionately as Williams Energy recoups the Prepayment set-off on the payment due date of amounts owing to the Company.

 

If the Company does not return the Prepayment to Williams Energy as set forth in the preceding paragraph, then the Company shall be considered in default under the Letter Agreement and Williams Energy shall be entitled to enforce any and or all of its contractual rights and remedies as set forth in the Power Purchase Agreement, including, but not limited to, drawing on the letter of credit previously posted by the Company in favor of Williams Energy.

 

Williams Energy made the Prepayment on November 14, 2002 and provided an additional $25 million of cash to the Company on January 6, 2003 as the alternative credit support.  As allowed by the Letter Agreement, Williams elected to have the $10 million Prepayment included as part of the alternative credit support. On September 24, 2004, Williams Energy posted a letter of credit and the Company returned the $25 million of alternative credit support. In the event that The Williams Companies, Inc. regains and maintains its investment grade status, provides a substitute guaranty of investment grade rating, or posts a letter of credit, the Company will be required to return the remaining $10 million alternative credit support to Williams Energy in accordance with the terms of the Letter Agreement as described above.  Williams Energy has notified the Company that it intends to post a letter of credit for the remaining $10 million in June 2005. Williams Energy will recoup the Prepayment by set-off, beginning in July 2005, of amounts owing to the Company under the Power Purchase Agreement. As of March 30, 2005, the Company had cash balances of approximately $40.0 million.  See “Item 7-Managements Discussion and Analysis of Financial Condition and Results of Operations -Liquidity and Capital Resources”.

 

Assignment

 

Generally, a party to the Power Purchase Agreement may not assign, transfer, pledge or otherwise encumber or dispose of any rights, duties, interests or obligations thereunder without the prior written consent of the other party except that (i) Williams Energy may, upon reasonable advance notice to us, assign its rights, duties and obligations under the Power Purchase Agreement to any of its affiliates or any other entity, provided that such affiliate or other entity’s long term unsecured debt at such time is rated investment grade by S&P and Moody’s or such affiliate or other entity’s obligations under the Power Purchase Agreement are guaranteed by an affiliate whose long-term unsecured debt at such time is rated investment grade by S&P and Moody’s and such assignee agrees to be bound by all of the terms and conditions on the Power Purchase Agreement to the same extent as Williams Energy, (ii) the Company may, upon reasonable advance notice to Williams Energy, assign the Power Purchase Agreement and any of its rights, interests, duties or obligations thereunder as collateral security to any Lender so long as the assignee

 

13



 

agrees to be bound by all of the terms and conditions of the Power Purchase Agreement to the same extent as the Company in the event that such lender exercises its rights under such assignment and (iii) the Company may assign any of its rights, duties and obligations under the Power Purchase Agreement to any affiliate provided such affiliate assumes in writing all of the Company’s obligations under the Power Purchase Agreement and the guaranty of its performance as required by the Power Purchase Agreement remains in effect.

 

Construction Agreement

 

The Company entered into an Agreement for Engineering, Procurement and Construction Services, dated as of October 15, 1999, with WGI (as the successor contractor) under which WGI was required to perform services in connection with the design, engineering, procurement, site preparation and clearing, civil works, construction, start-up, training and testing and to provide all materials and equipment (excluding operational spare parts), machinery, tools, construction fuels, chemicals and utilities, labor, transportation, administration and other services and items (collectively and separately, the “services”) for the Company’s facility. Under a Guaranty in its favor, effective as of October 15, 1999, all of WGI’s obligations under the construction agreement are irrevocably and unconditionally guaranteed by Raytheon.

 

WGI filed for bankruptcy on May 14, 2001, however construction of the facility continued through a series of cooperative agreements executed by us, WGI and Raytheon. On November 9, 2001, the Bankruptcy Court approved WGI’s rejection of the construction agreement and the execution of the PCA by WGI and Raytheon. Additionally, on November 21, 2001, the Company and Raytheon entered into the Owner/Guarantor Supplemental Agreement pursuant to which (i) Raytheon and the Company acknowledged that, notwithstanding the rejection of the construction agreement by WGI, Raytheon would cause the project to be completed in accordance with the terms of the construction agreement pursuant to Raytheon’s performance guaranty obligations, and the construction agreement will have continuing applicability insofar as it defines (x) the obligations owed to the Company by Raytheon under its guaranty and (y) the Company’s obligations to Raytheon arising from the performance of those obligations, (ii) Raytheon (or their designees) was designated as the Company’s agent for purposes of administering the subcontracts and vendor contracts assigned by WGI to us, (iii) all future payments by the Company would be paid in accordance with the terms of the construction agreement directly to Raytheon, and (iv) Raytheon would indemnify the Company with respect to any claims arising out of the subcontracts and vendor contracts assumed by us.

 

Provisional acceptance of the facility was achieved on August 11, 2002 when the Company entered into a settlement agreement with Raytheon.  In return for provisional acceptance, Raytheon agreed to perform work identified in the punch list provided as part of the agreement.  Raytheon was also required to pay a $5 million settlement fee, minus outstanding milestones and change-orders for a net payment to the Company for $2.37 million, which it paid in 2002.  Raytheon must perform certain agreed upon completion items in order to obtain final acceptance.  See “Completion and Acceptance of the Company’s Project – Final Acceptance”.

 

Raytheon Services and Other Obligations

 

Raytheon must complete the Company’s project by performing or causing to be performed all of the agreed upon services. The services have included: engineering and design; construction and construction management; providing the Company design documents, instruction manuals, a project procedures manual and quality assurance plan; procurement of all materials, equipment and supplies and all contractor and subcontractor labor and manufacturing and related services; providing a spare parts list; providing all labor and personnel; obtaining all applicable permits; performing inspection, expediting, quality surveillance and traffic services; transporting, shipping, receiving and marshaling all materials, equipment and supplies and other items; providing storage for all materials, supplies and equipment and procurement or disposal of all soil and gravel (including remediation and disposal of specific hazardous materials); providing for design, construction and installation of electrical interconnection facilities (including electric metering equipment, automatic regulation equipment, protective apparatus and control system equipment) and reviewing other utility interconnections to the Company’s facility (including gas and water pipelines); performing performance tests; providing for start-up and initial operation functions; providing specified spare parts, waste disposal services, chemicals, consumables and utilities.

 

The services have also included: training the Company’s personnel prior to provisional acceptance; providing the Company and its designee with access to the site; obtaining additional necessary real estate rights; cleaning-up

 

14



 

and waste disposal (including hazardous materials brought to the site by Raytheon or the subcontractors); submitting a project schedule and progress reports; paying of contractor taxes; making employee identification and security arrangements; protecting adjoining utilities and public and private lands from damage; paying appropriate royalties and license fees; providing final releases and waivers to us; posting collateral or providing other assurances if major subcontractors fail to furnish final waivers; maintaining labor relations and project labor agreements; providing further assurances; coordinating with other contractors; and causing Raytheon to execute and deliver the related guaranty.

 

As mentioned above, provisional acceptance was granted by the Company on August 11, 2002.  Raytheon must perform certain agreed upon completion items in order to obtain final acceptance.  See “Completion and Acceptance of the Company’s Project – Final Acceptance”.

 

Construction and Start-Up

 

Raytheon was required to perform certain services in accordance with prudent utility practices, generally accepted standards of professional care, skill, diligence and competence applicable to engineering, construction and project management practices, all applicable laws, all applicable permits, the real estate rights, the quality assurance plan, the electrical interconnection requirements, the environmental requirements and safety precautions set forth in the construction agreement, and all of the requirements necessary to maintain the warranties granted by the subcontractors under the construction agreement. Raytheon must perform the services in accordance with the Company’s project schedule and is obligated to cause:

 

                  each construction progress milestone to be achieved on or prior to the applicable construction progress milestone date; and

 

                  final acceptance of the Company’s facility on or before the guaranteed final acceptance date. See “Completion and Acceptance of the Company’s Project – Final Acceptance “.  Raytheon must perform the services so that its facility, when operated in accordance with the instruction manual and the Power Purchase Agreement operating requirements as of provisional acceptance and final acceptance, will comply with all applicable laws and applicable permits, the electrical interconnection requirements and the guaranteed emissions limits in accordance with the completed performance test requirements.

 

Contract Price and Payment

 

The adjusted contract price, including base scope changes through the date of the construction agreement, was $295.7 million and commencing on the construction commencement date was paid in installments in accordance with the payment and milestone schedule. The contract was adjusted as a result of scope changes. The prepayment funds were backed by a prepayment letter of credit in the Company’s favor. However, under the construction agreement, the bankruptcy filing by WGI on May 14, 2001 constituted an event of default under the construction agreement. Accordingly, the Company requested that the full available amount of such letter of credit be drawn upon and deposited in the construction account held by the collateral agent. The collateral agent made such drawing on May 4, 2001 in the amount of $95.8 million, which was the then outstanding amount of the prepayment letter of credit as it had been reduced by WGI’s achievement of construction milestones under the construction agreement. Subsequent to the termination of the prepayment arrangements with WGI, payments to WGI for achievement of construction milestones as specified in the construction agreement were made in accordance with the terms of the construction agreement.

 

Under the construction agreement, Raytheon was entitled to post a letter of credit in the amount of the then current retainage. On March 4, 2002, Raytheon provided the Company with a letter of credit in the amount of $29.5 million (which amount represented the outstanding amount of retainage under the construction agreement on the date the letter of credit was posted) and the Company paid Raytheon the amount of the retainage.  Raytheon has subsequently increased the amount of the letter of credit in proportion to the amounts which would otherwise be retained by the Company and the Company has paid Raytheon the corresponding amount of this retainage.  As of December 31, 2003, Raytheon had provided a letter of credit of approximately $30.8 million.  On August 26, 2004, the Company drew down approximately $30.3 million under a letter of credit posted by Raytheon pursuant to the terms of the EPC Agreement. Prior to this date, the Company had drawn $0.5 million on this letter of credit.  See “Completion and Acceptance of the Company’s Project – Final Acceptance.”

 

15



 

The Company’s Services

 

The Company’s responsibilities include: designating a representative for the Company’s project; furnishing Raytheon access to the site; securing specified real estate rights; providing specified start-up personnel; furnishing specified spare parts, water disposal services and consumables; providing permanent utilities for the start-up, testing and operation of the Company’s facility; providing raw and potable water arrangements; providing fuel supply arrangements; providing electrical interconnection facilities arrangements; furnishing approvals; administering third-party contracts; causing The AES Corporation to provide a pre-financial closing guaranty.

 

If the Company fails to meet any of the Company’s obligations under the construction agreement, then, to the extent that Raytheon was reasonably delayed in the performance of the services as a direct result thereof, an equitable adjustment to one or more of the contract price, the guaranteed completion dates, the construction progress milestone dates, the payment and milestone schedule and the Company’s project schedule, and, as appropriate, the other provisions of the construction agreement that may be affected thereby, will be made by agreement between the Company and Raytheon.

 

Completion and Acceptance of the Company’s Project

 

Mechanical Completion

 

Mechanical completion was achieved on August 13, 2002.

 

Performance Tests and Power Purchase Agreement Output Tests

 

Once mechanical completion was achieved, Raytheon was required to perform certain performance tests in accordance with criteria set forth in the construction agreement. Raytheon gave the Company notice of the performance tests, the Company arranged for the disposition of output during start-up and testing and Raytheon declared these performance tests complete since during the tests the operation of the Company’s facility complied with applicable laws, applicable permits, Guaranteed Emissions Limits and other required standards.  Although the performance test met the levels required for the commencement of commercial operations, they did not meet the levels guaranteed by Raytheon under the construction agreement.  Therefore, as provided by the construction agreement, Raytheon had been paying the Company interim rebates until their notice of final acceptance date of July 22, 2003, but the Company contends that these amounts should continue to be paid until the final acceptance date, which the Company contends has not yet occurred. Based on the Company’s interpretation of the contract, the Company expects that on the final acceptance date additional performance tests will be performed and if specified levels of heat rate and output are not met, Raytheon will be required to pay the Company a final lump-sum payment which will be based on the amount of the deficiency. Raytheon disputes the Company’s position since they contend that the final acceptance date has already occurred.  See “Final Acceptance”.

 

Provisional Acceptance

 

Provisional acceptance was achieved on August 11, 2002 and risk transfer occurred on August 13, 2002 when:

 

                  Raytheon caused a completed performance test in which the Company’s facility demonstrated an average net electrical output of 95% (or higher) of the electrical output guarantee and 105% (or lower) of the gas-based heat rate guarantee; and

 

                  our facility achieved the requirements of mechanical completion.

 

The independent engineer and the Company were satisfied that the provisional acceptance requirements had been met and delivered to Raytheon a provisional acceptance certificate on August 11, 2002.  The Company took possession and control of the Company’s facility and the Company is now solely responsible for the operation and maintenance of the facility although Raytheon continues to have reasonable access to its facility to complete the services.

 

Final Acceptance

 

Final acceptance will be achieved when:

 

16



 

                  Raytheon has caused a completed performance test in accordance with the construction agreement to be concluded in which the Company’s facility demonstrates during the performance test an average net electrical output of 100% (or higher) of the electrical output guarantee and 100% (or lower) of the heat rate guarantee;

 

                  our facility has achieved, and continues to satisfy the requirements for the achievement of, mechanical completion;

 

                  the reliability guarantee has been achieved under the construction agreement; and

 

                  Raytheon has completed performance of the services except for (i) punch list items and (ii) services that are required by the terms of the construction agreement to be completed after the achievement of final acceptance, such as Raytheon’s warranty obligations.

 

The reliability guarantee will have been achieved if and only if the Company’s facility demonstrates an average equivalent availability of not less than 95% while operating over a period of at least 30 consecutive days in accordance with applicable laws, applicable permits, the electrical interconnection requirements, the Power Purchase Agreement operating requirements, the guaranteed emissions limits, the instruction manual and the Power Purchase Agreement.

 

At any time after provisional acceptance of the Company’s facility has been achieved, Raytheon may, after exhausting all reasonable repair and replacement alternatives in order to achieve the applicable performance guarantees for final acceptance, and so long as that the reliability guarantee will have been achieved, give to the Company notice of its intention to elect to declare final acceptance. In that event, Raytheon may elect to use the results of the most recent eligible completed performance test for the purpose of determining the Company’s facility’s level of achievement of the performance guarantees.  Final acceptance will be deemed effective as of the last to occur of (i) the date of the Company’s receipt of the declaration and report of the final completed performance test, or, as applicable, the most recent completed performance test and (ii) the effective date of the achievement of the reliability guarantee.

 

If on or before the guaranteed final acceptance date (i) the Company’s facility has achieved provisional acceptance and (ii) the reliability guarantee has been achieved, then final acceptance of its facility will be deemed to occur on the guaranteed final acceptance date.

 

The guaranteed final acceptance date was originally required to occur 13.5 months after the guaranteed provisional acceptance date as defined under the construction agreement, but on March 8, 2003 the Company entered into a letter agreement with Raytheon pursuant to which the Company agreed to extend the guaranteed final acceptance date to June 30, 2003.  Raytheon gave notice of Final Acceptance on July 22, 2003 based on its July 8, 2003 performance test.  On July 31, 2003, the Company received a letter from the project’s independent engineer stating that it could not support Raytheon’s claim of final acceptance and it did not consider the July 8, 2003 performance test valid.  In making this assessment, the independent engineer cited, among other reasons, (i) modifications made to certain equipment in performance of the July 8 performance test which would adversely impact the operations of the plant and other pieces of equipment and (ii) Raytheon’s failure to demonstrate compliance with guaranteed emissions limits.  On August 1, 2003, the Company rejected Raytheon’s claim of final acceptance.  This rejection was based upon Raytheon’s failure to meet the conditions for final acceptance provided for in the EPC contract. On August 7, 2003, the Company received a response from Raytheon in which Raytheon claims that the Company’s rejection of the final acceptance is invalid and improper.

 

On August 26, 2004, the Company drew down approximately $30.3 million under a letter of credit posted by Raytheon pursuant to the terms of the EPC Agreement. Prior to this date, the Company had drawn $544,000 on this letter of credit. The Company believes that Raytheon substantially breached the EPC Agreement, due, among other things, to the facility’s failure to achieve compliance with certain performance tests, and Raytheon’s failure to complete other services under the EPC Agreement and certain amendments thereto, including a Settlement Agreement dated August 6, 2002, that purported to resolve disputes over whether Raytheon had achieved Mechanical Completion and Provisional Acceptance. As a result, the Company claims that Raytheon’s breaches have caused damages in excess of the amount of the letter of credit. Raytheon disputes these claims and has failed and refused to pay costs and damages to the Company despite the Company’s demands for such payment.

 

17


 


 

On August 27, 2004, Raytheon filed a construction lien claim for $30,963,662 in Middlesex County against the real property and improvements owned by the Company under the New Jersey Construction Lien Law.  Among other things, Raytheon claims therein that the draw of the Letter of Credit represents a debt to Raytheon owed by the Company.

 

On October 28, 2004, the Company received a complaint filed by Raytheon in the State of New York. In the complaint, Raytheon is seeking to recover $30,302,269, which represents the amount Red Oak drew down on the letter of credit on August 26, 2004, attorneys’ fees and costs, and also to recover up to $110 million of net expense Raytheon claims to have incurred in good faith under the governing guaranty and construction agreements.  The Company filed an answer and counterclaim on December 13, 2004, in which it denied liability to Raytheon, asserted various defenses and countersued Raytheon for breach of the EPC Agreement and Settlement Agreement, breach of express warranties under the EPC Agreement, and fraudulent misrepresentation and concealment.  The Company claimed damages of not less than $140 million and attorneys’ fees and costs to the extent allowable.  Raytheon moved to dismiss the Company’s fraudulent misrepresentation and concealment claim and to limit the Company’s damages on January 14, 2005.  The Company filed its opposition to the motion to dismiss and also filed an amended counterclaim on February 18, 2005. Thereafter, Raytheon agreed to withdraw its motion to dismiss.  On March 4, 2005, Raytheon filed a motion for summary judgment that seeks the return of $16,311,711 of the Letter of Credit draw.  The Company has not yet filed its opposition to the motion, and Raytheon has not yet filed an answer to the amended counterclaim. The Company has recorded the $30.3 million as a current liability, but has not accrued any additional amounts with respect to Raytheon’s claims.  The Company believes it has meritorious defenses to the claims asserted by Raytheon against it and intends to defend the lawsuit and pursue its counterclaims vigorously.

 

Project Completion

 

Project completion will be achieved under the construction agreement when:

 

                  Final acceptance of the Company’s facility will have occurred and the performance guarantees with respect to its facility will have been achieved (or in lieu of achievement of the performance guarantees, applicable rebates under the construction agreement will have been paid, or the Company will have elected final acceptance);

 

                  The reliability guarantee will have been achieved;

 

                  Raytheon will have demonstrated during the completed performance test that the operation of the Company’s facility does not exceed the guaranteed emissions limits;

 

                  The requirements for achieving mechanical completion of the Company’s facility will continue to be met;

 

                  The punch list items will have been completed in accordance with the construction agreement; and

 

                  Raytheon will have performed all of the services, other than those services, such as Raytheon’s warranty obligations, which by their nature are intended to be performed after project completion.

 

When Raytheon believes that it has achieved project completion, it will deliver to the Company a notice of project completion. If the Company is satisfied that the final acceptance requirements have been met, the Company will deliver to Raytheon a project completion certificate. If reasonable cause exists for doing so, the Company will notify Raytheon in writing that project completion has not been achieved, stating the reasons therefore. If the Company’s project completion has not been achieved as so determined by us, Raytheon will promptly take the action or perform the additional services as will achieve project completion and will issue to the Company another notice of project completion. The procedure will be repeated as necessary until project completion is achieved.

 

Raytheon will be obligated to achieve project completion within 90 days after final acceptance of the Company’s facility. If Raytheon does not achieve its project completion on or before the Company’s project completion deadline or if the Company determines that Raytheon is not proceeding with all due diligence to complete the services in order to achieve project completion by the deadline, the Company may retain another contractor to complete the work at contractor’s expense.

 

18



 

As a result of the Company’s ongoing disagreement with Raytheon regarding final acceptance, project completion has not yet occurred.

 

Price Rebate for Failure to Meet Guarantees

 

Completion Dates

 

Raytheon guaranteed that (i) provisional acceptance or final acceptance of the Company’s facility will be achieved on or before the guaranteed provisional acceptance date and (ii) final acceptance of the Company’s facility will be achieved on or before the guaranteed final acceptance date.

 

If neither provisional acceptance nor final acceptance of the Company’s facility occurred by the date that is 50 days after the guaranteed provisional acceptance date, Raytheon was obligated to pay the Company $108,000 per day as liquidated damages, for each day provisional acceptance or final acceptance is later than the guaranteed provisional acceptance date. The aggregate amount of such payments that Raytheon is obligated to make is limited to 13% of the adjusted contract price (approximately $40 million). Since neither provisional nor final acceptance had occurred within 50 days of the guaranteed provisional acceptance date of February 14, 2002, Raytheon began to pay the Company scheduled late completion payments beginning on April 6, 2002 and ending on August 10, 2002 (the day prior to the provisional acceptance date).  A total of $14 million in liquidated damages was received in 2002, and no amounts were received in 2003 or 2004.

 

Pursuant to the construction agreement, if neither provisional acceptance nor final acceptance of the Company’s facility occurred on or before the date that was 90 days after the guaranteed provisional acceptance date, Raytheon was required to submit for approval by the Company and the independent engineer a plan to accelerate the performance of the services as necessary in order to achieve final acceptance of the Company’s facility by the guaranteed final acceptance date. Raytheon submitted the required plan which was subsequently approved by the Company and the independent engineer.

 

Performance Guarantees

 

Electrical Output

 

Under the construction contract, if the average net electrical output of the Company’s facility at provisional acceptance or interim acceptance, whichever is the earlier to occur, is less than the electrical output guarantee, then Raytheon must pay us, as a rebate and not as liquidated damages, for each day during the interim period, an amount equal to $0.22 per day for each kilowatt by which the average net electrical output is less than the electrical output guarantee.  During performance testing, the Company’s output was calculated to be 13,370 kilowatts less than the electrical output guarantee.  Accordingly, the Company’s daily charge for this amount has been calculated at $2,941.40 per day. Raytheon had been paying the Company this amount until their notice of final acceptance date of July 22, 2003, but the Company is disputing this claim of final acceptance and contends that these amounts should continue to be paid until the final acceptance date. See “Final Acceptance”.

 

Upon final acceptance, if the average net electrical output of the Company’s facility during the completed performance test is less than the electrical output guarantee, then Raytheon must pay us, as a bonus, an amount equal to $520 for each kilowatt by which the average net electrical output is less than the guarantee minus any interim rebates paid or to be paid by Raytheon.

 

Heat Rate Guarantees

 

If the average net heat rate of the Company’s facility at provisional acceptance or interim acceptance, if having occurred before final acceptance, exceeds the heat rate guarantee, then Raytheon must pay us, as a rebate and not as liquidated damages, for each day during the interim period, an amount equal to $46 per day for each BTU/KwH by which the measured net heat rate is greater than the heat rate guarantee.

 

Upon final acceptance, if the net heat rate of the Company’s facility during the completed performance test exceeds the heat rate guarantee, then Raytheon will pay us, as a rebate, a lump sum amount equal to $110,000 for each BTU/KwH by which the measured heat rate is greater than the heat rate guarantee minus any interim rebates paid or to be paid by Raytheon.

 

19



 

As of December 31, 2004, Raytheon owed approximately $65,000 in rebates that were invoiced in 2003.  This amount is reflected in accounts receivable at December 31, 2004.  The Company did not invoice interim rebates in 2004, pending resolution of the Final Acceptance date with Raytheon.

 

Liability and Damages

 

Limitation of Liability

 

In no event will Raytheon’s liability (i) for provisional acceptance late completion payments exceed an amount equal to 13% of the contract price, (ii) for performance guarantee payments arising from the electrical output guarantee exceed in the aggregate an amount equal to 10% of the contract price, (iii) for performance guarantee payments arising from the heat rate guarantee exceed in the aggregate 15% of the contract price and (iv) for all provisional acceptance late completion payments and performance guarantee payments exceed an amount equal to 34% of the contract price.

 

Consequential Damages

 

Neither party nor any of its contractors, subcontractors or other agents providing equipment, material or services for the Company’s project will be liable for any indirect, incidental, special or consequential loss or damage of any type.

 

Aggregate Liability of Contractor

 

The total aggregate liability of Raytheon and any of its subcontractors, including, without limitation, liabilities described above, to the Company will not in any event exceed an amount equal to the contract price for liability due to events occurring before the provisional acceptance date or 40% of the contract price for liability due to events occurring after the provisional acceptance date; however, the limitation of liability will not apply to obligations to remove liens or to make indemnification payments.

 

Warranties and Guarantees

 

Raytheon warrants and guarantees that during the applicable warranty period:

 

                  all machinery, equipment, materials, systems, supplies and other items comprising the Company’s project will be new and of first-rate quality which satisfies utility-grade standards and in accordance with prudent utility practices and the specifications set forth in the construction agreement, suitable for the use in generating electric energy and capacity under the climatic and normal operating conditions and free from defective workmanship or materials;

 

                  it will perform all of its design, construction, engineering and other services in accordance with the construction agreement;

 

                  our project and its components are free from all defects caused by errors or omissions in engineering and design, as determined by reference to prudent utility practices, and comply with all applicable laws, all applicable permits, the electrical interconnection requirements, the Power Purchase Agreement operating requirements and the guaranteed emissions limits; and

 

                  the completed project performs its intended functions of generating electric energy and capacity as a complete, integrated operating system as contemplated in the construction agreement.

 

If the Company notifies Raytheon within 30 days after the expiration of the applicable warranty period of any defects or deficiencies discovered during the applicable warranty period, Raytheon will promptly reperform any of the services at its own expense to correct any errors, omissions, defects or deficiencies and, in the case of defective or otherwise deficient machinery, equipment, materials, systems supplies or other items, replace or repair the same at its own expense. Raytheon warrants and guarantees that, to the extent the Company has made all payments then due to Raytheon, title to the Company’s facility and all work, materials, supplies and equipment will pass to the Company free and clear of all liens, other than any permitted liens. Other than the warranties and guarantees provided in the construction agreement there are no other warranties of any kind, whether statutory, express or implied relating to the services.

 

20



 

Upon notification from the Company no later than 30 days after the expiration of the applicable warranty period of any defects or deficiencies in the Company’s project or any component thereof, the Company will, subject to the provisions of the construction agreement, make the Company’s facility or the subject equipment available to Raytheon for Raytheon to re-perform, replace or, at Raytheon’s option, repair the same at Raytheon expense so that it is in compliance with the standards warranted and guaranteed, all in accordance with the construction agreement.

 

Force Majeure

 

Force Majeure Event

 

A force majeure event will mean any act or event that prevents the affected party from performing its obligations, other than the payment of money, under the construction agreement or complying with any conditions required to be complied with under the construction agreement if the act or event is beyond the reasonable control of and not the fault of the affected party and the party has been unable by the exercise of due diligence to overcome or mitigate the effects of the act or event. Force majeure events include, but are not limited to, acts of declared or undeclared war, sabotage, landslides, revolution, terrorism, flood, tidal wave, hurricane, lightning, earthquake, fire, explosion, civil disturbance, insurrection or riot, act of God or the public enemy, action, including unreasonable delay or failure to act, of a court or public authority, or strikes or other labor disputes of a regional or national character that are not limited to only the employees of Raytheon or its subcontractors and that are not due to the breach of a labor contract or applicable law by the party claiming force majeure or any of its subcontractors. Force majeure events do not include (i) acts or omissions of Raytheon or any subcontractors, except as expressly provided in the foregoing sentence, (ii) late delivery of materials or equipment, except to the extent caused by a force majeure event, and (iii) economic hardship.

 

Excused Performance

 

If either party is rendered wholly or partly unable to perform its obligations because of a force majeure event, that party will be excused from whatever performance is affected by the force majeure event to the extent so affected so long as:

 

                  the non-performing party gives the other party prompt notice describing the particulars of the occurrence;

 

                  the suspension of performance is of no greater scope and of no longer duration than is reasonably required by the force majeure event;

 

                  the non-performing party exercises all reasonable efforts to mitigate or limit damages to the other party;

 

                  the non-performing party uses its best efforts to continue to perform its obligations under the construction agreement and to correct or cure the event or condition excusing performance; and

 

                  when the non-performing party is able to resume performance of its obligations, that party will give the other party written notice to that effect and will promptly resume performance under the construction agreement.

 

Scope Changes

 

The Company may order scope changes to the services, in which event one or more of the contract price, the construction progress milestone dates, the guaranteed completion dates, the payment and milestone schedule, the Company’s project schedule and the performance guarantees will be adjusted accordingly, if necessary. All scope changes will be authorized by a scope change order and only the Company or its representative may issue scope change orders.

 

As soon as Raytheon becomes aware of any circumstances which Raytheon has reason to believe may necessitate a scope change, Raytheon will issue to the Company a scope change order notice at Raytheon’s expense. If the Company desires to make a scope change, in response to a scope change order notice or otherwise, the Company will submit a scope change order request to Raytheon. Raytheon will promptly review the scope change order request and notify the Company in writing of the options for implementing the proposed scope change and the effect, if any, each option would have on the contract price, the guaranteed completion dates, the construction

 

21



 

progress milestone dates, the payment and milestone schedule, the Company’s project schedule and the performance guarantees.

 

No scope change order will be issued and no adjustment of the contract price, the guaranteed completion dates, the construction progress milestone dates, the payment and milestone schedule, the Company’s project schedule or the performance guarantees will be made in connection with any correction of errors, omission, deficiencies, or improper or defective work on the part of Raytheon or any subcontractors in the performance of the services. Changes due to changes in applicable laws or applicable permits occurring after the date of the construction agreement will be treated as scope changes.

 

Effect of Force Majeure Event

 

If and to the extent that any force majeure events affect Raytheon’s ability to meet the guaranteed completion dates, or the construction progress milestone dates, an equitable adjustment in one or more of the dates, the payment and milestone schedule and the Company’s project schedule will be made by agreement of the Company and Raytheon. No adjustment to the performance guarantees and, except as otherwise expressly set forth below, the contract price will be made as a result of a force majeure event. If Raytheon is delayed in the performance of the services by a force majeure event, then:

 

                  to the extent that the delay(s) are, in the aggregate, 60 days or less, Raytheon will absorb all of its costs and expenses resulting from said delay(s); and

 

                  to the extent that the delay(s) are, in the aggregate, more than 60 days, Raytheon will be reimbursed by the Company for those incremental costs and expenses resulting from said delay(s) which are incurred by Raytheon after said 60-day period.

 

Price Change

 

An increase or decrease in the contract price, if any, resulting from a scope change requested by the Company or made under the construction contract will be determined by mutual agreement of the parties.

 

Continued Performance Pending Resolution of Disputes

 

Notwithstanding any dispute regarding the amount of any increase or decrease in Raytheon’s costs with respect to a scope change, Raytheon will proceed with the performance of the scope change promptly following the Company’s execution of the corresponding scope change order.

 

Hazardous Materials

 

If hazardous materials were not identified in an environmental site assessment report delivered by the Company to Raytheon prior to the commencement date and were not brought onto the site by Raytheon or any of its subcontractors, then Raytheon will be entitled to a scope change under the construction agreement.

 

Risk of Loss

 

Since the risk transfer date with respect to the Company’s facility, the Company bear all risk of loss and full responsibility for repair, replacement or reconstruction with respect to any loss, damage or destruction to its facility.

 

Termination

 

Termination for the Company’s Convenience

 

The Company may for its convenience terminate any part of the services or all remaining services at any time upon 30 days’ prior written notice to Raytheon specifying the part of the services to be terminated and the effective date of termination. The Company may elect to suspend completion of all or any part of the services upon 10 days’ prior written notice to Raytheon, or, in emergency situations, upon prior notice as circumstances permit.

 

22



 

Termination by Raytheon

 

If the Company fails to pay to Raytheon any payment and the failure continues for 30 days, then (i) Raytheon may suspend its performance of the services upon 10 days’ prior written notice to us, which suspension may continue until the time as the payment, plus accrued interest thereon, is paid to Raytheon, and/or (ii) if the payment has not been made prior to the commencement of a suspension by Raytheon under clause (i) above, Raytheon may terminate the construction agreement upon 60 days’ prior written notice to us; however, the termination will not become effective if the payment, plus accrued interest thereon, is made to Raytheon prior to the end of the notice period. If the suspension occurs, an equitable adjustment to one or more of the contract price, the guaranteed completion dates, the construction progress milestone dates, the payment and milestone schedule and the Company’s project schedule, and, as appropriate, the other provisions of the construction agreement that may be affected thereby, will be made by agreement between the Company and Raytheon. If the Company has suspended completion of all or any part of the services in accordance with the construction agreement for a period in excess of 365 days in the aggregate, Raytheon may, at its option, at any time thereafter so long as the suspension continues, give written notice to the Company that Raytheon desires to terminate the construction agreement. Unless the Company orders Raytheon to resume performance of the suspended services within 15 days of the receipt of the notice from Raytheon, the suspended services will be deemed to have been terminated by the Company for the Company’s convenience. If the occurrence of one or more force majeure events prevents Raytheon from performing the services for a period in the aggregate of 720 days, either party may, at its option, give written notice to the other party of its desire to terminate the construction agreement.

 

Consequences of Termination

 

                  Upon any termination, the Company may, so long as the termination is pursuant to any default Raytheon will have been paid all amounts due and owing to it under the construction agreement, which will not be deemed to constitute a waiver by Raytheon of any rights to payment it may have as a result of a non-default related termination in the event of a termination pursuant to a default, at the Company’s option elect to have itself, or its designee, which may include any other affiliate or any third-party purchaser, (i) assume responsibility for and take title to and possession of the Company’s project and any or all work, materials or equipment remaining at the site and (ii) succeed automatically, without the necessity of any further action by Raytheon, to the interests of Raytheon in any or all items procured by Raytheon for the Company’s project and in any and all contracts and subcontracts entered into between Raytheon and any subcontractor with respect to the equipment specified in the construction agreement, and with respect to any or all other subcontractors selected by the Company which are materially necessary to the timely completion of the Company’s project, Raytheon will use all reasonable efforts to enable the Company, or the Company’s designee, to succeed to Raytheon’s interests thereunder.

 

                  If any termination occurs, the Company may, without prejudice to any other right or remedy it may have, at its option, finish the services by whatever method the Company may deem expedient.

 

Surviving Obligations

 

Termination of the construction agreement (i) will not relieve either party of any obligation with respect to the confidentiality of the other party’s information, (ii) will not relieve either party of any obligation which expressly or by implication survives termination of the construction agreement and (iii) except as otherwise provided in any provision of the construction agreement expressly limiting the liability of either party, will not relieve either party of any obligations or liabilities for loss or damage to the other party arising out of or caused by acts or omissions of the party prior to the effectiveness of the termination or arising out of the termination, and will not relieve Raytheon of its obligations as to portions of the services already performed or as to obligations assumed by Raytheon or the Company prior to the date of termination.

 

Default and Remedies

 

Raytheon’s Default

 

Raytheon’s events of default include: voluntary bankruptcy or insolvency; involuntary bankruptcy or insolvency; materially adverse misleading or false representation or warranty; improper assignment; failure to maintain required insurance; failure to comply with applicable laws or applicable permits; cessation or abandonment

 

23



 

of the performance of services; termination or repudiation of, or default under the related construction contract guaranty; failure to supply sufficient skilled workers or suitable material or equipment; failure to make payment when due for labor, equipment or materials; non-occurrence of either provisional acceptance or final acceptance within 90 days after the guaranteed provisional acceptance date, non-occurrence of construction progress milestones and failure proceed under a remediation plan within 90 days after the non-occurrence; and failure to remedy non-performance or non-observance of any provision in the construction agreement.

 

The Company’s Rights and Remedies

 

If Raytheon is in default of its obligations, the Company will have any or all of the following rights and remedies, in addition to any other rights and remedies that may be available to the Company under the construction agreement or at law or in equity, and Raytheon will have the following obligations:

 

                  The Company may, without prejudice to any other right or remedy the Company may have under the construction agreement or at law or in equity, terminate the construction agreement in whole or in part immediately upon delivery of notice to Raytheon. In case of the partial termination, the parties will mutually agree upon a scope change order to make equitable adjustments, including the reduction and/or deletion of obligations of the parties commensurate with the reduced scope Raytheon will have after taking into account the partial termination, to one or more of the guaranteed completion dates, the construction progress milestone dates, the contract price, the payment and milestone schedule, the Company’s project schedule, the performance guarantees and the other provisions of the construction agreement which may be affected thereby, as appropriate. If the parties are unable to reach mutual agreement as to said scope change order and the dispute resolution procedures set forth in the construction agreement are invoked, the procedures will give due consideration to customary terms and conditions under which Raytheon has entered subcontracts with third party prime contractors covering services substantially similar to those services which are not being terminated.

 

                  If requested by us, Raytheon must withdraw from the site, must assign to the Company such of contractor’s subcontracts, to the extent permitted therein, as the Company may request, and must remove the materials, equipment, tools and instruments used by, and any debris and waste materials generated by, Raytheon in the performance of the Services as the Company may direct, and we, without incurring any liability to Raytheon, other than the obligation to return to Raytheon at the completion of the Company’s project the materials that are not consumed or incorporated into the Company’s project, solely on an “as is, where is” basis without any representation or warranty of any kind whatsoever, may take possession of any and all designs, drawings, materials, equipment, tools, instruments, purchase orders, schedules and facilities of Raytheon at the site that the Company deems necessary to complete the services.

 

Assignment

 

The parties shall have no right to assign or delegate any of their respective rights or obligations under the construction agreement either voluntarily or involuntarily or by operation of law, except that the Company may, without Raytheon’s approval, assign any or all of its rights under the construction agreement (a) as collateral security to the financing parties and (b) to any transferee of the Company’s project or a substantial portion of its project so long as such assignee has financial and operational capabilities that are either substantially similar to the Company’s at the time or otherwise are such that the assignment could not reasonably be expected to have a material adverse effect on Raytheon’s rights and obligations under the construction agreement.

 

Maintenance Services Agreement

 

The Company has entered into the Maintenance Program Parts, Shop Repairs and Scheduled Outage Technical Field Assistance (“TFA”) Services Contract (the “Maintenance Services Agreement”), dated as of December 8, 1999, with Siemens Westinghouse by which Siemens Westinghouse will provide the Company with, among other things, combustion turbine parts, shop repairs and scheduled outage technical field assistance services.  The fees assessed by Siemens Westinghouse will be based on the number of Equivalent Base Load Hours (“EBH”) or Equivalent Starts (“ES”), accumulated by the applicable Combustion Turbine as adjusted for inflation. The Company has received approximately $11.0 million in rotable spare parts under this agreement.  This amount is

 

24



 

recorded as Spare Parts Inventory, under Property, Plant and Equipment, and the remaining amount owed as current and long-term liabilities in the accompanying balance sheets.

 

The maintenance services agreement became effective on the date of execution and unless terminated early, will terminate upon completion of shop repairs performed by Siemens Westinghouse following the twelfth scheduled outage of the applicable combustion turbine or sixteen years from the date of execution, whichever occurs first, unless the Company exercises its right to terminate the agreement after the first major outage of the turbines. The estimated timeframe for the completion of the first major outages is 2011.

 

Scope of Work

 

During the term of the maintenance services agreement, and in accordance with the scheduled outage plan, Siemens Westinghouse is required to do the following:

 

                  deliver the type and quantity of new program parts for installation of the combustion turbine;

 

                  repair/refurbish program parts and equipment for the combustion turbine;

 

                  provide miscellaneous hardware;

 

                  provide the Company with material safety data sheets for all hazardous materials Siemens Westinghouse intends to bring/use on the site;

 

                  provide the services of a maintenance program engineer to manage the combustion turbine maintenance program;

 

                  provide technical field assistance, or TFA Services, which involves advice and consultation for the disassembly, inspection and assembly of various equipment; and

 

                  remove and reinstall insulation as required to complete inspections.

 

The Company is responsible for, among other things:

 

                  storing and maintaining parts, materials and tools to be used in or on the combustion turbine;

 

                  maintaining and operating the combustion turbine consistently with the warranty conditions;

 

                  ensuring that the Company’s operator and maintenance personnel are properly trained;

 

                  transporting program parts in need of repair/refurbishing; and

 

                  providing Siemens Westinghouse, on a monthly basis, with the number of equivalent starts and the number of equivalent base hours incurred by each combustion turbine.

 

The Company and Siemens Westinghouse will continue to jointly develop the scheduled outage plan. The scheduled outage plan will be consistent with the terms and conditions of the Power Purchase Agreement.

 

Early Replacement

 

If it is determined that due to normal wear and tear a program part(s) for the combustion turbine has failed or will not last until the next scheduled outage, and the part has to be repaired before the scheduled replacement period, Siemens Westinghouse will replace the program part by moving up a new program part which is otherwise scheduled to be delivered at a later date. The contract price for the replacement will not be affected if the replacement date is less than or equal to one year earlier than the scheduled outage during which the program part was scheduled to be replaced. If the actual replacement date for a program part is more than one year earlier than the scheduled outage at which point the program part was scheduled to be replaced, the early replacement will result in an adjustment to the payment schedule. Siemens Westinghouse has the final decision with regard to the replacement

 

25



 

or refurbishment associated with any program part. If the Company disputes Siemens Westinghouse’s decision, the Company may seek to resolve the dispute in accordance with the dispute resolution procedures discussed below.

 

Parts Life Credit

 

After applicable warranty periods set forth in the maintenance services agreement and the construction agreement, Siemens Westinghouse will provide a parts life credit if a program part requires replacement due to normal wear and tear prior to meeting its expected useful life. Siemens Westinghouse has the final decision with regard to actual parts life and the degree of repair or refurbishment associated with any program parts. The parts life credit will be calculated in terms of EBH’s and ES’s. The price of the replacement part will be adjusted for inflation. If the Company disputes Siemens Westinghouse’s decision, the Company may seek to resolve the dispute in accordance with the dispute resolution procedures discussed below.

 

Contract Price and Payment Terms

 

Siemens Westinghouse will invoice the Company monthly and payments are then due within 25 days. The fees assessed by Siemens Westinghouse will be based on the number of EBH’s or ES’s accumulated by the applicable combustion turbine as adjusted for changes in the consumer price index. The contract price will be the aggregate number of fees as adjusted plus any additional payment amount mutually agreed to by the parties under a change order.

 

Unscheduled Outages and Unscheduled Outage Work

 

If during the term of the maintenance services agreement an unscheduled outage occurs resulting from (i) the non-conformity of new program parts; (ii) the failing of a shop repair; (iii) a program part requiring replacement due to normal wear and tear prior to achieving its expected life in terms of EBH’s or ES’s; or (iv) the failure of a service, performed by Siemens Westinghouse, the Company will hire Siemens Westinghouse, to the extent not supplied by Siemens Westinghouse as a warranty remedy under Siemens Westinghouse’s warranties under the maintenance services agreement, to supply any additional parts, miscellaneous hardware, shop repairs and TFA Services under a change order. The Company will be entitled to any applicable parts life credit with respect to program parts as well as a discount for TFA Services. If the unscheduled outage occurs within a specified number of EBH’s of a scheduled outage and it was anticipated that the additional parts, miscellaneous hardware, shop repairs and TFA Services to be used in the unscheduled outage were to be used during the upcoming scheduled outage, the upcoming scheduled outage will be moved up in time to become the unscheduled outage/moved-up scheduled outage. The Company will not be required to pay any additional money for the program parts, miscellaneous hardware, shop repairs and TFA Services.

 

If any program parts are delivered by Siemens Westinghouse within 15 days of receipt of the change order, the Company will pay to Siemens Westinghouse the price for the program part set forth in the maintenance services agreement plus a specified percentage.

 

Any program part delivered after 30 days of the change order will cost the Company the price set forth in the maintenance services agreement minus a specified percentage.

 

The remedies set forth in the maintenance services agreement, and discounts on any TFA Services purchased by the Company from Siemens Westinghouse will constitute Siemens Westinghouse’s sole liability and the Company’s exclusive remedies for unscheduled outages whether its claims are based in contract, in tort, or otherwise. If Siemens Westinghouse fails to send a TFA Services representative by the end of the second day following written receipt of the unscheduled outage, the Company may hire another qualified person, at its cost, to perform the work. If the hired party proceeds to disassemble the combustion turbine to determine the case of the unscheduled outage and Siemens Westinghouse still has not provided personnel to assist with the inspection, the Company can elect to terminate the maintenance services agreement on the basis that Siemens Westinghouse has failed to perform a material obligation.

 

Changes in Operating Restrictions

 

The maintenance services agreement requires that each combustion turbine will be operated in accordance with the requirements of the Power Purchase Agreement and prudent utility practices, with 8,000 EBH’s/year and 250 ES/ year by using natural gas and water. Should the actual operations differ from these operating parameters which

 

26



 

causes a scheduled outage to be planned/performed earlier or later than as expected, then, under a change order, an adjustment in the scope, schedule, and price will be made.

 

Warranties

 

Siemens Westinghouse warrants that the new program parts, miscellaneous hardware and any shop repairs will conform to standards of design, materials and workmanship consistent with generally accepted practices of the electric utility industry. The warranty period with respect to program parts, hardware and shop repair is until the earlier of one year from the date of installation of the original program part or hardware, a specific number of starts or fired hours after installation of the program parts and hardware, or three years from the date of delivery of the original program part, hardware, and in the case of shop repair, three years from completion of the work. Warranties on the program parts and hardware will not expire more than one year after the conclusion of the maintenance services agreement. Siemens Westinghouse will repair or replace any program part or hardware, at its cost, if notified of any failure or non-conformity of the program part or hardware during the warranty period.

 

Siemens Westinghouse also warrants that the services of its personnel and technical information transmitted will be competent and consistent with prudent utility practices and the services will comply in all material respects with laws and will be free from defects in workmanship for a period of one year from the date of completion of that item of services. The warranties on the services will expire no later than one year after the termination or end of the term of the maintenance services agreement.

 

In addition, Siemens Westinghouse warrants that any program part removed during a scheduled outage and delivered by the Company to the designated facility for repair will be repaired and delivered by Siemens Westinghouse within 26 weeks. If Siemens Westinghouse does not deliver the program part within this time frame or does not provide a new program part in lieu of the program part being shop repaired and an outage occurs which requires such a program part, Siemens Westinghouse will pay the Company liquidated damages for each day the program part is not repaired and delivered the aggregate of which liquidated damage payments will not exceed a maximum annual cap. If upon reaching the maximum cap on aggregate liquidated damages, Siemens Westinghouse still has not repaired and delivered the program part, the Company may elect to terminate the maintenance services agreement because Siemens Westinghouse will be considered to have failed to perform its material obligations.

 

Except for the express warranties set forth in the maintenance services agreement, Siemens Westinghouse makes no other warranties or representations of any kind. No implied statutory warranty of merchantability or fitness for a particular purpose applies.

 

The warranties provided by Siemens Westinghouse are conditioned upon (i) the Company’s receipt, handling, storage, operation and maintenance of the Company’s project, including any program parts and miscellaneous hardware, being done in accordance with the terms of the combustion turbine instruction manuals; (ii) operation of the combustion turbine in accordance with the terms of the maintenance services agreement; (iii) repair of accidental damage done consistently with the equipment manufacturer’s recommendations; (iv) the Company’s providing Siemens Westinghouse with access to the site to perform its services under the maintenance services agreement; and (v) hiring Siemens Westinghouse to provide TFA Services, program parts, shop repairs and miscellaneous hardware required to dissemble, repair and reassemble the combustion turbine.

 

Termination

 

The Company may terminate the maintenance services agreement if (i) specific bankruptcy events affecting Siemens Westinghouse occur; (ii) Siemens Westinghouse fails to perform or observe in any material respect any provision in the maintenance services agreement and fails to (a) promptly commence to cure and diligently pursue the cure of the failure or (b) remedy the failure within 45 days after Siemens Westinghouse receives written notice of the failure; (iii) the Company terminates the construction agreement due to Raytheon’s default thereunder or due to the Company’s inability to obtain construction financing or environmental operating permits; or (iv) Raytheon terminates the construction agreement for any reason other than the Company’s default thereunder. Notwithstanding the foregoing, the Company may terminate the maintenance services agreement at any time for convenience following the completion of the first major outage of both combustion turbine generators. In addition, the maintenance services agreement will automatically terminate if (i) the Company terminates the construction agreement for reasons other than (a) the default of Raytheon and (b) the Company’s inability to obtain permits for the Company’s project or (ii) Raytheon terminates the construction agreement for the Company’s default thereunder.

 

27



 

If such termination occurs, Siemens Westinghouse will discontinue any work or services being performed and continue to protect the Company’s property. Siemens Westinghouse will transfer title to the Company and deliver any new program parts and miscellaneous hardware already purchased by the Company. The Company will pay Siemens Westinghouse those amounts owed at the time of termination.

 

Siemens Westinghouse may also terminate the maintenance services agreement if: (i) the Company fails to make payments or (ii) specific bankruptcy events affecting the Company occur. Siemens Westinghouse cannot terminate the maintenance services agreement if the Company pays outstanding amounts due within 90 days. Upon termination, Siemens Westinghouse will stop all work, place no additional orders, protect the Company’s property and deliver the property to the Company upon the Company’s instructions. Siemens Westinghouse will be entitled to payment for work performed up until its termination of the maintenance services agreement, and to all outstanding fees and reasonable costs associated with the termination.

 

Limitation of Liability

 

Each party agrees that, except to the extent liquidated damages provided in the maintenance services agreement are so considered, neither Siemens Westinghouse, nor its suppliers, nor will the Company under any circumstances be liable for: any indirect, special, incidental or consequential loss or damage whatsoever; damage to or loss of property or equipment; loss of profits or revenues; loss of use of material, equipment or power system; increased costs of any kind, including but not limited to capital cost, fuel cost and cost of purchased or replacement power, or claims of the Company’s customers.

 

The Company agrees that the remedies provided in the maintenance services agreement are exclusive and that under no circumstances will the total aggregate liability of Siemens Westinghouse during a given year exceed 100% of the contract price payable to Siemens Westinghouse for that given year under the maintenance services agreement. The Company further agrees that under no circumstances will the total aggregate liability of Siemens Westinghouse for liquidated damages during a given year exceed a specified percentage of the contract price payable to Siemens Westinghouse for that given year under the maintenance services agreement. The Company further agrees that under no circumstances will the total aggregate liability of Siemens Westinghouse exceed a specified percentage of the contract price payable to Siemens Westinghouse under the maintenance services agreement.

 

Force Majeure

 

Neither party will be liable for failure to perform any obligation or delay in performance, excluding payment, to the extent the failure or delay is caused by any act or event beyond the reasonable control of the affected party or Siemens Westinghouse’s suppliers; so long as the act or event is deemed to be a force majeure and is not the fault or the result of negligence of the affected party and the party has been unable by exercise of reasonable diligence to overcome or mitigate the effects of the act or event. Force majeure includes: any act of God; act of civil or military authority; act of war whether declared or undeclared; act, including delay, failure to act, or priority, of any governmental authority; civil disturbance; insurrection or riot; sabotage; fire; inclement weather conditions; earthquake; flood; strikes, work stoppages, or other labor difficulties of a regional or national character which are not limited to only the employees of Siemens Westinghouse or its subcontractors or suppliers and which are not due to the breach of an applicable labor contract by the party claiming force majeure; embargo; fuel or energy shortage; delay or accident in shipping or transportation to the extent attributable to another force majeure; changes in laws which substantially prevent a party from complying with its obligations in conformity with its requirements under the maintenance services agreement or failure or delay beyond its reasonable control in obtaining necessary manufacturing facilities, labor, or materials from usual sources to the extent attributable to another force majeure; or failure of any principal contractor to provide equipment to the extent attributable to another force majeure. Force majeure will not include: (i) economic hardship, (ii) changes in market conditions or (iii) except due to an event of force majeure, late delivery of program parts or other equipment.

 

If a delay in performance is excusable due to a force majeure, the date of delivery or time for performance of the work will be extended by a period of time reasonably necessary to overcome the effect of the force majeure and if the force majeure lasts for a period longer than 30 days and the delay directly increases Siemens Westinghouse’s costs or expenses, the Company, after reviewing Siemens Westinghouse’s additional direct costs and expenses, will reimburse Siemens Westinghouse for its reasonable additional direct costs and expenses incurred after 30 days from the beginning of the force majeure resulting from said delay.

 

28



 

Environmental Compliance

 

Siemens Westinghouse will indemnify the Company from any fines, penalties, expense, loss or liability, including the costs of clean-up, incurred by the Company as a result of (i) Siemens Westinghouse’s failure to meet its obligations under the maintenance services agreement or (ii) any spills of hazardous waste or oil, petroleum or petroleum products to the environment which are attributable to and occur during Siemens Westinghouse’s performance, or the performance of its contractors or subcontractors, of the workscope obligations at the site under the maintenance services agreement.

 

The Company will indemnify Siemens Westinghouse from any fines, penalties, expense, loss or liability incurred by Siemens Westinghouse as a result of the Company’s failure to meet its obligations under the maintenance services agreement. The Company will have no responsibility or liability with regard to any hazardous waste or oil, petroleum or petroleum products which were spilled by Siemens Westinghouse, or any other of its contractors or subcontractors performing workscope obligations at the site.

 

Fleetwide Issue Notification

 

During the term of this agreement, if Siemens Westinghouse becomes aware of a fleetwide issue involving the Siemens Westinghouse 501F combustion turbine which may have a deleterious effect on the Company’s combustion turbines, Siemens Westinghouse will, within a reasonable time of becoming aware of the fleetwide issues, notify the Company thereof, and if the fleetwide issue requires an additional repair or replacement of a program part or miscellaneous hardware to be performed, the additional repair or replacement will be performed in accordance with the provisions of the maintenance services agreement.

 

Interconnection Agreement

 

The Company has entered into a Generation Facility Transmission Interconnection Agreement, dated as of April 27, 1999 with JCP&L, for the installation, operation and maintenance of the facilities necessary to interconnect the Company’s facility to JCP&L’s transmission system. Under the interconnection agreement, the Company and JCP&L constructed, own, operate and maintain the interconnection facilities. The Company is responsible for all of the costs of construction, operation and maintenance of the interconnection facilities, including those owned by JCP&L. The Company has been importing electricity from the transmission system to support commissioning of the facility since July 2001 and the interconnection facilities have exported power to the transmission system since that time.  At December 31, 2002, the interconnection facilities and protective gas apparatus needed to generate and deliver net electric and/or ancillary services to the electric delivery point had been completed as required under the Power Purchase Agreement.

 

Company Market-Based Tariff Petition

 

FERC approval of the Company’s market-based tariff petition was received on June 22, 2001.

 

JCP&L’s Obligations

 

The Company has entered into an interconnection installation agreement, by which JCP&L has installed, at the Company’s cost and expense, the JCP&L interconnection facilities. The JCP&L interconnection facilities, together with the facilities that the Company has installed, are necessary to allow the interconnection of the Company’s facility with the transmission system of JCP&L. The JCP&L interconnection facilities which include, but are not limited to, certain substation protective relaying equipment and two 230 kV 2-cycle circuit breakers, are owned, maintained and operated by JCP&L, at the Company’s cost and expense. The remainder of the interconnection facilities have been installed and are owned, maintained and operated by the Company.

 

JCP&L has completed the installation of the JCP&L interconnection facilities necessary to permit the Company to meet the Company’s construction agreement requirement to energize the switch yard and commence commissioning of the Company’s facility.  The Company has been importing electricity from the transmission system to support commissioning of the facility since July 2001 and the interconnection facilities have exported power to the transmission system since that time.  The cost of these interconnection facilities was approximately $5.1 million, and is included on the balance sheet as property, plant and equipment.

 

29



 

The Company’s Obligations

 

The Company has installed and owns, operates and maintains a portion of the interconnection facilities, including, but not limited to, a 230 kV switchyard, including generator step up transformers, instrument transformers, revenue metering, power circuit breakers, control and protective relay panels, supervisory control and data acquisition equipment, and protective relaying equipment.

 

The Company is obligated to give prior notice to JCP&L before undertaking any additions, modifications or replacements to the Company’s facility or its interconnection facilities that will increase the generating capacity of the Company’s facility or could reasonably be expected to affect the transmission system, the JCP&L Interconnection Facilities or the operation of the Company’s facility. The Company must reimburse JCP&L for all costs incurred by JCP&L associated with any modifications, additions or replacements that it must make to the transmission system or the JCP&L Interconnection Facilities, as reasonably required by JCP&L, in connection with the Company’s proposed addition, modification or replacement at the Company’s facility. The Company is obligated to modify its portion of the interconnection facilities as may be required to conform to changes in good utility practice or as required by PJM Interconnection, L.L.C., which is the independent system operator that operates the transmission system to which the Company’s facility will be interconnected.

 

The Company is obligated to keep the Company’s facility insured against loss or damage in accordance with the minimum coverages specified in the Interconnection Agreement.

 

Operation and Maintenance of Interconnection Facilities

 

The parties are obligated to operate and maintain their respective portions of the interconnection facilities in accordance with good utility practices and the requirements and guidelines of PJM and JCP&L.

 

JCP&L will have the right to disconnect the Company’s facility from its transmission system and/or curtail, interrupt or reduce the output of the Company’s facility when operation of the Company’s facility or the interconnection facilities adversely affects the quality of service rendered by JCP&L or interferes with the safe and reliable operation of its transmission system or the regional transmission system. JCP&L, however, is obligated to use reasonable efforts to minimize any disconnection, curtailment, interruption or reduction in output.

 

In accordance with good utility practice, JCP&L may remove the interconnection facilities from service as necessary to perform maintenance or testing or to install or replace equipment on the interconnection facilities or the transmission system. JCP&L is obligated to use due diligence to restore the interconnection facilities to service as promptly as practicable.

 

In addition, if the Company fails to operate, maintain, administer, or insure its facility or its portion of the interconnection facilities, JCP&L may, following 30 days notice and opportunity to cure the failure, disconnect the Company’s facility from the transmission system.

 

Revenue Metering

 

Revenue meters, which are part of the interconnection facilities, will be installed to measure the transfer of electrical energy between the parties at the point of interconnection. The revenue meters have been installed at the Company’s expense and will be owned, maintained and repaired by JCP&L, also at the Company’s expense. JCP&L has provided, at the Company’s expense, telemetering equipment which has been installed by us, to retrieve certain information. The revenue meters are to be tested at least once every two years, or more frequently at the Company’s request. Any revenue meter found to be inaccurate by greater than 1% is to be adjusted, repaired or replaced.

 

Land Rights and Access

 

The Company has granted to JCP&L the right of reasonable access and all necessary rights of way, easements, and licenses as JCP&L may require to install, operate, maintain, replace and remove the revenue meters and other portions of the JCP&L interconnection facilities.

 

30



 

Force Majeure

 

If either party is delayed in or prevented from performing or carrying out its obligations under the interconnection agreement by reason of force majeure, the party will not be liable to the other party for or on account of any loss, damage, injury or expense resulting from or arising out of the delay or prevention; however, the party encountering the delay or prevention will use due diligence to remove the cause or causes thereof.

 

Default

 

The events of default under the interconnection agreement are:

 

                  breach of a material term or condition and uncured failure to provide a required schedule, report or notice;

 

                  failure or refusal of a party to permit the representatives of the other party access to maintenance records, or its interconnection facilities or protective apparatus;

 

                  appointment by a court of a receiver or liquidator or trustee that is not discharged within 60 days, issuance by a court of a decree adjudicating a party as bankrupt or insolvent or sequestering a substantial part of its property that has not been discharged within 60 days after its entry, or filing of a petition to declare a party bankrupt or to reorganize a party under the Federal Bankruptcy Code or similar state statute that has not been dismissed within 60 days;

 

                  voluntary filing by a party of a petition in bankruptcy or consent to the filing of a bankruptcy or reorganization petition, an assignment for the benefit of creditors, an admission by a party in writing of its inability to pay its debts as they come due, or consent to the appointment of a receiver, trustee, or liquidator of a party or any part of its property; and

 

                  failure to provide the other party with reasonable written assurance of the party’s ability to perform any of the material duties and responsibilities under the interconnection agreement within 60 days of a reasonable request for the assurance.

 

Upon an event of default, the non-defaulting party may give notice of the event of default to the defaulting party. The defaulting party will have 60 days following the receipt of the notice to cure the default or to commence in good faith the steps necessary to cure a default that cannot be cured within that 60-day period. If the defaulting party fails to cure its default within 60 days or fails to take the steps necessary to cure a default that cannot be cured within a 60-day period, the non-defaulting party will have the right to terminate the interconnection agreement.

 

JCP&L will have the right to operate and/or to purchase specific equipment, facilities and appurtenances from the Company that are necessary for JCP&L to operate and maintain its transmission system if (i) the Company commences bankruptcy proceedings or petitions for the appointment of a trustee or other custodian, liquidator, or receiver; (ii) a court issues a decree for relief of the Company or appoints a trustee or other custodian, liquidator, or receiver for the Company or a substantial part of the Company’s assets and the decree is not dismissed within 60 days or (iii) the Company ceases operation for 30 consecutive days without having an assignee, successor, or transferee in place.

 

Operations Agreement and Services Agreement

 

The Company entered into a Development and Operations Services Agreement (the “Operations Agreement”), dated as of March 10, 2000, with AES Sayreville under which AES Sayreville is providing, operating and maintenance services for the Company’s facility for a period of 32 years. Under the Operations Agreement, AES Sayreville is responsible for, among other things, preparing plans and budgets related to start-up and commercial operation of the Company’s facility, providing qualified operating personnel, making repairs, purchasing consumables and spare parts (not otherwise provided under the maintenance services agreement) and providing other services as needed according to industry standards.

 

AES Sayreville is compensated for its maintenance and operation services on a cost basis, and it also receives certain management fees which it passes on to The AES Corporation.  For the years ended December 31, 2004, 2003

 

31



 

and 2002, the Company paid AES Sayreville a total of $5.3 million, $5.3 million and $4.4 million, respectively, for their services.

 

Under a services agreement between AES Sayreville and The AES Corporation, The AES Corporation has and continues to provide to AES Sayreville all of the personnel and services necessary for AES Sayreville to comply with its obligations under the operations agreement.

 

Water Supply Agreement

 

The Company has entered into a Water Supply Agreement dated as of December 22, 1999 with the Borough of Sayreville (“Borough”) under which the Borough will provide untreated water to the Company’s facility.

 

Supply of Untreated Water

 

Untreated Water Supply

 

The Borough of Sayreville is in the final stages of approval of the Lagoon Water Pipeline, Lagoon Pumping Station, and Sayreville Interconnection Number 2.  The Company was responsible for selection of a contractor and for payment of all costs.  The pipeline construction has been completed.  The construction contract for the Pumping Station was awarded and is completed.  Startup and commissioning of this system started May 1, 2002.  Subsequent to the completion of the Lagoon Pumping Station and the Lagoon Water Pipeline, the Borough has made available to the Company’s facility a supply of untreated water from the South River that is up to 4.6 million gallons per day and 1.53 billion gallons per year.  The Borough must use reasonable efforts to maintain the Lagoon’s water level at an elevation of 29 feet, but during periods when water cannot be drawn from the South River, the Lagoon’s water level must not be drawn to elevations below 20 feet. During periods when either the Lagoon’s water level is below 20 feet and water cannot be drawn from the South River or when water from the Lagoon is needed to ensure a supply of treated water to Borough treated water customers, the Borough must supply the Company’s facility with water drawn from the Duhernal aquifer and transported through the Duhernal water pipeline.

 

Compensation

 

The cost of the pipeline and pumping station was approximately $678,000 and $1.71 million, respectively.  The Company has paid the pipeline and pumping station projects in full, as of December 31, 2003. In addition, the Company paid the Borough an initial payment of $150,000 from the bond proceeds, which was credited to the Company’s account and was used to offset the cost of untreated water purchased during the Company’s project’s start-up and testing phase and during the first year of operation.  If the Borough incurs additional costs from Middlesex Water Company as a result of the Borough providing the Company with Duhernal Water, the Company also must pay the Borough for those additional costs. The Company must pay the Borough monthly for all untreated water delivered to the point of delivery during the prior month. The base rate for untreated water supplied from the South River is $216 per million gallons, which includes $53 per million gallons to cover operations, maintenance and administrative costs and $163 per million gallons to cover past infrastructure costs. The operations and maintenance rate will be escalated in accordance with the percentage changes in water rates that are applicable to other Borough water customers. The base rate for untreated water delivered from the Duhernal aquifer is $932 per million gallons which includes $785 to cover the operations, maintenance and administrative costs and $147 to cover acquisition costs. The operations and maintenance portion of the base rate for water delivered from the Duhernal aquifer is also subject to escalation in accordance with the percentage changes in water rates that are applicable to other Borough water customers.

 

With respect to each contract year there is a minimum bill amount, which is initially $300,000 per year. One-twelfth of the minimum bill amount must be paid each month. The minimum bill amount is adjusted as follows:

 

                  For the first contract year it is reduced by the amount of the initial payment;

 

                  it is reduced by an amount equal to the product of (x) the quantity of untreated water that would have been delivered but for service interruptions by the Borough and (y) the rate for untreated water delivered from the South River; and

 

32



 

                  starting with 8th contract year and with six months prior written notice, the Company has the right to reduce the minimum bill amount for any contract year by reducing the annual quantity of water to be provided by up to 15%. Starting with the 21st contract year the Company may reduce the annual quantity to be delivered without limit.

 

Service Interruptions

 

In the event that there is an interruption in the delivery of untreated water attributable to a break in the infrastructure, the Borough will provide a shortfall notice and the Borough and the Company will agree on the best way to repair the infrastructure and restore service. If the Borough fails to restore service within a reasonable period of time, the Company may, at the Company’s expense, contract with contractors reasonably approved by the Borough to remedy the interruption.

 

Infrastructure and Real Estate Rights—The Lagoon Water Pipeline, Lagoon Pumping Station and Sayreville Interconnection Number 2

 

The Borough has designed, at the Company’s expense, the Lagoon Water Pipeline, Lagoon Pumping Station and Sayreville Interconnection Number 2 in conformance with standard water system practice. The Borough was responsible for obtaining, at the Company’s expense, all necessary government approvals. The Borough and the Company have cooperated to obtain, at the Company’s expense, the real estate rights necessary for the construction, operation and maintenance of the Lagoon Water Pipeline, Lagoon Pumping Station and Sayreville Interconnection Number 2. The Borough was not required to exercise its power of eminent domain to obtain the necessary real estate rights. The Company obtained easement rights from two adjacent property owners and the Borough of Sayreville. The Company also obtained permission from the New Jersey State House Commission to cross property designated as “Green Acres” by the New Jersey Department of Protection. Upon completion and testing of the Lagoon Water Pipeline, Lagoon Pumping Station and Sayreville Interconnection Number 2, the Company executed, without being compensated by the Borough, the documents necessary to evidence the Borough’s ownership of those facilities in November 2003.

 

Operation and Maintenance of Infrastructure

 

The Borough will operate and maintain all infrastructure necessary to supply the untreated water to the project boundary. The Company will reimburse the Borough for its associated maintenance and replacement costs.

 

The Borough will own and maintain metering equipment to measure the delivery of untreated water from each source to the point of delivery and will transmit a signal of the measurements to the Borough, which uses the information to compile billing invoices. At least once every five years, or more often if requested by either party, the Company must test the metering equipment. If the tests reveal that the metering equipment is inaccurate, the equipment must be recalibrated or replaced and a billing adjustment may be made.

 

Infrastructure Studies and Additions

 

The Company pays for the actual cost, subject to a mutually agreed upon cap, of infrastructure studies to determine the costs and benefits of (i) installing a new pipeline and (ii) improving the existing South River intake structure. The Company will have the right to pay for the upgrades, improvements and/or new infrastructure that may be identified as necessary or desirable by the studies in exchange for the benefits allowed with their implementation. Other water users that benefit from the improvements will pay a pro-rata portion of the costs of the improvements.

 

If the Borough or the Company reasonably determines that capital improvements to the infrastructure are required, the party will notify the other party and the parties will meet in good faith to determine the scope of the capital improvements. The Company will pay for its costs and expenses arising from the capital improvements as well as those of the Borough. If the Company damages either infrastructure or capital improvements, the Company will restore the damaged portions thereof or pay the Borough to restore the damaged portions.

 

Land Development Plan

 

The Company entered into an agreement with the Borough of Sayreville by which the Company will develop and implement a plan to replace trees which were removed during clearing of the facility site.  The Land

 

33



 

Development Plan is required for final site approval. The estimated cost of the plan is approximately $425,000.  The Company is in the process of selecting a contractor to perform the service and no payments have been made as of December 31, 2004.  On July 23, 2003, the project was secured by a letter of credit issued by Union Bank of California for $425,000 with the Borough of Sayreville as the beneficiary.  This irrevocable standby letter of credit had an expiration date of June 30, 2004, but was automatically extended for another one-year period. On August 19, 2004, AES secured a performance bond for $539,493 relating to the tree replacement and other site improvements. This bond replaces the previous letter of credit and represents the amount potentially due if there is a failure of AES Red Oak, LLC to take action regarding the plan.

 

Additional Obligations of the Parties

 

Additional Obligations of the Borough

 

The Borough must use its best efforts to either (i) amend its existing permit, which limits pumping from the Lagoons to 1,000,000 gallons of water per day or (ii) obtain or change any other permits necessary to allow it to meet its obligations under the water supply agreement. The Borough must provide the Company with written invoices by not later than the 15th of each month. The amounts due under the invoices are due within 30 days of receipt. The Borough must provide the Company and the financing parties with escorted access to any infrastructure or other property owned by the Borough to which the Company or the financing parties reasonably request access.

 

The Company’s Additional Obligations

 

The Company must provide the Borough with notice of any violation by the Borough of applicable government approvals related to the delivery of untreated water. Not later than the 15th day of each month, the Company must provide the Borough with a detailed invoice listing any amounts due to the Company under the water supply agreement.

 

Force Majeure

 

If either party is unable to carry out any obligation under the water supply agreement due to an event of force majeure, the water supply agreement will remain in effect but the obligation will be suspended for the period necessitated by the force majeure, as long as:

 

                  the affected party gives the other party written notice within 48 hours of the occurrence of the force majeure;

 

                  the suspension of performance is of no greater scope and no longer than required by the force majeure; and

 

                  the non-performing party uses its best efforts to remedy its inability to perform.

 

Term

 

The water supply agreement has a term of 30 years with an option to extend for up to four additional five year terms. The agreement may be terminated by the Company and by the Borough under some circumstances including; (i) the Company’s failure to deliver a commencement notice on or prior to December 31, 2003; (ii) the occurrence of a bankruptcy event affecting the other party; and (iii) failure of a party to perform a material obligation within the time contemplated and the continuation of the failure for a period of 30 days or more.

 

ITEM 2.                              PROPERTIES

 

The Company’s principal property is the project site, on which the Company’s facility is located, which the Company owns. The site is located in the Borough of Sayreville, Middlesex County, New Jersey on an approximately 62-acre parcel of land. The Company has access, utility and construction easements and licenses across neighboring property. The Company has title insurance in connection with the Company’s property rights.

 

Under the Company’s financing documents, its rights and interests in the Company’s property are encumbered by mortgages, security agreements, collateral assignments and pledges for the benefit of the Company’s bondholders and other senior creditors.

 

34



 

The Company’s facility consists of an approximately 830 megawatt (net) gas-fired combined cycle electric generating facility. The Company’s facility was designed, engineered, procured and constructed for the Company by WGI and Raytheon, as successor guarantor, under a fixed-price, turnkey construction agreement.  Among other components, the Company’s facility uses three Siemens Westinghouse model 501F combustion turbines, three heat recovery steam generators and one multicylinder steam turbine. Under a maintenance services agreement, Siemens Westinghouse is providing the Company with specific combustion turbine maintenance services and spare parts in respect of each combustion turbine until sixteen years after execution of the agreement or the twelfth planned outage of the combustion turbine, whichever is earlier, unless the Company exercises its right to cancel the agreement after the first major outage of the combustion turbines which will be after approximately the eighth year of operation of the facility. Under the Power Purchase Agreement, Williams Energy or its affiliates is supplying the fuel necessary to allow the Company to provide capacity, fuel conversion and ancillary services to Williams Energy. AES Sayreville has provided development, construction management, and operations and maintenance services for the Company’s facility under an operations agreement. The Company has provided installation, operation and maintenance of facilities necessary to interconnect the Company’s facility to JCP&L’s transmission system under an interconnection agreement.

 

ITEM 3.                              LEGAL PROCEEDINGS

 

Williams Energy - On November 4, 2003, the Company and Williams Energy, through arbitration, settled a dispute regarding the date of commercial operation and the proper interpretation of certain provisions of the Power Purchase Agreement relating to amounts the Company claimed were payable by Williams Energy. The arbitration related to disputed amounts of approximately $7.6 million, which included a $594,000 payment extension dispute and a $7 million commercial operation start date dispute.  Under the settlement, Williams made a cash payment to the Company of $4,050,153 on November 14, 2003, which included $225,055 of interest from October 2002 to the payment date, and the Commercial Operation Date was deemed to be September 28, 2002.  The related revenue had been substantially recorded in 2002, with the remaining amount recorded in the fourth quarter of 2003. This payment settled all payment obligations between the parties for the month of September 2002 with respect to the Commercial Operation Date under the Power Purchase Agreement.  From the Company’s perspective, the cash payment has the economic effect of recognizing a Commercial Operation Date prior to of September 28, 2002. The Company is currently disputing $1.4 million of merchant price, testing gas and other charges with Williams Energy that the Company contends Williams Energy owes to us. These charges were not part of the arbitration discussed above.

 

Raytheon - On October 28, 2004, the Company received a complaint filed by Raytheon in the State of New York. In the complaint, Raytheon is seeking to recover $30,302,269, which represents the amount Red Oak drew down on the letter of credit on August 26, 2004, attorneys’ fees and costs, and also to recover up to $110 million of net expense Raytheon claims to have incurred in good faith under the governing guaranty and construction agreements.  The Company filed an answer and counterclaim on December 13, 2004, in which it denied liability to Raytheon, asserted various defenses and countersued Raytheon for breach of the EPC Agreement and Settlement Agreement, breach of express warranties under the EPC Agreement, and fraudulent misrepresentation and concealment.  The Company claimed damages of not less than $140 million and attorneys’ fees and costs to the extent allowable.  Raytheon moved to dismiss the Company’s fraudulent misrepresentation and concealment claim and to limit Company’s damages on January 14, 2005.  The Company filed its opposition to the motion to dismiss and also filed an amended counterclaim on February 18, 2005.  Thereafter, Raytheon agreed to withdraw its motion to dismiss.  On March 4, 2005, Raytheon filed a motion for summary judgment that seeks the return of $16,311,711 of the Letter of Credit draw.  Company has not yet filed its opposition to the motion, and Raytheon has not yet filed an answer to the amended counterclaim. The Company has recorded the $30.3 million as a current liability, but has not accrued any additional amounts with respect to Raytheon’s claims. The Company believes it has meritorious defenses to the claims asserted by Raytheon against it and intends to defend the lawsuit and pursue its counterclaims vigorously.

 

ITEM 4.                              SUBMISSION OF MATTERS TO A VOTE OF SECURITY HOLDERS

 

Not applicable pursuant to General Instruction I of the Form 10-K.

 

35


 


 

PART II

 

ITEM 5.                              MARKET FOR REGISTRANT’S COMMON EQUITY AND RELATED STOCKHOLDER MATTERS

 

There is no market for the Company’s equity interests. All of the Company’s member interests are owned by the Company’s parent, AES Red Oak, Inc., a wholly owned subsidiary of The AES Corporation.  On December 22, 2003, the Company declared and paid a $1.05 million dividend to AES Red Oak, Inc. No dividends were paid in 2004.

 

ITEM 6.                              SELECTED FINANCIAL DATA

 

Not applicable pursuant to General Instruction I of the Form 10-K.

 

ITEM 7.                              MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS

 

The following discussion and analysis should be read in conjunction with the Company’s financial statements and the notes thereto included elsewhere in this annual report. The following discussion involves forward-looking statements. The Company’s actual results may differ significantly from the results suggested by these forward-looking statements. See “Cautionary Note Regarding Forward-Looking Statements.”

 

General

 

AES Red Oak, L.L.C. (“the Company”) was formed on September 13, 1998 to develop, construct, own, operate and maintain the Company’s facility. The Company was dormant until March 15, 2000, the date of the sale of the Company’s senior secured bonds. The Company obtained $384 million of project financing from the sale of the senior secured bonds. The total cost of the construction of the Company’s facility was approximately $450 million, which was financed by the proceeds from the Company’s sale of the senior secured bonds, equity contributions, operating revenues and the amount of liquidated damages received from Raytheon through August 10, 2002 under the Construction Agreement, as described below. In late September 2000, the Company consummated an exchange offer whereby the holders of the Company’s senior secured bonds exchanged their privately placed senior secured bonds for registered senior secured bonds.

 

The Company reached provisional acceptance on August 11, 2002, risk transfer on August 13, 2002, and took the position that the Company was commercially available on September 1, 2002.  Williams Energy disputed the September 1, 2002, commercial operation date and informed the Company that it recognized commercial availability of the facility as of September 28, 2002.  On November 4, 2003, a settlement was reached and a commercial operation date of September 28, 2002 was agreed upon.  See “Item 3 – Legal Proceedings”.

 

Since achieving commercial operations, under the Power Purchase Agreement with Williams Energy, the Company is eligible to receive variable operations and maintenance payments, total fixed minimum capacity payments, energy exercise fee payments (each as defined in the Power Purchase Agreement) and other payments for the delivery of fuel conversion, capacity and ancillary services.  During 2003 the PJM market, into which the Company’s generation is distributed, experienced a general decline in the amount paid for electricity. There was also a marked increase in the cost of natural gas. As a result, Williams Energy dispatched the Company’s facility on a very limited basis. The Company’s facility was called on to generate only 21% of the year in 2004 and only 14% of the year in 2003. Accordingly, the minimum capacity payments have been the Company’s primary source of operating revenues, representing $62.5 million and $62.0 million of the Company’s total revenues for the years ended December 31, 2004 and 2003, respectively.

 

Based upon current market conditions and projections from Williams Energy, the Company anticipates a dispatch level in 2005 to be within the range of the levels for 2003 and 2004.  In the event that these market conditions do not improve, and Williams Energy does not dispatch the Company’s facility at all in 2005, the Company believes that the fixed capacity payments are sufficient to meet the cash demands of the Company’s business, but the Company will require the additional revenue from such fuel conversion services to be profitable.

 

The Company is concerned that Williams Energy will not dispatch the Company’s facility in a manner that will increase its profitability. As a result, the Company’s management is researching ways to enhance its facility’s

 

36



 

performance. The Company believes that any savings in starting the facility or improved performance will also benefit Williams Energy, with the result that Williams Energy may find it more economically feasible to dispatch the Company’s facility.

 

The following discussion presents certain financial information for the years ended December 31, 2004, 2003 and 2002.

 

Equity Contributions

 

Under an equity subscription agreement, AES Red Oak, Inc. agreed to contribute up to approximately $56.7 million to the Company to fund project costs.  As of December 31, 2002 all $56.7 million had been contributed, and there have been no further contributions other than employee stock issuances.  The equity that AES Red Oak Inc. provided to the Company was provided to it by The AES Corporation.

 

Results of Operations

 

Net income for 2004 was $0.8 million, while the first full year of operation in 2003 yielded a net loss of $0.3 million.  The Company commenced commercial operations in August 2002 and had a net loss for the year ended December 31, 2002 of $3.0 million.

 

Operating revenues were approximately $69.7 million, $64.2 million and $26.2 million for the years ended December 31, 2004, 2003 and the partial year of operations ended December 31, 2002, respectively. These amounts included fixed payments of $62.5 million, $62.0 million and $15.2 million for the years ended December 31, 2004, 2003 and 2002, respectively.  Revenues from September 2002 through December 2004 consist of capacity sales and ancillary services under the Power Purchase Agreement. Revenues for the period of August and part of September 2002 consisted of merchant revenue in this partial year of operations. The remaining amount of revenue relates to variable revenue which the Company receives when dispatched, and merchant revenue the Company earned prior to the Company’s commercial operation date in September 2002. The Company has no control over when the facility is dispatched, as that decision is made by Williams Energy based on several factors including market conditions.

 

Operating expenses were $34.5 million and $30.9 million for the years ended December 31, 2004 and 2003, respectively and $16.8 million for the partial year of operations ended December 31, 2002.  These costs are largely of a recurring nature and are discussed below.

 

Fuel purchased from Williams Energy during the period of merchant operations and testing was $0.6 million, $0.9 million and $6.9 million for the years ended December 31, 2004, 2003 and 2002, respectively. The Company purchased more fuel in 2002 in connection with the merchant operations the Company conducted in the period prior to the commercial operation date.

 

The fuel conversion volume rebate was $5.9 million and $5.8 million for the years ended December 31, 2004 and 2003, respectively and $1.6 million for the partial year of operations ended December 31, 2002. This cost represents payments to Williams and is based upon a twelve month facility utilization factor.

 

Corporate management fees were $1.6 million for each of the years ended December 31, 2004 and 2003 and was $0.6 million for the partial year of operations ended December 31, 2002. Corporate management fees are charged on a monthly basis based on a fixed amount which is adjusted annually for inflation.

 

Other operating expenses were $10.6 million and $7.2 million for the years ended December 31, 2004 and 2003, respectively and $2.0 million for the partial year of operations ended December 31, 2002.  Maintenance costs were higher in the 2004 period, largely the result of two planned combustor inspection outages, compared to only one in 2003, and other unplanned maintenance costs.

 

Depreciation expense was $11.8 million and $11.4 million for the years ended December 31, 2004 and 2003, respectively and was $4.4 million for the partial year of operations ended December 31, 2003. The increase in depreciation expense results from additional parts placed in service after planned combustor inspection outages.

 

General and administrative costs were $1.1 million and $1.7 million for the years ended December 31, 2004 and 2003, respectively and $0.4 million for the partial year of operations ended December 31, 2002. The decrease of general and administrative costs in the year ended December 31, 2004 as compared to the year ended December 31,

 

37



 

2003 primarily relates to higher legal fees in the 2003 period related to the dispute with Williams Energy of the Commercial Operation Date.

 

Total other income (expense) was approximately $(34.4) million and $(33.6) million for the years ended December 31, 2004 and 2003, respectively and $(12.5) million for the partial year of operations ended December 31, 2002. These costs are comprised of other income and expense, liquidated damages received and paid and interest income and expense.

 

Other income from interim rebates was approximately $1.4 million for the years ended December 31, 2003, and $1.0 million for the partial year of operations ended December 31, 2002. These amounts consist of interim rebates received from Raytheon under the construction agreement as a result of their failure to meet heat rate and output performance guarantees.  The Company did not invoice interim rebates in 2004, pending resolution of the Final Acceptance date with Raytheon.

 

Other (expenses) included letter of credit fees which were approximately $(1.0) million for each of the years ended December 31, 2004 and 2003 and $(.4) million for the partial year of operations ended December 31, 2002. These amounts consist of fees paid to Dresdner Bank pursuant to the Company’s debt service reserve letter of credit and reimbursement agreement and Power Purchase Agreement letter of credit and reimbursement agreement.  See “Liquidity and Capital Resources” for a description of these letters of credit.

 

For the year ended December 31, 2002, the Company recognized revenue of $1.8 million, for liquidated damages received from Raytheon for late completion payments and a construction related outage in November 2002.  This revenue was recognized in 2002 after the commercial operation date.

 

For the years ended December 31, 2003 and 2002, the Company expensed $.2 million and $1.8 million, respectively of liquidated damages paid to Williams Energy as a result of the Company’s extension of the commercial operation date and a construction related outage in November 2002.  This expense was recognized in 2002 after the commercial operation date. The Company did not incur any liquidated damages for the year ended December 31, 2004.

 

Interest income earned on invested funds, including the security collateral received from Williams Energy, the proceeds of the letter of credit from Raytheon and other available funds, was approximately $.5 million for each of the years ended December 31, 2004 and 2003, respectively and $.1 million for the partial year of operations ended December 31, 2002.  The interest income earned for the year ended December 31, 2003 included $.2 million of interest on amounts owed by, and paid as part of the arbitration settlement with, Williams Energy.  See “Item 3 – Legal Proceedings”. Excluding the interest on the arbitration settlement, interest income was approximately $.2 million higher in 2004, as compared to 2003, primarily relating to higher interest rates. The amount of interest income earned for the year ended December 31, 2003 compared to the year ended December 31, 2002 decreased as a result of a lower average balance in the construction account resulting from the Company’s use of the bond proceeds for construction of the facility.

 

Interest (expense) was approximately $(33.8) million and $(34.2) million for the years ended December 31, 2004 and 2003, respectively and $(13.2) million for the partial year of operations ended December 31, 2002. The decrease from 2003 as compared to 2004 resulted from lower principal balances after scheduled repayments. Interest expense was lower in 2002, as compared to 2004 and 2003, as interest costs prior to commencement of commercial operations were capitalized.

 

On August 13, 2002, the risk transfer date, the balance of construction in progress was transferred to Property, Plant and Equipment.  As of December 31, 2004, Property Plant and Equipment adjusted for accumulated depreciation was $399.3 million, which includes generation, building and office equipment.

 

Liquidity and Capital Resources

 

Sources and Uses of Cash

 

Since achieving commercial operations under the Power Purchase Agreement with Williams Energy the Company is eligible to receive variable operations and maintenance payments, total fixed payments, energy exercise payments (each as defined in the Power Purchase Agreement) and other payments for the delivery of fuel conversion, capacity and ancillary services.  The Company currently anticipates being dispatched by Williams

 

38



 

Energy beginning in April 2005 but can provide no assurance that this will occur.  If the facility is not dispatched, the Company’s operating revenues will consist of minimum capacity payments under the Power Purchase Agreement.  Any future operating revenues, including any minimum capacity payments received in the event that Williams Energy does not dispatch the facility, will be used to fund the Company’s generation expenses and other operations and maintenance expenses and to meet the obligations described below.

 

Since September 28, 2002, Williams Energy has not dispatched the facility to a significant degree, outside the peak summer months. The minimum capacity payments provided for under the Power Purchase Agreement have been the Company’s primary source of operating revenues, representing $62.5 million of the Company’s total revenues of $69.7 million in 2004.  The minimum cash flow from Williams under the Power Purchase Agreement is approximately $3.8 million per month for October through May and $7.9 million per month from June through September.

 

During 2004, net cash provided by operating activities was $14.1 million. The Company currently anticipates that the plant will be dispatched in future periods within a similar range as it was during 2004 and 2003 and that operating cash flow will be comparable to 2004 in 2005.  The Company also believes that cash flows from the sale of electricity and/or minimum capacity payments under the Power Purchase Agreement and funds available to be drawn under the debt service reserve letter of credit or the power purchase letter of credit will be sufficient to pay project costs, including ongoing expenses and principal and interest on the Company’s senior secured bonds, fund costs of the Company’s commercial operations and pay fees and expenses in connection with the letters of credit.

 

The Company has provided the collateral agent with a debt service reserve letter of credit in an initial stated amount of $22.0 million. The Company has also provided Williams Energy a $10 million letter of credit under the Power Purchase Agreement, which the Company refers to as the power purchase letter of credit, to support specific payment obligations under the Power Purchase Agreement. The repayment obligations with respect to any drawings under the power purchase letter of credit are the Company’s senior debt obligation. The interest rate on these loans would be the sum of a) the higher of (i) the Federal Funds Rate plus .50% and (ii) the Agent’s prime rate and b) an applicable margin rate which is based upon the rating of the Company’s senior secured bonds. Since the Company’s senior secured bonds are currently rated below investment grade, the Company’s working capital facility has been unavailable and the Company is required to pay higher fees for draws on any of the Company’s project support agreements.

 

As discussed below, Williams Energy has notified the Company that it intends to post a letter of credit for the remaining $10 million in June 2005. Under the terms of the Letter Agreement, Williams Energy has the right to recoup the Prepayment by set-off of any and all amounts owing to the Company under the Power Purchase Agreement no earlier than the June in the calendar year after the earlier of (i) The Williams Companies, Inc. regaining its investment grade rating or Williams Energy providing a substitute guaranty of investment grade rating; (ii) the beginning of Contract Year 20; or (iii) the posting of alternative credit support by Williams Energy, whichever comes first (Note 7). Williams Energy will recoup the Prepayment by set-off, beginning in July 2005, of amounts owing to the Company under the Power Purchase Agreement. The Company is currently reviewing financing facilities, comparable to the working capital agreement which expired March 31, 2005, that would allow for funds to be available for future working capital requirements, as needed (Note 6). After the Power Purchase Agreement expires, the Company plans to depend on revenues generated from market sales of electricity.  These beliefs are subject to certain assumptions, risks and uncertainties, including those set forth above under the caption “Cautionary Note Regarding Forward-Looking Statements” and there can be no assurances.

 

39



 

Contractual Obligations

 

A summary of the Company’s contractual obligations and commitments as of December 31, 2004 is presented in the table below.

 

($000’s)

 

Total

 

2005

 

2006-
2007

 

2008-
2009

 

2010 and
Thereafter

 

Notes
Reference

 

Debt Service Obligations

 

$

814,670

 

$

37,648

 

$

76,821

 

$

81,699

 

$

618,502

 

(a)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Operations Agreement

 

63,374

 

1,672

 

3,470

 

3,645

 

54,587

 

(b)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Water Supply Agreement

 

8,400

 

300

 

600

 

600

 

6,900

 

(c)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

$

886,444

 

$

39,620

 

$

80,891

 

$

85,944

 

$

679,989

 

 

 

 

(a) Debt Service Obligations (including interest)

 

The senior secured bonds were issued in two series: 8.54% senior secured bonds due 2019 (the “2019 Bonds”) in an aggregate principal amount of $224 million and 9.20% senior secured bonds due 2029 (the “2029 Bonds”) in an aggregate principal amount of $160 million.  Principal repayment dates on the 2019 Bonds are February 28, May 31, August 31, and November 30 of each year, with the final payment due November 30, 2019.  Quarterly principal repayments on the 2019 Bonds commenced on August 31, 2002.  Annual principal repayments over the life of the 2019 Bonds range from 1.0799% of original principal amount or $2.4 million to 11.2819% of original principal amount or $25.3 million.  Quarterly principal repayment of the 2029 Bonds does not commence until February 28, 2019.

 

(b) Operations Agreement

 

The Company entered into an Operations Agreement (the “Operations Agreement”), dated as of March 1, 2000 with AES Sayreville, L.L.C. by which AES Sayreville, L.L.C. provides operating and maintenance services for the Company’s facility for a period of 32 years. “See Item 1 – Business”. The fee is adjusted annually by the change in Gross Domestic Product, Implicit Price Deflator, which the Company has assumed will be 2.5% on average.  Total fees paid by the Company were $1.6 million for the year ended December 31, 2004.  Under the services agreement between AES Sayreville, L.L.C and The AES Corporation, The AES Corporation provides to AES Sayreville, L.L.C all of the personnel and services necessary for AES Sayreville, L.L.C to comply with its obligations under the Operations Agreement. These obligations are not recorded in the Company’s consolidated financial statements until services are rendered.

 

(c) Water Supply Agreement

 

The Company has also entered into a contract (the “Water Supply Agreement”), dated as of December 22, 1999, with the Borough of Sayreville (the “Borough”) pursuant to which the Borough will provide untreated water to the Company. The contract has a term of 30 years with an option to extend for up to four additional five-year terms. The Company is contractually committed to a minimum annual payment of $300,000. These obligations are not recorded in the Company’s consolidated financial statements until period has elapsed.

 

Other Commitments.

 

Maintenance Services Agreement

 

The Company has entered into the Maintenance Program Parts, Shop Repairs and Scheduled Outage TFA Services Contract (the “Maintenance Services Agreement”), dated as of December 8, 1999, with Siemens Westinghouse by which Siemens Westinghouse will provide the Company with, among other things, combustion turbine parts, shop repairs and scheduled outage technical field assistance services. The Maintenance Services Agreement became effective on the date of execution and unless terminated early, will terminate upon completion of shop repairs performed by Siemens Westinghouse following the twelfth scheduled outage of the applicable combustion turbine or 16 years from the effective date of the contract, whichever occurs first, unless the Company exercises its right to terminate the agreement after the first major outage of the turbines.

 

40



 

The Maintenance Services Agreement indicates that the Company will pay fees each month based on a stated amount for each equivalent base load hour (“EBH”) of the combustion turbines, adjusted for inflation, over the term of the agreement.  However, if a scheduled maintenance outage occurs prior to 8,000 EBH’s being accumulated since the last scheduled maintenance outage for that turbine, the Company will be invoiced the remaining amount to equate to 8,000 hours (“true-up”). In the event the Company is not required to dispatch the facility, there is no charge for that month. Accordingly, no amounts have been included in the Contractual Obligations table above.

 

The total of these payments was approximately $6.8 million, $4.7 million and $1.2 million for the years ended December 31, 2004, 2003 and 2002, respectively, which included true-ups for two planned maintenance outages in 2004 and one in 2003, as the turbines were far short of the 8,000 EBH level. Assuming a similar dispatch level in 2005 as in 2004, and the performance of one planned hot gas maintenance outage, a comparable level of payments would be expected for the year ended December 31, 2005. Based upon the Company’s current estimates, assuming a certain number of EBH’s and equivalent starts (“ES”), the first major outages would be completed by 2011 and the remaining minimum payments to Siemens Westinghouse would approximate $32 million through that period.

 

Power Purchase Agreement

 

As discussed in “Item 1-Business-Power Purchase Agreement -Security” and Footnote 7 to the Consolidated Financial Statements, pursuant to Section 18.3 of the Power Purchase Agreement, Williams Energy has provided the Company $10 million of cash and has posted a $25 million letter of credit as alternate credit support.  In the event that the Williams Companies, Inc. regains and maintains its investment grade status, provides a substitute guaranty of investment grade rating, or posts a letter of credit, the Company will be required to return the $10 million prepayment to Williams Energy. Under the terms of the Letter Agreement, Williams Energy shall have the right to recoup the Prepayment by set-off of any and all amounts owing to the Company under the Power Purchase Agreement no earlier than the June in the calendar year after the occurrence of regaining its investment grade rating or the posting of alternative credit support by Williams Energy whichever comes first (Note 7). The Company is currently reviewing financing facilities, comparable to the working capital agreement which expired March 31, 2005, that would allow for funds to be available for future working capital requirements, as needed (Note 6).  As of December 31, 2004, the Company had cash balances of approximately $41.6 million.  Williams Energy has notified the Company that it intends to post a letter of credit for the remaining $10 million in June 2005. Williams Energy will recoup the Prepayment by set-off, beginning in July 2005, of amounts owing to the Company under the Power Purchase Agreement. The $10 million prepayment, which is currently reported as restricted cash, will then be reported as unrestricted cash as amounts are effectively repaid to Williams Energy. This belief is subject to certain assumptions, risks and uncertainties, including those set forth above under the caption “Cautionary Note Regarding Forward-Looking Statements” and there can be no assurances that the Company’s operating revenues will generate sufficient cash.

 

Land Development Plan

 

The Company has entered into an agreement with the Borough of Sayreville by which the Company will develop and implement a plan to replace trees which were removed during clearing of the facility site.  The Land Development Plan is required for final site approval. The estimated cost of the plan is approximately $425,000.  The Company is in the process of selecting a contractor to perform the service and no payments have been made as of December 31, 2004.  On July 23, 2003, the project was secured by a letter of credit issued by Union Bank of California for $425,000 with the Borough of Sayreville as the beneficiary.  This irrevocable standby letter of credit had an expiration date of June 30, 2004, but was automatically extended for another one-year period. On August 19, 2004, AES secured a performance bond for $539,493 relating to the tree replacement and other site improvements. This bond replaces the previous letter of credit and represents the amount potentially due if there is a failure of AES Red Oak, LLC to take action regarding the plan.

 

Other

 

It is anticipated that the Company will incur capital expenditures of approximately $1.5 million in 2005 related to general improvements of the facility, and another $1.3 million relating to the Construction Agreement.

 

41



 

Risks that May Impact the Company’s Liquidity

 

Williams Energy is currently the Company’s sole customer for purchases of capacity, ancillary services, and energy and the Company’s sole source for fuel. Williams Energy’s payments under the Power Purchase Agreement are expected to provide all of the Company’s operating revenues during the term of the Power Purchase Agreement.

 

The payment obligations of the Williams Companies, Inc. under its guaranty of Williams Energy’s obligations under the Power Purchase Agreement were originally capped at an amount equal to approximately $510 million. Beginning on January 1 of the first full year after the commercial operation date, this guaranty cap is to be reduced semiannually by a fixed amount which is based on the amortization of the Company’s senior secured bonds during the applicable semiannual period.  As of December 31, 2004, the guarantee was capped at $501.4 million.

 

Due to the downgrade of The Williams Companies, Inc. to below investment grade, the Company and Williams Energy entered into a letter agreement dated November 7, 2002 (the “Letter Agreement”) under which Williams Energy agreed to provide the Company with a $10 million prepayment (the “Prepayment”) and certain additional collateral.  A description of the collateral that supports Williams Energy’s obligations under the Power Purchase Agreement is set forth under “Item 1-Business Power Purchase Agreement-Security” and Footnote 7 to the Company’s Consolidated Financial Statements.

 

Since the Company depends on Williams Energy for both revenues and fuel supply under the Power Purchase Agreement, if Williams Energy were to terminate or default under the Power Purchase Agreement, there would be a severe negative impact to the Company’s cash flow and financial condition which could result in a default on the Company’s senior secured bonds.  Due to the current pool prices, the Company would expect that if it were required to seek alternate purchasers of the Company’s power in the event of a default of Williams Energy, even if the Company was successful in finding alternate revenue sources, any such alternate revenue sources would be substantially below the amounts that would have been otherwise payable pursuant to the Power Purchase Agreement. There can be no assurance as to the Company’s ability to generate sufficient cash flow to cover operating expenses or the Company’s debt service obligations in the absence of a long-term power purchase agreement with Williams Energy.

 

In addition to the factors discussed above, and/or the other factors listed under the “Cautionary Note Regarding Forward-Looking Statements,” if a working capital facility continues to be unavailable, the Company could experience a negative impact on the its cash flow and financial condition, which may result in draws upon its letters of credit.

 

Business Strategy and Outlook

 

The Company’s overall business strategy is to market and sell all of the Company’s net capacity, fuel conversion and ancillary services to Williams Energy during the 20-year term of the Power Purchase Agreement. After expiration of the Power Purchase Agreement, or in the event the Power Purchase Agreement is terminated prior to its 20-year term or Williams Energy otherwise fails to perform, the Company would seek to sell the Company’s facility’s capacity, ancillary services and energy in the spot market or under a short or long-term power purchase agreement or into the PJM power pool market.  Due to recent declines in pool prices, however, the Company would expect that even if it were successful in finding alternate revenue sources, any such alternate revenues would be substantially below the amounts that would have been otherwise receivable pursuant to the Power Purchase Agreement.  There can be no assurances as to whether such efforts would be successful.

 

The Company intends to cause the Company’s facility to be managed, operated and maintained in compliance with the project contracts and all applicable legal requirements.

 

Recent and New Accounting Pronouncements

 

In January 2003, the Financial Accounting Standards Board (“FASB”) issued FIN No. 46, Consolidation of Variable Interest Entities, an Interpretation of ARB No. 51 (“FIN No. 46”).  In October 2003, FASB Staff Position No. 46-6, “Effective Date of FIN No. 46, Consolidation of Variable Interest Entities” deferred the effective date of FIN No. 46 for variable interests held by a public entity in a variable interest entity (“VIE”) that was created or acquired before February 1, 2003 to the end of the first interim or annual period ending after December 15, 2003.  In December 2003, FASB issued FIN 46 (revised December 2003), Consolidation of Variable Interest Entities, an

 

42



 

Interpretation of ARB No. 51 (“FIN 46(R)”), which clarified some requirements and incorporated several staff positions that the Company was already required to apply.  In addition, FIN 46(R) deferred the effective date for VIEs that were created or acquired before February 1, 2003 and were not considered special purpose entities (“SPEs”) prior to the issuance of the interpretation until the end of the first reporting period ending after March 15, 2004.  FIN 46(R) defines a VIE as (i) any entity in which the equity investors at risk in such entity do not have the characteristics of a controlling financial interest, or (ii) any entity that does not have sufficient equity at risk to finance its activities without additional subordinated financial support from other parties.  It requires the consolidation of the VIE by the primary beneficiary.  The adoption of FIN 46(R) requires the Company to include disclosures for non SPE VIEs created or acquired on or after February 1, 2003 in its consolidated financial statements related to the total assets and the maximum exposure to loss resulting from the Company’s interests in VIEs.  The adoption of FIN 46(R) did not have a material effect on the Company’s financial position, results of operations, or cash flows.

 

Critical Accounting Policies

 

General– The Company prepares the Company’s financial statements in accordance with accounting principles generally accepted in the United States of America. As such, the Company is required to make certain estimates, judgments and assumptions that the Company believes are reasonable based upon the information available. These estimates and assumptions affect the reported amounts of assets and liabilities at the date of the financial statements and the reported amounts of revenues and expenses during the periods presented. The significant accounting policies which the Company believes are most critical to understanding and evaluating the Company’s reported financial results include the following:  Revenue Recognition, Property, Plant and Equipment and Contingencies.

 

Revenue Recognition —  The Company generates energy revenues under the Power Purchase Agreement with Williams Energy.  During the 20-year term of the agreement, the Company expects to sell capacity and electric energy produced by the facility, as well as ancillary services and fuel conversion services.  Under the Power Purchase Agreement, the Company also generates revenues from meeting (1) base electrical output guarantees and (2) heat rate rebates through efficient electrical output.  Revenues from the sales of electric energy and capacity are recorded based on output delivered and capacity provided at rates as specified under contract terms.  Revenues for ancillary and other services are recorded when the services are rendered. Amounts that are in dispute are reserved for accordingly, based on the probability that they will be realized.

 

Property, Plant and Equipment —  Property, plant and equipment is recorded at cost and is depreciated, after consideration for salvage value, over its useful life.  The estimated lives of the Company’s generation facilities range from five to thirty-six years.  A significant decrease in the estimated useful life of a material amount of the Company’s property, plant or equipment could have a material adverse impact on the Company’s operating results in the period in which the estimate is revised and in subsequent periods.  The depreciable lives and original costs of the Company’s property plant and equipment by category are as follows:

 

Description of Asset

 

Depreciable Life

 

Original Costs at
December 31, 2004

 

Original Costs at
December 31, 2003

 

 

 

 

 

(in thousands)

 

(in thousands)

 

Buildings

 

35

 

$

1,767

 

$

1,767

 

Vehicles

 

5

 

112

 

112

 

Computers

 

6

 

772

 

772

 

Furniture and Fixtures

 

10

 

515

 

515

 

Combustion Turbine Generator Parts

 

9-36

 

53,345

 

45,367

 

Gas Heaters

 

35

 

1,119

 

1,119

 

Spare Parts Inventory

 

 

5,379

 

12,751

 

Plant

 

35

 

363,943

 

362,390

 

 

 

 

 

$

426,952

 

$

424,793

 

 

Spare Parts Inventory – Spare parts inventory consists of rotable and other spare parts, primarily covered under the Maintenance Services Agreement discussed in Note 8.  Inventory is reported at cost and is included in Property, Plant and Equipment, once received from Siemens Westinghouse.  The liability for these spare parts is reflected as

 

43



 

current and long-term liabilities in the accompanying balance sheets. For financial reporting purposes, payments made to Siemens Westinghouse are treated as a reduction of the liability in the accompanying balance sheet, except for the portion that is considered maintenance expense when a scheduled outage occurs.  Spare parts begin to be depreciated over their useful lives once placed in service.

 

Commitments and Contingencies

 

Raytheon - The Company’s facility was initially designed, engineered, procured and constructed for the Company by Washington Group International, Inc. (“WGI”) (as the successor contractor) on a fixed-price, turnkey basis. On May 14, 2001, WGI filed a plan of reorganization along with voluntary petitions to restructure under Chapter 11 of the U.S. Bankruptcy Code in the U.S. Bankruptcy Court for the District of Nevada in Reno (the “Bankruptcy Court”). As a result of WGI’s bankruptcy filing, on June 20, 2001 the Company made a demand on the Raytheon Company (“Raytheon”) to perform its obligations under a guarantee which Raytheon had given the Company of WGI’s performance obligations under the construction agreement and Raytheon became responsible for the construction of the Company’s facility.  As discussed above, provisional acceptance has been granted and the facility has commenced commercial operations, however, Raytheon must perform certain agreed upon completion items in order to obtain final acceptance. Raytheon gave notice of Final Acceptance on July 22, 2003 based on its July 8, 2003 performance test.  On July 31, 2003, the Company received a letter from the project’s independent engineer stating that it could not support Raytheon’s claim of final acceptance and it did not consider the July 8, 2003 performance test valid.  In making this assessment, the independent engineer cited, among other reasons, (i) modifications made to certain equipment in performance of the July 8 performance test which would adversely impact the operations of the plant and other pieces of equipment and (ii) Raytheon’s failure to demonstrate compliance with guaranteed emissions limits.  On August 1, 2003, the Company rejected Raytheon’s claim of final acceptance.  This rejection was based upon Raytheon’s failure to meet the conditions for final acceptance provided for in the EPC contract. On August 7, 2003, the Company received a response from Raytheon in which Raytheon claims that the Company’s rejection of the final acceptance is invalid and improper.

 

On August 26, 2004, the Company drew down approximately $30.3 million under a letter of credit posted by Raytheon pursuant to the terms of the EPC Agreement. Prior to this date, the Company had drawn $544,000 on this letter of credit. The Company believes that Raytheon substantially breached the EPC Agreement, due, among other things, to the facility’s failure to achieve compliance with certain performance tests, and Raytheon’s failure to complete other services under the EPC Agreement and certain amendments thereto, including a Settlement Agreement dated August 6, 2002, that purported to resolve disputes over whether Raytheon had achieved Mechanical Completion and Provisional Acceptance. As a result, the Company claims that Raytheon’s breaches have caused damages in excess of the amount of the letter of credit. Raytheon disputes these claims and has failed and refused to pay costs and damages to the Company despite the Company’s demands for such payment.

 

On August 27, 2004, Raytheon filed a construction lien claim for $30,963,662 in Middlesex County against the real property and improvements owned by the Company under the New Jersey Construction Lien Law.  Among other things, Raytheon claims therein that the draw of the Letter of Credit represents a debt to Raytheon owed by the Company.

 

On October 28, 2004, the Company received a complaint filed by Raytheon in the State of New York. In the complaint, Raytheon is seeking to recover $30,302,269, which represents the amount Red Oak drew down on the letter of credit on August 26, 2004, attorneys’ fees and costs, and also to recover up to $110 million of net expense Raytheon claims to have incurred in good faith under the governing guaranty and construction agreements.  The Company filed an answer and counterclaim on December 13, 2004, in which it denied liability to Raytheon, asserted various defenses and countersued Raytheon for breach of the EPC Agreement and Settlement Agreement, breach of express warranties under the EPC Agreement, and fraudulent misrepresentation and concealment.  The Company claimed damages of not less than $140 million and attorneys’ fees and costs to the extent allowable.  Raytheon moved to dismiss the Company’s fraudulent misrepresentation and concealment claim and to limit the Company’s damages on January 14, 2005.  The Company filed its opposition to the motion to dismiss and also filed an amended counterclaim on February 18, 2005.  Thereafter, Raytheon agreed to withdraw its motion to dismiss.  On March 4, 2005, Raytheon filed a motion for summary judgment that seeks the return of $16,311,711 of the Letter of Credit draw.  The Company has not yet filed its opposition to the motion, and Raytheon has not yet filed an answer to the amended counterclaim. The Company has recorded the $30.3 million as a current liability, but has not accrued any

 

44



 

additional amounts with respect to Raytheon’s claims.  The Company believes it has meritorious defenses to the claims asserted by Raytheon against it and intends to defend the lawsuit and pursue its counterclaims vigorously.

 

Williams Energy- The Company had entered into arbitration with Williams Energy to resolve certain disputes regarding the date of commercial operation and the proper interpretation of certain provisions of the Power Purchase Agreement relating to the amounts claimed by the Company to be payable by Williams Energy.  On November 4, 2003, the Company and Williams Energy settled this dispute.  The Company is also disputing $1.4 million of merchant price, testing gas and other charges with Williams Energy that the Company contends is owed from Williams. This was not part of the above arbitration.

 

 

ITEM 7A.                    QUANTITATIVE AND QUALITATIVE DISCLOSURE ABOUT MARKET RISK

 

The Company issued and has outstanding two series of bonds, registered under the Securities Act of 1933.  As of December 31, 2004, the aggregate outstanding principal amount of these bonds was $370.1 million. The Company is not subject to interest rate risk as the interest rates associated with the Company’s outstanding indebtedness are fixed over the life of the bonds.

 

The Company currently has no other financial or derivative financial instruments. The Company does not believe that the it faces other material market risks requiring disclosure pursuant to Item 305 of Regulation S-K.

 

During 2003 the PJM market, into which the Company’s facility’s generation is distributed, experienced a general decline in the amount paid for electricity. This, in combination with a marked increase in the cost of natural gas, was a major factor in Williams’ decision to dispatch the Company’s facility on a very limited basis. These market conditions continued through 2004. Based upon current market conditions and projections from Williams, the Company anticipates a dispatch level in 2005 comparable to the range over the last two years.  In the event that these market conditions do not improve, and Williams does not dispatch the Company’s facility at all in 2005, the Company believes that the fixed capacity payments are sufficient to meet the cash demands of the Company’s business, but the Company requires the additional revenue from such fuel conversion services to be profitable.

 

45



 

ITEM 8.                             FINANCIAL STATEMENTS AND SUPPLEMENTAL DATA

 

AES Red Oak L.L.C. and Subsidiary
(An Indirect, Wholly Owned
Subsidiary Of The AES Corporation)

 

Index To Consolidated Financial Statements

 

Report of Independent Registered Public Accounting Firm

 

 

 

Consolidated Balance Sheets

 

 

 

Consolidated Statements of Operations

 

 

 

Consolidated Statements of Changes in Member’s Capital

 

 

 

Consolidated Statements of Cash Flows

 

 

 

Notes to Consolidated Financial Statements

 

 

46



 

Report of Independent Registered Public Accounting Firm

 

To the Member of
AES Red Oak, L.L.C. and Subsidiary:

 

We have audited the accompanying consolidated balance sheets of AES Red Oak, L.L.C. and Subsidiary (an indirect wholly owned subsidiary of The AES Corporation) (the “Company”) as of December 31, 2004 and 2003 and the related consolidated statements of operations, changes in member’s capital and cash flows for each of the three years in the period ended December 31, 2004. These financial statements are the responsibility of the Company’s management. Our responsibility is to express an opinion on the financial statements based on our audits.

 

We conducted our audits in accordance with the standards of the Public Company Accounting Oversight Board (United States).  Those standards require that we plan and perform the audit to obtain reasonable assurance about whether the financial statements are free of material misstatement.  The Company is not required to have, nor were we engaged to perform, an audit of its internal control over financial reporting.  Our audit included consideration of internal control over financial reporting as a basis for designing audit procedures that are appropriate in the circumstances, but not for the purpose of expressing an opinion on the effectiveness of the Company’s internal control over financial reporting.  Accordingly, we express no such opinion.  An audit also includes examining, on a test basis, evidence supporting the amounts and disclosures in the financial statements, assessing the accounting principles used and significant estimates made by management, as well as evaluating the overall financial statement presentation.  We believe that our audits provide a reasonable basis for our opinion.

 

In our opinion, such consolidated financial statements present fairly, in all material respects, the financial position of AES Red Oak, L.L.C., and Subsidiary as of December 31, 2004 and 2003, and the results of their operations and their cash flows for each of the three years in the period ended December 31, 2004, in conformity with accounting principles generally accepted in the United States of America.

 

As more fully discussed in Note 7, the Company’s dependence upon Williams Power Company, Inc., formerly Williams Energy Marketing & Trading Company, under the Power Purchase Agreement exposes the Company to possible loss of revenues and fuel supply. There can be no assurances as to the Company’s ability to generate sufficient cash flow to cover operating expenses or debt service obligations in the absence of a Power Purchase Agreement with Williams Power Company, Inc. and related guaranty by The Williams Companies, Inc. or their affiliates.

 

 

Deloitte & Touche LLP
McLean, Virginia

March 24, 2005

 

47



 

AES RED OAK, L.L.C. AND SUBSIDIARY
AN INDIRECT, WHOLLY OWNED SUBSIDIARY OF THE AES CORPORATION

 

Consolidated Balance Sheets,
December 31, 2004 and 2003
(dollars in thousands, except share amounts)

 

 

 

2004

 

2003

 

ASSETS:

 

 

 

 

 

 

 

 

 

 

 

Current Assets:

 

 

 

 

 

Cash

 

$

5

 

$

38

 

Restricted cash at cost, which approximates market value

 

41,584

 

34,837

 

Receivables

 

4,374

 

4,070

 

Receivable from affiliate

 

30

 

51

 

Prepaid and other assets

 

599

 

628

 

Total current assets

 

46,592

 

39,624

 

Land

 

4,240

 

4,240

 

Property, plant, and equipment – net of accumulated depreciation of $27,614 and $15,830, respectively

 

399,338

 

408,963

 

Deferred financing costs – net of accumulated amortization of $3,941 and $3,128 respectively

 

14,764

 

15,577

 

Other assets

 

606

 

219

 

Total assets

 

$

465,540

 

$

468,623

 

 

 

 

 

 

 

LIABILITIES AND MEMBER’S EQUITY

 

 

 

 

 

 

 

 

 

 

 

Current Liabilities:

 

 

 

 

 

Accounts payable

 

$

784

 

$

398

 

Accrued liabilities

 

1,945

 

956

 

Accrued interest

 

2,722

 

2,759

 

Liabilities under spare parts agreement – current portion

 

827

 

4,520

 

Payable to affiliate

 

282

 

131

 

Bond payable-current portion

 

5,072

 

5,230

 

Payable to Raytheon.

 

30,302

 

 

Payable to Williams

 

10,000

 

35,000

 

Total current liabilities

 

51,934

 

48,994

 

 

 

 

 

 

 

Bonds payable

 

365,060

 

370,132

 

Other liabilities

 

141

 

2,017

 

Total liabilities

 

$

417,135

 

$

421,143

 

 

 

 

 

 

 

Commitments and Contingencies (Note 8)

 

 

 

 

 

 

 

 

 

 

 

Member’s capital:

 

 

 

 

 

Common stock, $1 par value-10 shares authorized, none issued or outstanding

 

$

 

$

 

Contributed capital

 

56,873

 

56,775

 

Member’s deficit

 

(8,468

)

(9,295

)

Total member’s capital

 

48,405

 

47,480

 

Total liabilities and member’s capital

 

$

465,540

 

$

468,623

 

 

See notes to consolidated financial statements.

 

48



 

AES RED OAK, L.L.C. AND SUBSIDIARY
AN INDIRECT, WHOLLY OWNED SUBSIDIARY OF THE AES CORPORATION

 

Consolidated Statements of Operations,
years ended December 31, 2004, 2003 and 2002
(dollars in thousands)

 

 

 

Year Ended
December 31,
2004

 

Year Ended
December 31,
2003

 

Year Ended
December 31,
2002

 

OPERATING REVENUES

 

 

 

 

 

 

 

Energy

 

$

69,682

 

$

64,206

 

$

26,244

 

 

 

 

 

 

 

 

 

OPERATING EXPENSES

 

 

 

 

 

 

 

Fuel costs

 

627

 

906

 

6,898

 

Fuel conversion volume rebate

 

5,859

 

5,793

 

1,645

 

Corporate management fees

 

1,642

 

1,608

 

594

 

Other operating expenses

 

10,631

 

7,207

 

1,990

 

Depreciation expense

 

11,788

 

11,392

 

4,438

 

Property taxes and insurance

 

2,801

 

2,284

 

794

 

General administrative costs

 

1,149

 

1,718

 

443

 

Total operating expenses

 

34,497

 

30,908

 

16,802

 

Operating income

 

$

35,185

 

$

33,298

 

$

9,442

 

 

 

 

 

 

 

 

 

OTHER INCOME (EXPENSE)

 

 

 

 

 

 

 

Interest income

 

$

476

 

$

495

 

$

125

 

Other income- interim rebates

 

 

1,427

 

957

 

Liquidated damages received

 

 

 

1,810

 

Interest expense

 

(33,798

)

(34,232

)

(13,163

)

Letter of credit fees and other

 

(1,036

)

(1,013

)

(379

)

Liquidated damages paid

 

 

(249

)

(1,810

)

Total other income (expense)

 

(34,358

)

(33,572

)

(12,460

)

NET INCOME (LOSS)

 

$

827

 

$

(274

)

$

(3,018

)

 

See notes to consolidated financial statements.

 

49



 

AES RED OAK, L.L.C. AND SUBSIDIARY
AN INDIRECT, WHOLLY OWNED SUBSIDIARY OF THE AES CORPORATION

 

Consolidated Statements of Changes in Member’s Capital,
years ended December 31, 2004, 2003 and 2002
(dollars in thousands)

 

 

 

Common Stock

 

Contributed

 

Member’s

 

Member’s

 

 

 

Shares

 

Amount

 

Capital

 

Deficit

 

Equity

 

BALANCE, DECEMBER 31, 2001

 

 

$

 

$

986

 

$

(2,953

)

$

(1,967

)

Contributed capital

 

 

 

55,750

 

 

55,750

 

Dividends

 

 

 

 

(2,000

)

(2,000

)

Net loss

 

 

 

 

(3,018

)

(3,018

)

BALANCE, DECEMBER 31, 2002

 

 

$

 

$

56,736

 

$

(7,971

)

$

48,765

 

Contributed capital

 

 

 

39

 

 

39

 

Dividends

 

 

 

 

(1,050

)

(1,050

)

Net loss

 

 

 

 

(274

)

(274

)

BALANCE, DECEMBER 31, 2003

 

 

$

 

$

56,775

 

$

(9,295

)

$

47,480

 

Contributed capital

 

 

 

$

98

 

 

$

98

 

Net income

 

 

 

 

827

 

827

 

BALANCE, DECEMBER 31, 2004

 

 

$

 

$

56,873

 

$

(8,468

)

$

48,405

 

 

See notes to consolidated financial statements.

 

50



 

AES RED OAK, L.L.C. AND SUBSIDIARY
AN INDIRECT, WHOLLY OWNED SUBSIDIARY OF THE AES CORPORATION

 

Consolidated Statements of Cash Flows, for the years
ended December 31, 2004, 2003 and 2002
(dollars in thousands)

 

 

 

Year Ended
December 31,
2004

 

Year Ended
December 31,
2003

 

Year Ended
December 31,
2002

 

OPERATING ACTIVITIES:

 

 

 

 

 

 

 

Net income (loss)

 

$

827

 

$

(274

)

$

(3,018

)

Amortization of deferred financing costs

 

813

 

813

 

853

 

Depreciation

 

11,788

 

11,392

 

4,438

 

Loss on disposal of asset

 

46

 

 

 

Change in:

 

 

 

 

 

 

 

Accounts receivable

 

(304

)

4,372

 

(8,442

)

Receivable from affiliate

 

21

 

258

 

(184

)

Prepaid and other assets

 

29

 

(398

)

(230

)

Other assets

 

(387

)

(78

)

(141

)

Accounts payable

 

386

 

(777

)

293

 

Accrued liabilities

 

753

 

(560

)

1,454

 

Accrued interest

 

(37

)

(45

)

(17

)

Payable to affiliate

 

151

 

113

 

(64

)

 

 

 

 

 

 

 

 

Net cash provided by (used in) operating activities

 

14,086

 

14,816

 

(5,058

)

INVESTING ACTIVITIES:

 

 

 

 

 

 

 

Payments for capital additions

 

(1,973

)

(2,696

)

(24,029

)

Payments under long term spare parts agreement

 

(5,569

)

(2,788

)

(1,175

)

Retention payable

 

 

 

(29,478

)

Restricted cash

 

(6,747

)

(27,088

)

(1,688

)

 

 

 

 

 

 

 

 

Net cash (used in) investing activities

 

(14,289

)

(32,572

)

(56,370

)

FINANCING ACTIVITIES:

 

 

 

 

 

 

 

Payment of principal on bonds payable

 

(5,230

)

(6,218

)

(2,420

)

Contribution from parent

 

98

 

39

 

55,750

 

Security proceeds from (repayment to) Williams under PPA

 

(25,000

)

25,000

 

10,000

 

Proceeds from Raytheon letter of credit under EPC agreement

 

30,302

 

 

 

Dividends paid to parent

 

 

(1,050

)

(2,000

)

Net cash provided by financing activities

 

170

 

17,771

 

61,330

 

NET (DECREASE) INCREASE IN CASH AND CASH EQUIVALENTS

 

$

(33

)

$

15

 

$

(98

)

CASH AND CASH EQUIVALENTS, BEGINNING OF PERIOD

 

$

38

 

$

23

 

$

121

 

CASH AND CASH EQUIVALENTS, END OF PERIOD

 

$

5

 

$

38

 

$

23

 

SUPPLEMENTAL DISCLOSURE OF OTHER ACTIVITIES:

 

 

 

 

 

 

 

Interest paid (net of amounts capitalized)

 

$

33,022

 

$

33,537

 

$

8,437

 

Receipt of spare parts under long-term service agreement

 

$

205

 

$

289

 

$

10,500

 

Transfer of construction in progress to property, plant and equipment

 

$

223

 

$

344

 

$

411,597

 

 

See notes to consolidated financial statements.

 

51



 

AES RED OAK L.L.C. AND SUBSIDIARY
AN INDIRECT WHOLLY OWNED SUBSIDIARY OF THE AES CORPORATION
NOTES TO CONSOLIDATED FINANCIAL STATEMENTS
YEARS ENDED DECEMBER 31, 2004, 2003 AND 2002

 

1.              ORGANIZATION

 

AES Red Oak, L.L.C. (the “Company”) was formed on September 13, 1998, in the State of Delaware, to develop, construct, own and operate an 830-megawatt (MW) gas-fired, combined cycle electric generating facility (the “Facility”) in the Borough of Sayreville, Middlesex County, New Jersey. The Company was considered dormant until March 15, 2000 (hereinafter, inception), at which time it consummated a project financing and certain related agreements. On March 15, 2000, the Company issued $384 million in senior secured bonds for the purpose of providing financing for the construction of the facility and to fund, through the construction period, interest payments to the bondholders (see Note 6). In late September 2000, the Company consummated an exchange offer whereby the holders of the senior secured bonds exchanged their privately placed senior secured bonds for registered senior secured bonds.

 

The Company is a wholly owned subsidiary of AES Red Oak, Inc. (“Red Oak”), which is a wholly-owned subsidiary of The AES Corporation (“AES”). Red Oak has no assets other than its ownership interests in the Company and AES Sayreville, L.L.C. (see Note 9). Red Oak has no operations and is not expected to have any operations. Red Oak’s only income is distributions (if any) it receives from the Company and AES Sayreville, L.L.C.  The equity that Red Oak provided to the Company was provided to Red Oak by AES, which owns all of the equity interests in Red Oak. Pursuant to an equity subscription agreement (see Note 6), Red Oak agreed to contribute up to approximately $56.7 million to the Company to fund construction after the bond proceeds have been fully utilized.

 

The Company owns all of the equity interests in AES Red Oak Urban Renewal Corporation (“AES URC”), which was organized as an urban renewal corporation under New Jersey Law. As an urban renewal corporation under New Jersey law, portions of the facility can be designated as redevelopment areas in order to provide certain real estate tax and development benefits to the facility. URC has no operations outside of its activities in connection with the facility.

 

2.              OPERATIONS

 

During 2002, as further discussed in Note 7, the credit ratings of the long-term senior unsecured debt of The Williams Companies, Inc. were downgraded to below investment grade.  Since achieving commercial operations, under the Power Purchase Agreement with Williams Energy, the Company is eligible to receive variable operations and maintenance payments, total fixed payments, energy exercise fee payments (each as defined in the Power Purchase Agreement) and other payments for the delivery of fuel conversion, capacity and ancillary services.  Since September 28, 2002, Williams Energy has not requested that the Company run the facility or “dispatch” the facility to a significant degree, outside the peak summer months. The minimum capacity payments provided for under the Power Purchase Agreement have been the Company’s primary source of operating revenues, representing $62.5 million of the Company’s total revenues of $69.7 million for the twelve months ended December 31, 2004.  The Company has used these operating revenues, together with interest income from the investment of available cash balances and the $10 million Prepayment from Williams (Note 7) to fund its generation expenses, other operations and maintenance expenses and debt service costs.  As discussed in Note 7, in the event that The Williams Companies, Inc. regains and maintains its investment grade status, Williams Energy provides a substitute guaranty of investment grade rating, or posts a letter of credit, the Company will be required to return the $10 million alternative credit support prepayment provided by Williams Energy in accordance with the terms of the Letter Agreement. Williams Energy has notified the Company that it intends to post a letter of credit for the remaining $10 million in June 2005.

 

The Company currently anticipates being dispatched by Williams Energy beginning in April 2005 but can provide no assurance that this will occur.  In the event that the facility is not dispatched, the Company’s operating revenues will consist of minimum capacity payments under the Power Purchase Agreement.  The Company has also

 

52



 

provided two letters of credit, the Power Purchase Agreement Letter of Credit ($10 million) and the debt service reserve letter of credit ($22 million) (Notes 6 and 7) that may be utilized if necessary to fund obligations as they become due.

 

The Company currently believes that its sources of liquidity will be adequate to meet its needs through the end of 2005.  This belief is based on a number of assumptions, including but not limited to the continued performance and satisfactory financial condition of the third parties on which the Company depends, particularly Williams Energy as fuel supplier and purchaser of all electric energy and capacity produced by the facility as well as ancillary and fuel conversion services of the Company (as provided by the Power Purchase Agreement) and The Williams Companies, Inc. as guarantor of Williams Energy’s performance under the Power Purchase Agreement.  Known and unknown risks, uncertainties and other factors outside the Company’s control may cause actual results to differ materially from its current expectations.  These risks, uncertainties and factors include but are not limited to risks and uncertainties related to the financial condition and continued performance of the third parties on which the Company depends, including Williams Energy and The Williams Companies and its affiliates, the possibility that the facility will not be dispatched to a significant degree, delays in or disputes over the completion of the facility, the possibility of unexpected problems related to the performance of the facility, the possibility of unexpected expenses or lower than expected revenues and additional factors that are unknown to the Company or beyond its control.

 

Since the Company depends on Williams Energy for both revenues and fuel supply under the Power Purchase Agreement, if Williams Energy were to terminate or default under the Power Purchase Agreement, there would be a severe negative impact on the Company’s cash flow and financial condition which could result in a default on its senior secured bonds.  Due to recent declines in pool prices, the Company would expect that if it were required to seek alternative purchasers of its power as a result of a default by Williams Energy that any such alternate revenues would be substantially below the amounts that would have been otherwise payable pursuant to the Power Purchase Agreement.  There can be no assurance as to the Company’s ability to generate sufficient cash flow to cover operating expenses or its debt service obligations in the absence of a long-term power purchase agreement with Williams Energy.

 

3.              SIGNIFICANT ACCOUNTING POLICIES

 

Principles of Consolidation - The consolidated financial statements include the accounts of the Company and AES URC, its wholly owned subsidiary. All intercompany transactions and balances have been eliminated in consolidation.

 

Cash and Cash Equivalents - The Company considers unrestricted cash on hand, deposits in banks, and investments with original maturities of three months or less to be cash and cash equivalents for the purpose of the statement of cash flows.

 

Restricted Cash and Investments - The Company is prohibited from making any distributions unless it has required minimum balances in certain accounts and has met certain other conditions contained in the Indenture and the Collateral Agency and Intercreditor Agreement governing the senior secured bonds. The $41.6 million balance of restricted cash consists of cash to be used to repay the drawdown of the letter of credit from Raytheon and the prepayment credit support amount owed to Williams (See Note 7 - Power Purchase Agreement).  The Company had the required minimum balances and had met the required conditions when it made distributions of $1.05 million and $2.0 million to AES Red Oak, Inc. on December 31, 2003 and 2002, respectively.

 

Property, Plant and Equipment — Property, plant and equipment is recorded at cost.  Depreciation, after consideration of salvage value, is computed using the straight-line method over the estimated useful lives of the assets, which range from five to thirty-six years.  Maintenance and repairs are charged to expense as incurred.  The depreciable lives and the original costs of the Company’s property, plant and equipment by category are as follows:

 

53


 


 

Description of Asset

 

Depreciable Life

 

Original Costs at
December 31, 2004

 

Original Costs at
December 31, 2003

 

 

 

 

 

(in thousands)

 

(in thousands)

 

Buildings

 

35

 

$

1,767

 

$

1,767

 

Vehicles

 

5

 

112

 

112

 

Computers

 

6

 

772

 

772

 

Furniture and Fixtures

 

10

 

515

 

515

 

Combustion Turbine Generator Parts

 

9-36

 

53,345

 

45,367

 

Gas Heaters

 

35

 

1,119

 

1,119

 

Spare Parts Inventory

 

 

5,379

 

12,751

 

Plant

 

35

 

363,943

 

362,390

 

 

 

 

 

$

426,952

 

$

424,793

 

 

Spare Parts Inventory – Spare parts inventory consists of rotable and other spare parts, primarily covered under the Maintenance Services Agreement discussed in Note 8.  Inventory is reported at cost and is included in Property, Plant and Equipment, once received from Siemens Westinghouse.  The liability for these spare parts is reflected as current and long-term liabilities in the accompanying balance sheets. For financial reporting purposes, payments made to Siemens Westinghouse are treated as a reduction of the liability in the accompanying balance sheet, except for the portion that is considered maintenance expense when a scheduled outage occurs.

 

Deferred Financing Costs - Financing costs are deferred and are being amortized using the straight-line method over the life of the bonds, which does not differ materially from the effective interest method of amortization.

 

Revenue Recognition —  The Company generates energy revenues under the Power Purchase Agreement with Williams Energy.  During the 20-year term of the agreement, the Company expects to sell capacity and electric energy produced by the facility, as well as ancillary services and fuel conversion services.  Under the Power Purchase Agreement, revenues are generated from meeting (1) base electrical output guarantees and (2) heat-rate rebates through efficient electrical output.  Revenues from the sales of electric energy and capacity are recorded based on output delivered and capacity provided at rates as specified under contract terms.  Revenues for ancillary and other services are recorded when the services are rendered.

 

Use of Estimates - The preparation of financial statements in conformity with accounting principles generally accepted in the United States of America requires the Company to make estimates and assumptions that affect reported amounts of assets and liabilities and disclosures of contingent assets and liabilities as of the date of the financial statements, as well as the reported amounts of revenues and expenses during the reporting period. Actual results could differ from those estimates.

 

Income Taxes - The Company is a limited liability company and is treated as a disregarded entity for tax purposes. Therefore, it does not pay income taxes, and no provision for income taxes has been reflected in the accompanying financial statements.

 

Reclassifications – Certain reclassifications have been made to prior period amounts to conform to the 2004 presentation.

 

4.  CONCENTRATION OF CREDIT RISK IN WILLIAMS ENERGY AND ITS AFFILIATES

 

Williams Energy is currently the Company’s sole customer for purchases of capacity, ancillary services, and energy and its sole source for fuel.  Williams Energy’s payments under the Power Purchase Agreement are expected to provide all of the Company’s operating revenues during the term of the Power Purchase Agreement.  It is unlikely that the Company would be able to find another purchaser or fuel source on similar terms for its facility if Williams Energy were not performing under the Power Purchase Agreement.  Any material failure by Williams Energy to make capacity and fuel conversion payments or to supply fuel under the Power Purchase Agreement would have a severe impact on the Company’s operations, and may result in a default on the Company’s debt.  The payment

 

54



 

obligations of Williams Energy under the Power Purchase Agreement are guaranteed by The Williams Companies, Inc.  The payment obligations of The Williams Companies, Inc. under the guaranty are capped at an amount equal to approximately $510 million.  Beginning on January 1 of the first full year after the commercial operation date, this guaranty cap is to be reduced semiannually by a fixed amount which is based on the amortization of the Company’s senior secured bonds during the applicable semiannual period (see Note 7). As of December 31, 2004, the guarantee was capped at $501.4 million.

 

The Company’s dependence upon The Williams Companies, Inc. and its affiliates under the Power Purchase Agreement exposes the Company to possible loss of revenues and fuel supply, which in turn, could negatively impact its cash flow and financial condition and may result in a default on its senior secured bonds.  There can be no assurances as to the Company’s ability to generate sufficient cash flow to cover operating expenses or its debt service obligations in the absence of a long-term power purchase agreement with Williams Energy.

 

5.              NEW ACCOUNTING PRONOUNCEMENTS

 

In January 2003, the Financial Accounting Standards Board (“FASB”) issued FIN No. 46, Consolidation of Variable Interest Entities, an Interpretation of ARB No. 51 (“FIN No. 46”).  In October 2003, FASB Staff Position No. 46-6, “Effective Date of FIN No. 46, Consolidation of Variable Interest Entities” deferred the effective date of FIN No. 46 for variable interests held by a public entity in a variable interest entity (“VIE”) that was created or acquired before February 1, 2003 to the end of the first interim or annual period ending after December 15, 2003.  In December 2003, FASB issued FIN 46 (revised December 2003), Consolidation of Variable Interest Entities, an Interpretation of ARB No. 51 (“FIN 46(R)”), which clarified some requirements and incorporated several staff positions that the Company was already required to apply.  In addition, FIN 46(R) deferred the effective date for VIEs that were created or acquired before February 1, 2003 and were not considered special purpose entities (“SPEs”) prior to the issuance of the interpretation until the end of the first reporting period ending after March 15, 2004.  FIN 46(R) defines a VIE as (i) any entity in which the equity investors at risk in such entity do not have the characteristics of a controlling financial interest, or (ii) any entity that does not have sufficient equity at risk to finance its activities without additional subordinated financial support from other parties.  It requires the consolidation of the VIE by the primary beneficiary.  The adoption of FIN 46(R) requires the Company to include disclosures for non SPE VIEs created or acquired on or after February 1, 2003 in its consolidated financial statements related to the total assets and the maximum exposure to loss resulting from the Company’s interests in VIEs.  The adoption of FIN 46(R) did not have a material effect on the Company’s financial position, results of operations, or cash flows.

 

6.              BONDS PAYABLE

 

On March 15, 2000, the Company issued $224 million of 8.54% senior secured bonds due 2019 (“2019 Bonds”) and $160 million of 9.20% senior secured bonds due 2029 (2029 Bonds and together with the 2019 Bonds, the “Bonds”) to qualified institutional buyers and/or institutional accredited investors, pursuant to a transaction exempt from registration under the Securities and Exchange Act of 1933 (the Act) in accordance with Rule 144A of the Act. In late September 2000, the Company consummated an exchange offer whereby the holders of the Bonds exchanged their privately placed bonds for registered bonds. The net proceeds of the bonds (after deferred financing costs), approximately $365 million, were used to prepay Washington Group International, Inc. (“WGI”) and other construction costs of the Company and were also used, during the construction period, for interest payments to bondholders.

 

Future Maturities of Debt - Principal on the Bonds is payable quarterly in arrears.  Principal payments on the 2019 Bonds commenced on August 31, 2002. Quarterly principal repayment of the 2029 Bonds does not commence until February 28, 2019.  The final maturity date for the Bonds is November 30, 2019 and November 30, 2029, respectively.

 

55



 

 Interest & Principal Repayment Schedule:

 

Year

 

Interest

 

Principal

 

 

 

(in thousands)

 

2005

 

$

32,578

 

$

5,072

 

2006

 

32,111

 

7,100

 

2007

 

31,502

 

6,106

 

2008

 

30,940

 

8,122

 

2009

 

30,117

 

12,520

 

2010 and thereafter

 

287,290

 

331,212

 

Total Payments

 

$

444,538

 

$

370,132

 

 

Optional Redemption - The Bonds are subject to optional redemption by the Company, in whole or in part, at any time at a redemption price equal to 100% of the principal amount plus accrued interest, together with a premium calculated using a discount rate equal to the interest rate on comparable U.S. Treasury securities plus 50 basis points.

 

Mandatory Redemption - The Bonds are subject to mandatory redemption by the Company, in whole or in part, at a redemption price equivalent to 100% of the principal amount plus accrued interest under certain situations pursuant to receiving insurance proceeds, eminent domain proceeds, liquidated damages under the construction agreement, or in certain instances in which payments are received under the Power Purchase Agreement if the Company terminates the Power Purchase Agreement as a result of a default by Williams.

 

Indenture - The Trust Indenture Agency (the Indenture) contains limitations on the Company incurring additional indebtedness, granting liens on the Company’s property, distributing equity and paying subordinated indebtedness issued by affiliates of the Company, entering into transactions with affiliates, amending, terminating or assigning any of the Company’s contracts and fundamental changes or disposition of assets.

 

Collateral for the Bonds consists of the facility and related entities, all agreements relating to the operation of the project, the bank and investment accounts of the Company, and all ownership interests in the Company, as prescribed under the Indenture. The Company is also bound by a collateral agency agreement (the Collateral Agency Agreement) and an equity subscription agreement (the Equity Subscription Agreement).

 

Collateral Agency Agreement - The Collateral Agency Agreement requires the Company to fund or provide the funding or a letter of credit for a debt service reserve fund. The debt service reserve fund letter of credit was posted at financial closing in the amount of $22 million dollars, and has an expiration date of March 15, 2007. The amount required for funding the debt service reserve fund is equal to six months scheduled payments of principal and interest on the bonds.

 

Equity Subscription Agreement - The Company, along with Red Oak, entered into an Equity Subscription Agreement, pursuant to which Red Oak agreed to contribute up to approximately $56.7 million to the Company to fund project costs. As of December 31, 2002, Red Oak had contributed the entire $56.7 million to the Company, including the reclassification of a $986,000 payable to an affiliate (AES Corporation) to contributed capital in February 2001. The equity that Red Oak provided to the Company was provided by AES. The Company does not have access to additional liquidity pursuant to this agreement as Red Oak has fulfilled its funding obligations thereunder.

 

Covenants - The Indenture, Collateral Agency Agreement and Equity Subscription Agreement, contain specific covenants and requirements to be met by the Company.

 

Bond Ratings and Effect on Working Capital Agreement.  In connection with the initial financing of the facility, the Company had entered into a working capital agreement pursuant to which it could borrow up to $2.5 million for use in connection with the payment of operating and maintenance costs of the project.  The obligation of the banks that were party to the working capital agreement to extend loans to the Company under the working capital agreement were subject to, among others, the following conditions precedent:

 

56



 

                                         The Company’s senior secured bonds must be rated “BBB-”or higher by S&P and “Baa3” or higher by Moody’s;

 

                                         no default or event of default under the working capital agreement shall have occurred and be continuing; and

 

                                         no event has occurred and is continuing which could reasonably be expected to have a material adverse effect on the Company.

 

As the Company’s senior secured bonds have been rated lower than “BBB-” by S&P and lower than “Baa3” by Moody’s since 2002, funds had not been available to the Company under the working capital agreement. The term of this working capital agreement expired on March 15, 2005. The Company is currently reviewing comparable financing facilities that would allow for funds to be available for future working capital requirements, as needed. Further, as a result of the bond ratings downgrades the Company must pay higher fees for draws on its project support agreements.  There can be no assurance that the ratings on the senior secured bonds of the Company will be increased or that lenders will provide a comparable replacement of the working capital agreement.

 

7.              POWER PURCHASE AGREEMENT

 

General.  The Company and Williams Energy have entered into a Power Purchase Agreement for the sale of all capacity produced by the facility, as well as ancillary services and fuel conversion services. Under the Power Purchase Agreement, Williams Energy has the obligation to deliver, on an exclusive basis, all quantities of natural gas and fuel oil required by the facility to generate electricity or ancillary services, to start-up or shut-down the plant, and to operate the facility during any period other than a start-up, shut-down, or required dispatch by Williams Energy for any reason. The term of the Power Purchase Agreement is 20 years from the first contract anniversary date, which is the last day of the month in which commercial availability occurs.  As part of the arbitration settlement with Williams Energy, described below, the Company recognizes September 28, 2002 as the commercial availability date.

 

Under the Power Purchase Agreement, the commercial operation date was required to occur by December 31, 2001, however the Company had the right to extend the commercial operation date until June 30, 2002 by invoking its right to a free extension option which was available under the Power Purchase Agreement if certain conditions were met.  The Company exercised its right to extend the commercial operation date from December 31, 2001 to June 30, 2002, as granted under the free extension option. In addition, the Company had the right under the Power Purchase Agreement to again extend the commercial operation date (the Second Paid Extension Option) from June 30, 2002 to June 30, 2003, upon written notification to Williams Energy no later than May 21, 2002 (which represented an agreed upon extension from the original April 30, 2002 notification deadline), by paying Williams Energy (i) an amount equal to the lesser of any actual damages Williams Energy suffered or incurred after June 30, 2002, as a result of Williams Energy’s reliance upon delivery by such date, to the extent said damages cannot be mitigated fully, or $3.0 million and (ii) certain amount of liquidated damages as calculated pursuant to the Power Purchase Agreement.  On May 21, 2002, the Company exercised the Second Paid Extension Option.  As of December 31, 2002, the Company had paid liquidated damages to Williams Energy at the rate of $11,000 per day for the period beginning on July 1, 2002 and ending on August 31, 2002 which in aggregate amounted to $682,000.  The Company had also paid liquidated damages to Williams Energy at the rate of $22,000 per day for the period beginning on September 1, 2002, and ending on September 27, 2002 which in aggregate amounted to $594,000.  During the period of the Second Paid Extension Option, the Company continued to collect liquidated damages through August 10, 2002 from Raytheon under the construction agreement in the amount of $108,000 per day.  As of December 31, 2003, the Company had received $14 million in liquidated damages from Raytheon under the construction agreement, but none subsequent to that date.

 

The Company entered into arbitration with Williams Energy to resolve certain disputes regarding the date of commercial operation and the proper interpretation of certain provisions of the Power Purchase Agreement relating to the amounts claimed by the Company to be payable by Williams Energy.  Williams Energy has withheld or offset from amounts invoiced by the Company amounts that Williams Energy believes were improperly invoiced based on

 

57



 

Williams Energy’s interpretation of the Power Purchase Agreement.  The arbitration related to disputed amounts of approximately $7.6 million, which included a $594,000 payment extension option dispute and a $7.0 million commercial operation start date dispute. On November 4, 2003, the Company and Williams Energy settled this dispute.  Under the settlement, Williams made a cash payment to the Company of $4,050,153 on November 14, 2003, which included $225,055 of interest from October 2002 to the payment date, and the commercial operation date was agreed to be September 28, 2002. The related revenue had been substantially recorded in September 2002, with the remaining amount recorded in the fourth quarter of 2003. This payment settles all payment obligations between the parties for the month of September 2002 with respect to the commercial operation date under the Power Purchase Agreement.  From the Company’s perspective, the cash payment has the economic effect of recognizing a commercial operation date prior to September 28, 2002. The Company is also disputing $1.4 million of merchant price, testing gas and other charges with Williams Energy that the Company contends is owed by Williams Energy. This was not part of the above arbitration.

 

  Guaranties.  The Company provided Williams Energy a letter of credit (Power Purchase Agreement Letter of Credit) in the amount of $30 million to support specific payment obligations should the facility not achieve commercial operation by the date required under the Power Purchase Agreement. Upon the commencement of commercial operations in September 2002, the stated amount of that letter of credit was reduced to $10 million. The repayment obligations with respect to any drawings under the Power Purchase Agreement Letter of Credit are a senior debt obligation of the Company.

 

The payment obligations of Williams Energy under the Power Purchase Agreement are guaranteed by The Williams Companies, Inc.  The payment obligations of The Williams Companies, Inc. under the guaranty are capped at an amount equal to approximately $510 million.  Beginning on January 1 of the first full year after the commercial operation date, this guaranty cap is to be reduced semiannually by a fixed amount which is based on the amortization of the Company’s senior secured bonds during the applicable semiannual period.

 

Pursuant to Section 18.3 of the Power Purchase Agreement, in the event that S&P’s or Moody’s rates the long-term senior unsecured debt of The Williams Companies, Inc. lower than investment grade, The Williams Companies, Inc. is required to supplement The Williams Companies, Inc. guaranty with additional alternative security that is acceptable to the Company within 90 days after the loss of such investment grade rating.  According to published sources, The Williams Companies, Inc.’s long term senior unsecured debt has been rated below investment grade since 2002 by both S&P and Moody’s.

 

Due to the downgrade of The Williams Companies, Inc. to below investment grade, the Company and Williams Energy entered into a letter agreement dated November 7, 2002 (the “Letter Agreement”), under which Williams Energy agreed to provide the Company (a) a prepayment of $10 million within five business days after execution of the Letter Agreement (the “Prepayment”); (b) alternative credit support equal to $35 million on or before January 6, 2003 in any of the following forms (i) cash, (ii) letter(s) of credit with the Company as the sole beneficiary substantially in the form of the Power Purchase Agreement Letter of Credit, unless mutually agreed to otherwise, or (iii) a direct obligation of the United States Government delivered to a custodial securities account as designated by the Company with a maturity of not more than three years; and (c) replenish any portion of the alternative credit support that is drawn, reduced, cashed, or redeemed, at any time, with an equal amount of alternative credit support.  In the Letter Agreement, the Company and Williams Energy acknowledged that the posting of such alternative credit support and Williams Energy’s agreement and performance of the requirements of (a), (b), and (c) as set forth in the immediately preceding sentence, would be in full satisfaction of Williams Energy’s obligations contained in Section 18.3 of the Power Purchase Agreement.  In the Letter Agreement, the Company and Williams Energy expressly agreed that the posting of the Prepayment or any alternative credit support either now or in the future or any other terms set forth in the Letter Agreement, was not intended, and did not modify, alter, or amend in any way, the terms and conditions or relieve The Williams Company, Inc. from any obligations it has under its guaranty of the payment obligations of Williams Energy under the Power Purchase Agreement.  The guaranty remains in full force and effect, and the Company retains all of its rights and remedies provided by that guaranty.

 

Under the terms of the Letter Agreement, the Company is obligated to return the Prepayment to Williams Energy upon the earlier of (i) The Williams Companies, Inc. regaining its investment grade rating or Williams Energy providing a substitute guaranty of investment grade rating; (ii) the beginning of Contract Year 20; or (iii) the posting of alternative credit support by Williams Energy as set forth below.  In the case of items (i) and (iii) above,

 

58



 

except to the extent, in the case of item (iii), Williams Energy elects to have all or a portion of the Prepayment make up a combination of the alternative credit support required to be posted pursuant to Section 18.3(b) of the Power Purchase Agreement, Williams Energy shall have the right to recoup the Prepayment by set-off of any and all amounts owing to the Company under the Power Purchase Agreement beginning no earlier than the June in the calendar year after the occurrence of item (i) or (iii) and continuing thereafter until the Prepayment has been fully recovered.  In the case of item (ii) above, Williams Energy shall have the right to immediately set-off all amounts owing to the Company under the Power Purchase Agreement after the occurrence of item (ii) and continuing thereafter until the Prepayment has been fully recovered.  Except to the extent Williams Energy elects to include the Prepayment as part of the alternative credit support, the amount of alternative credit support posted by Williams Energy pursuant to the Letter Agreement shall be initially reduced by the amount of the Prepayment, and Williams Energy shall thereafter increase the alternative credit support proportionately as Williams Energy recoups the Prepayment set-off on the payment due date of amounts owing to the Company.

 

If the Company does not return the Prepayment to Williams Energy as set forth in the preceding paragraph, then the Company shall be considered in default under the Letter Agreement and Williams Energy shall be entitled to enforce any and or all of its contractual rights and remedies as set forth in the Power Purchase Agreement, including, but not limited to, drawing on the letter of credit previously posted by the Company in favor of Williams Energy.

 

Williams Energy made the Prepayment on November 14, 2002 and provided an additional $25 million of cash to the Company on January 6, 2003 as the alternative credit support.  As allowed by the Letter Agreement, Williams elected to have the $10 million Prepayment included as part of the alternative credit support. On September 24, 2004, Williams Energy posted a letter of credit and the Company returned the $25 million of alternative credit support. As allowed by the Letter Agreement, Williams Energy has elected to have the $10 million Prepayment included as part of the alternative credit support.  In the event that The Williams Companies, Inc. regain and maintains its investment grade status, provides a substitute guaranty of investment grade rating, or posts a letter of credit, the Company will be required to return the remaining $10 million alternative credit support to Williams Energy in accordance with the terms of the Letter Agreement as described above.  Williams Energy has notified the Company that it intends to post a letter of credit for the remaining $10 million in June 2005.

 

8.              COMMITMENTS AND CONTINGENCIES

 

Construction Agreement - The Company entered into an Agreement for Engineering, Procurement and Construction (EPC) services, dated as of October 15, 1999, between the Company and WGI (as the successor contractor), as amended for the design, engineering, procurement, site preparation and clearing, civil works, construction, start-up, training and testing and to provide all materials and equipment (excluding operational spare parts), machinery, tools, construction fuels, chemicals and utilities, labor, transportation, administration and other services and items (collectively and separately, the “services”) of the facility. Under a guaranty in the Company’s favor, effective as of October 15, 1999, all of WGI’s obligations under the construction agreement are irrevocably and unconditionally guaranteed by Raytheon. In 2001, as a result of WGI’s bankruptcy filing, the Company made a demand on Raytheon to perform its obligations under the Raytheon guaranty and WGI, Raytheon and the Company entered into agreements pursuant to which Raytheon became responsible for the construction of the facility.

 

Provisional acceptance has been granted and the facility has commenced commercial operations, however, Raytheon must perform certain agreed upon completion items in order to obtain final acceptance. Raytheon gave notice of Final Acceptance on July 22, 2003 based on its July 8, 2003 performance test.  On July 31, 2003, the Company received a letter from the project’s independent engineer stating that it could not support Raytheon’s claim of final acceptance and it did not consider the July 8, 2003 performance test valid.  In making this assessment, the independent engineer cited, among other reasons, (i) modifications made to certain equipment in performance of the July 8, 2003 performance test which would adversely impact the operations of the plant and other pieces of equipment and (ii) Raytheon’s failure to demonstrate compliance with guaranteed emissions limits.  On August 1, 2003, the Company rejected Raytheon’s claim of final acceptance.  This rejection was based upon Raytheon’s failure to meet the conditions for final acceptance provided for in the EPC contract. On August 7, 2003, the Company received a response from Raytheon in which Raytheon claims that the Company’s rejection of the final acceptance is invalid and improper.

 

59



 

On August 26, 2004, the Company drew down approximately $30.3 million under a letter of credit posted by Raytheon pursuant to the terms of the EPC Agreement. Prior to this date, the Company had drawn $544,000 on this letter of credit. The Company believes that Raytheon substantially breached the EPC Agreement, due, among other things, to the facility’s failure to achieve compliance with certain performance tests, and Raytheon’s failure to complete other services under the EPC Agreement and certain amendments thereto, including a Settlement Agreement dated August 6, 2002, that purported to resolve disputes over whether Raytheon had achieved Mechanical Completion and Provisional Acceptance. As a result, the Company claims that Raytheon’s breaches have caused damages in excess of the amount of the letter of credit. Raytheon disputes these claims and has failed and refused to pay costs and damages to the Company despite the Company’s demands for such payment.

 

On October 28, 2004, the Company received a complaint filed by Raytheon in the State of New York. In the complaint, Raytheon is seeking to recover $30,302,269, which represents the amount Red Oak drew down on the letter of credit on August 26, 2004, attorneys’ fees and costs, and also to recover up to $110 million of net expense Raytheon claims to have incurred in good faith under the governing guaranty and construction agreements.  The Company filed an answer and counterclaim on December 13, 2004, in which it denied liability to Raytheon, asserted various defenses and countersued Raytheon for breach of the EPC Agreement and Settlement Agreement, breach of express warranties under the EPC Agreement, and fraudulent misrepresentation and concealment.  The Company claimed damages of not less than $140 million and attorneys’ fees and costs to the extent allowable.  Raytheon moved to dismiss the Company’s fraudulent misrepresentation and concealment claim and to limit Company’s damages on January 14, 2005.  The Company filed its opposition to the motion to dismiss and also filed an amended counterclaim on February 18, 2005.  Thereafter, Raytheon agreed to withdraw its motion to dismiss.  On March 4, 2005, Raytheon filed a motion for summary judgment that seeks the return of $16,311,711 of the Letter of Credit draw.  The Company has not yet filed its opposition to the motion, and Raytheon has not yet filed an answer to the amended counterclaim. The Company has recorded the $30.3 million as a current liability, but has not accrued any additional amounts with respect to Raytheon’s claims.  The Company believes it has meritorious defenses to the claims asserted by Raytheon against it and intends to defend the lawsuit and pursue its counterclaims vigorously.

 

Maintenance Services – The Company has entered into the Maintenance Program Parts, Shop Repairs and Scheduled Outage TFA Services Contract (“Maintenance Services Agreement”), dated as of December 8, 1999, with Siemens Westinghouse by which Siemens Westinghouse will provide the Company with, among other things, combustion turbine parts, shop repairs and scheduled outage technical field assistance services. The Maintenance Services Agreement became effective on the date of execution and unless terminated early, will terminate upon completion of shop repairs performed by Siemens Westinghouse following the twelfth scheduled outage of the applicable combustion turbine or 16 years from the effective date of the contract, whichever occurs first, unless the Company exercises its right to terminate the agreement after the first major outage of the turbines.

 

The Maintenance Services Agreement indicates that the Company will pay fees each month based on a stated amount for each equivalent base load hour of the combustion turbines, adjusted for inflation, over the term of the agreement.  However, if a scheduled maintenance outage occurs prior to 8,000 equivalent base load hours being accumulated since the last scheduled maintenance outage for that turbine, the Company will be invoiced the remaining amount to equate to 8,000 hours (“true-up”). In the event the Company is not required to dispatch the facility, there is no charge for that month.

 

The total of these payments was approximately $6.8 million, $4.7 million and $1.2 million for the years ended December 31, 2004, 2003 and 2002, respectively, which included true-ups for two planned maintenance outages, as the turbines were far short of the 8,000 EBH level. Assuming a similar dispatch level in 2005 as in 2004, and the performance of one planned hot gas maintenance outage, a comparable level of payments would be expected for the year ended December 31, 2005. Based upon the Company’s current estimates, assuming a certain number of equivalent base hours and equivalent starts, the first major outages would be completed by 2011 and the remaining minimum payments to Siemens Westinghouse would approximate $32 million through that period.

 

As of December 31, 2004, the Company had received approximately $11.0 million in rotable spare parts under this agreement.  This amount is recorded as spare parts inventory, or as Property, Plant and Equipment when placed in service. The remaining amount owed to Siemens is recorded as current and long-term liabilities in the accompanying balance sheets.  For financial reporting purposes, payments made to Siemens Westinghouse are

 

60



 

treated as a reduction of the liability in the accompanying balance sheet, except for the portion that is considered maintenance expense when a scheduled outage occurs.

 

Water Supply and Water Supply Pipeline – The Company has entered into a contract with the Borough of Sayreville (the “Borough”) by which the Borough will provide untreated water to the Company. The contract has a term of 30 years with an option to extend for up to four additional five-year terms. The Company is contractually committed to a minimum annual payment of $300,000.

 

Interconnection Agreement – The Company entered into an interconnection agreement with Jersey Central Power & Light Company (“JCP&L”) d/b/a GPU Energy (“GPU”), and is dated April 27, 1999. GPU has since been merged with, and into, FirstEnergy, and JCP&L is now a subsidiary of FirstEnergy.  This agreement is to transmit the electricity generated by the facility to the transmission grid so that it may be sold as prescribed under the Power Purchase Agreement. The agreement is in effect for the life of the facility, yet may be terminated by mutual consent of both GPU and the Company under certain circumstances as detailed in the agreement. Costs associated with the agreement are based on electricity transmitted via GPU at a variable price and the PJM (Pennsylvania/New Jersey/Maryland) Tariff as charged by GPU, which is comprised of both service cost and asset recovery cost, as determined by GPU and approved by the Federal Energy Regulatory Committee. The Company has been importing electricity from the transmission system to support commissioning of the facility since July 2001 and the interconnection facilities have exported power to the transmission system since that time.

 

Interconnection Services Agreement (PJM) – The Company entered into an interconnection agreement with the Independent System Operator (“ISO”) of the PJM Control Area on December 24, 2001, as required under the PJM Open Access Transmission Tariff. This agreement includes specifications for each generating unit that will be interconnected to the Transmission System, confirms Capacity Interconnection Rights and includes the Company’s agreement to abide by all rules and procedures pertaining to generation in the PJM Control Area.

 

Land Development Plan – The Company entered into an agreement with the Borough of Sayreville by which the Company will develop and implement a plan to replace trees which were removed during clearing of the facility site.  The Land Development Plan is required for final site approval. The estimated cost of the plan is approximately $425,000.  The Company is in the process of selecting a contractor to perform the service and no payments have been made as of December 31, 2004.  On July 23, 2003, the project was secured by a letter of credit issued by Union Bank of California for $425,000 with the Borough of Sayreville as the beneficiary.  This irrevocable standby letter of credit had an expiration date of June 30, 2004, but was automatically extended for another one-year period. On August 19, 2004, AES secured a performance bond for $539,493 relating to the tree replacement and other site improvements. This bond replaces the previous letter of credit and represents the amount potentially due if there is a failure of AES Red Oak, LLC to take action regarding the plan.

 

9.              RELATED PARTY TRANSACTIONS

 

Effective March 2000, the Company entered into a 32-year development and construction management agreement with AES Sayreville, L.L.C. (“Sayreville”), another wholly owned subsidiary of Red Oak, to provide certain support services required by the Company for the development and construction of the facility. Under this agreement Sayreville has also provided operations management services for the Company since the commencement of commercial operation. Minimum amounts payable under the contract during 2004 were approximately $137,000 per month. Corporate management fees were $1.6 million for each of the years ended December 31, 2004 and 2003 and was $0.6 million for the partial year of operations ended December 31, 2002. Corporate management fees are charged on a monthly basis based on a fixed amount which is adjusted annually for inflation.

 

AES Sayreville is compensated for its maintenance and operation services on a cost basis, and it also receives certain management fees which it passes on to The AES Corporation.  For the years ended December 31, 2004, 2003 and 2002, the Company paid AES Sayreville a total of $5.3 million, $5.3 million and $4.4 million, respectively, for their services. AES will continue to supply Sayreville with the personnel, operational and maintenance services necessary to carry out its obligations to the Company.

 

61



 

The Company had accounts receivable from affiliates of $30,000 and $51,000 as of December 31, 2004 and 2003, respectively.  The Company had accounts payable to its parent and affiliates of $282,000 and $131,000 as of December 31, 2004 and 2003, respectively.  Accounts receivable from affiliates generally represents charges for certain projects that the Company has paid for and invoiced to its affiliates.  Accounts payable to parent and affiliates represent general amounts owed to the Company’s parent and affiliates for shared services.

 

10.       FAIR VALUE OF FINANCIAL INSTRUMENTS

 

The estimated fair values of the Company’s financial instruments have been determined using available market information. The estimates are not necessarily indicative of the amounts the Company could realize in a current market exchange. The use of different market assumptions and/or estimation methodologies may have a material effect on the estimated fair value amounts.

 

The fair value of the Company’s restricted investments approximates their carrying value. The Bonds had a carrying amount of $370.1 million and $375.4 million at December 31, 2004 and 2003, respectively.  The Bonds had a fair value of approximately $415.4 million and $399.0 million, respectively, at December 31, 2004 and 2003.

 

11.       SEGMENT INFORMATION

 

Under the provisions of Statement of Financial Accounting Standards No. 131, “Disclosure About Segments of an Enterprise and Related Information”, the Company’s business is expected to be operated as one reportable segment, with operating income or loss being the measure of performance evaluated by the chief operating decision maker. As described in Notes 1 and 6, the Company’s primary customer is Williams, which is expected to provide all of the revenues of the Company during the term of the Power Purchase Agreement.

 

62



 

SELECTED QUARTERLY FINANCIAL DATA (UNAUDITED)

 

The following table summarizes the unaudited quarterly statements of operations for the Company for the years ended December 31, 2004 and 2003, respectively.

 

 

 

AES Red Oak, LLC

 

 

 

Quarter Ended
December 31, 2004

 

Quarter Ended
September 30, 2004

 

Quarter Ended
June 30, 2004

 

Quarter Ended
March 31, 2004

 

 

 

(dollars in thousands)

 

OPERATING REVENUES

 

 

 

 

 

 

 

 

 

Energy

 

$

12,235

 

$

27,904

 

$

17,915

 

$

11,628

 

OPERATING EXPENSES

 

 

 

 

 

 

 

 

 

Operating expenses

 

(7,484

)

(9,022

)

(9,215

)

(7,627

)

General and administrative costs

 

(448

)

(213

)

(311

)

(177

)

Total Operating Expense

 

(7,932

)

(9,235

)

(9,526

)

(7,804

)

OPERATING INCOME

 

4,303

 

18,669

 

8,389

 

3,824

 

 

 

 

 

 

 

 

 

 

 

OTHER INCOME/EXPENSE

 

 

 

 

 

 

 

 

 

Interest income

 

199

 

158

 

58

 

61

 

Interest expense

 

(8,386

)

(8,463

)

(8,471

)

(8,478

)

Other expense

 

(278

)

(240

)

(257

)

(261

)

Total Other Income/Expenses

 

(8,465

)

(8,545

)

(8,670

)

(8,678

)

NET INCOME (LOSS)

 

$

(4,162

)

$

10,124

 

$

(281

)

$

(4,854

)

 

 

 

AES Red Oak, LLC

 

 

 

Quarter Ended
December 31, 2003

 

Quarter Ended
September 30, 2003

 

Quarter Ended
June 30, 2003

 

Quarter Ended
March 31, 2003

 

 

 

(dollars in thousands)

 

OPERATING REVENUES

 

 

 

 

 

 

 

 

 

Energy

 

$

11,639

 

$

25,799

 

$

15,747

 

$

11,021

 

OPERATING EXPENSES

 

 

 

 

 

 

 

 

 

Operating expenses

 

(5,976

)

(7,549

)

(6,689

)

(6,692

)

General and administrative costs

 

(1,047

)

(1,025

)

(977

)

(953

)

Total Operating Expense

 

(7,023

)

(8,574

)

(7,666

)

(7,645

)

OPERATING INCOME

 

4,616

 

17,225

 

8,081

 

3,376

 

 

 

 

 

 

 

 

 

 

 

OTHER INCOME/EXPENSE

 

 

 

 

 

 

 

 

 

Interest income

 

294

 

57

 

67

 

77

 

Interest expense

 

(8,551

)

(8,575

)

(8,492

)

(8,614

)

Liquated damages received

 

12

 

202

 

610

 

603

 

Other expense

 

(252

)

(255

)

(255

)

(251

)

Liquated damages paid

 

(249

)

 

 

 

Total Other Income/Expenses

 

(8,746

)

(8,571

)

(8,070

)

(8,185

)

NET INCOME (LOSS)

 

$

(4,130

)

$

8,654

 

$

11

 

$

(4,809

)

 

63



 

ITEM 9.     CHANGES IN AND DISAGREEMENTS WITH ACCOUNTANTS ON ACCOUNTING AND FINANCIAL DISCLOSURE

 

None.

 

ITEM 9A.                    CONTROLS AND PROCEDURES

 

Evaluation of Disclosure Controls and Procedures.  We carried out an evaluation, under the supervision and with the participation of our management, including the chief executive officer (“CEO”) and chief financial officer (“CFO”), of the effectiveness of our “disclosure controls and procedures” (as defined in the Securities Exchange Act of 1934 Rules 13a-15(e) and 15-d-15 (e) as required by paragraph (b) of the Exchange Act Rules 13a-15 or 15d-15) as of December 31, 2004.  The Company’s management, including the CEO and CFO, is engaged in a comprehensive effort to review, evaluate and improve our controls; however, management does not expect that our disclosure controls or our internal controls over financial reporting will prevent all errors and all fraud.  A control system, no matter how well designed and operated, can provide only reasonable, not absolute, assurance that the control system’s objectives will be met.

 

Based upon the controls evaluation performed, the CEO and CFO have concluded that as of December 31, 2004, our disclosure controls and procedures were effective to provide reasonable assurance that material information relating to us and our consolidated subsidiaries is recorded, processed, summarized and reported within the time periods specified in the Securities and Exchange Commission’s rules and forms.

 

Changes in Internal Controls.  In the course of our evaluation of disclosure controls and procedures, management considered certain internal control areas in which the Company has made and are continuing to make changes to improve and enhance controls.  Based upon that evaluation, the CEO and CFO concluded that there were no changes in our internal controls over financial reporting identified in connection with the evaluation required by paragraph (d) of Exchange Act Rules 13a-15 or 15d-15 that occurred during the fourth quarter ended December 31, 2004, that have materially affected, or are reasonably likely to materially affect, our internal controls over financial reporting.

 

Compliance with Section 404 of the Sarbanes Oxley Act of 2002.  Beginning with the year ending December 31, 2006, Section 404 of the Sarbanes-Oxley Act of 2002 will require us to include an internal control report of management with our annual report on Form 10-K.  The internal control report must contain (1) a statement of management’s responsibility for establishing and maintaining adequate internal controls over financial reporting for our Company, (2) a statement identifying the framework used by management to conduct the required evaluation of the effectiveness of our internal controls over financial reporting, (3) management’s assessment of the effectiveness of our internal controls over financial reporting as of the end of our most recent fiscal year, including a statement as to whether or not our internal controls over financial reporting are effective, and (4) a statement that our independent auditors have issued an attestation report on management’s assessment of our internal controls over financial reporting.

 

Management developed a comprehensive plan in order to achieve compliance with Section 404 within the prescribed period and to review, evaluate and improve the design and effectiveness of our controls and procedures on an on-going basis.  The comprehensive compliance plan includes (1) documentation and assessment of the adequacy of our internal controls over financial reporting, (2) remediation of control weaknesses, (3) validation through testing that controls are functioning as documented and (4) implementation of a continuous reporting and improvement process for internal controls over financial reporting.  As a result of this initiative, the Company has made and will continue to make changes from time to time in our internal controls over financial reporting.

 

64



 

PART III

 

ITEM 10.                      DIRECTORS AND EXECUTIVE OFFICERS OF THE REGISTRANT

 

Not applicable pursuant to General Instruction I of Form 10-K.

 

ITEM 11.                      EXECUTIVE COMPENSATION

 

Not applicable pursuant to General Instruction I of the Form 10-K.

 

ITEM 12.                      SECURITY OWNERSHIP OF CERTAIN BENEFICIAL OWNERS AND MANAGEMENT

 

Not applicable pursuant to General Instruction I of the Form 10-K.

 

ITEM 13.                      CERTAIN RELATIONSHIPS AND RELATED TRANSACTIONS

 

Not applicable pursuant to General Instruction I of the Form 10-K.

 

ITEM 14.                      PRINCIPAL ACCOUNTING FEES AND SERVICES

 

   Audit Fees

 

The aggregate fees billed for each of the last two fiscal years for professional services rendered by the principal accountant for the audit of the registrant’s annual financial statements, included in registrant’s form 10-K, and review of the financial statements included in the registrant’s Form 10Q (17CFR249.308a) or services that are normally provided by the accountant in connection with statutory and regulatory filings or engagements for those fiscal years were approximately $241,000 and $219,000 for the years ended December 31, 2004 and 2003, respectively.

 

The registrant’s board of directors serves as its audit committee. All audit and non-audit services to be provided to the registrant by its principal accountant are approved by the board of directors. A pre-approval policy is in place with The AES Corporation Audit Committee.

 

All Other Fees

 

There were no other fees paid to the principal accountant for the years ended December 31, 2004 and 2003, respectively.

 

65



 

PART IV

 

ITEM 15.                      EXHIBITS AND FINANCIAL STATEMENT SCHEDULES.

 

a)              The following documents are filed as part of this report:

 

1.                                       Consolidated Financial Statements Filed:
Please refer to Item 8 - Consolidated Financial Statement and Supplementary Data.

 

2.                                       Consolidated Financial Statement Schedules Filed:
None.

 

3.                                       Exhibits Filed:

 

Unless otherwise indicated, all exhibits to this Form 10-K are incorporated herein by reference from the identically numbered exhibit of AES Red Oak, L.L.C.’s Registration Statement of Form S-4 (333-40478).

 

Exhibit Number

 

Description

3

 

Amended and Restated Limited Liability Company Agreement, dated as of November 23, 1999, of AES Red Oak, L.L.C.

 

 

 

4.1(a)

 

Trust Indenture, dated as of March 1, 2000, by and among AES Red Oak, L.L.C., the Trustee and the Depositary Bank.

 

 

 

4.1(b)

 

First Supplemental Indenture, dated as of March 1, 2000, by and among AES Red Oak, L.L.C., the Trustee and the Depositary Bank.

 

 

 

4.2

 

Collateral Agency and Intercreditor Agreement, dated as of March 1, 2000, by and among AES Red Oak, L.L.C., the Trustee, the Collateral Agent, the Debt Service Reserve Letter of Credit Provider, the Power Purchase Agreement Letter of Credit Provider, the Working Capital Provider and the Depositary Bank.

 

 

 

4.3

 

Debt Service Reserve Letter of Credit and Reimbursement Agreement, dated as of March 1, 2000, by and among AES Red Oak, L.L.C., the Debt Service Reserve Letter of Credit Provider and the Banks named therein.

 

 

 

4.4

 

Power Purchase Agreement Letter of Credit and Reimbursement Agreement, dated as of March 1, 2000, by and among AES Red Oak, L.L.C., the Power Purchase Agreement Letter of Credit Provider and the Banks named therein.

 

 

 

4.5

 

Global Bond, dated March 15, 2000, evidencing 8.54% Senior Secured Bonds of AES Red Oak, L.L.C., Series A due 2019 in the principal amount of $224,000,000.

 

 

 

4.6

 

Global Bond, dated March 15, 2000, evidencing 9.20% Senior Secured Bonds of AES Red Oak, L.L.C., Series B due 2029 in the principal amount of $160,000,000.

 

66



 

Exhibit Number

 

Description

4.7

 

Equity Subscription Agreement, dated as of March 1, 2000, by and among AES Red Oak, L.L.C., AES Red Oak, Inc. and the Collateral Agent.

 

 

 

4.8

 

Working Capital Agreement, dated as of March 1, 2000, by and among AES Red Oak, L.L.C., Working Capital Provider, and the Banks named therein.

 

 

 

4.9

 

Security Agreement, dated as of March 1, 2000, by and between AES Red Oak, L.L.C. and the Collateral Agent.

 

 

 

4.10

 

Pledge and Security Agreement, dated as of March 1, 2000, by and between AES Red Oak, Inc. and the Collateral Agent.

 

 

 

4.11

 

Pledge and Security Agreement, dated as of March 1, 2000, by and between AES Red Oak, L.L.C. and the Collateral Agent.

 

 

 

4.12

 

Consent to Assignment, dated as of March 1, 2000, by and between Williams Energy Marketing & Trading Company and the Collateral Agent, and consented to by AES Red Oak, L.L.C. (with respect to the Power Purchase Agreement).

 

 

 

4.13

 

Consent to Assignment, dated as of March 1, 2000, by and between The Williams Companies, Inc. and the Collateral Agent, and consented to by AES Red Oak, L.L.C. (with respect to the PPA Guaranty)

 

 

 

4.14

 

Consent to Assignment, dated as of March 1, 2000, by and between Raytheon Engineers & Constructors, Inc. and the Collateral Agent, and consented to by AES Red Oak, L.L.C. (with respect to the construction agreement).

 

 

 

4.15

 

Consent to Assignment, dated as of March 1, 2000, by and between Raytheon Company and the Collateral Agent, and consented to by AES Red Oak, L.L.C. (with respect to the EPC Guaranty).

 

 

 

4.16

 

Consent to Assignment, dated as of March 1, 2000, by and between Siemens Westinghouse Power Corporation and the Collateral Agent, and consented to by AES Red Oak, L.L.C. (with respect to the Maintenance Services Agreement).

 

 

 

4.17

 

Consent to Assignment, dated as of March 1, 2000, by and between AES Sayreville, L.L.C. and the Collateral Agent, and consented to by AES Red Oak, L.L.C. (with respect to the Development and Operations Services Agreement).

 

 

 

4.18

 

Consent to Assignment, dated as of March 1, 2000, by and between Jersey Central Power and Light Company d/b/a GPU Energy and the Collateral Agent, and consented to by AES Red Oak, L.L.C. (with respect to the Interconnection Agreement).

 

67



 

Exhibit Number

 

Description

4.19

 

Consent to Assignment, dated as of March 1, 2000, by and between the Borough of Sayreville and the Collateral Agent, and consented to by AES Red Oak, L.L.C. (with respect to the Water Supply Agreement).

 

 

 

10.1

 

Fuel Conversion Services, Capacity and Ancillary Services Purchase Agreement, dated as of September 17, 1999, and Amendment No. 1, dated as of February 21, 2000, by and between AES Red Oak, L.L.C. and Williams Energy Marketing & Trading Company. (Portions of this exhibit have been omitted pursuant to a request for confidential treatment.)

 

 

 

10.2(a)

 

Agreement for Engineering, Procurement and Construction Services, dated as of October 15, 1999, and Amendment No. 1, dated as of February 23, 2000, by and between AES Red Oak, L.L.C. and Raytheon Engineers & Constructors, Inc. (Portions of this exhibit have been omitted pursuant to a request for confidential treatment.)

 

 

 

10.2(b)

 

EPC Contract Prepayment Coordination Agreement, dated as of March 14, 2000, between AES Red Oak, L.L.C. and Raytheon Engineers and Constructors, Inc. (Portions of this exhibit have been omitted pursuant to a request for confidential treatment.)

 

 

 

10.3

 

Guaranty, dated as of October 15, 1999, by Raytheon Company in favor of AES Red Oak, L.L.C. (Portions of this exhibit have been omitted pursuant to a request for confidential treatment.)

 

 

 

10.4

 

Maintenance Program Parts, Shop Repairs and Scheduled Outage TFA Services Contract, dated as of December 8, 1999, and Amendment No. 1, dated February 15, 2000, by and between AES Red Oak, L.L.C. and Siemens Westinghouse Power Corporation. (Portions of this exhibit have been omitted pursuant to a request for confidential treatment.)

 

 

 

10.5

 

Development and Operations Services Agreement, dated as of March 1, 2000, by and between AES Sayreville, L.L.C. and AES Red Oak, L.L.C.

 

 

 

10.7

 

Water Supply Agreement, dated as of December 22, 1999, by and between AES Red Oak, L.L.C. and the Borough of Sayreville.

 

 

 

10.8

 

General Facility Transmission Interconnection Agreement, dated as of April 27, 1999, by and between Jersey Central Power & Light Company d/b/a GPU Energy and AES Red Oak, L.L.C.

 

 

 

10.9

 

Mortgage, Security Agreement and Assignment of Leases and Income, dated as of March 1, 2000, by and between AES Red Oak, L.L.C. and the Mortgagee.

 

 

 

10.10

 

Assignment of Leases and Income, dated as of March 1, 2000, by

 

68



 

Exhibit Number

 

Description

 

 

and between AES Red Oak, L.L.C. and the Collateral Agent.

 

 

 

10.11

 

Financial Agreement, dated as of December 3, 1999, by and between AES Red Oak Urban Renewal Corporation and the Borough of Sayreville.

 

 

 

10.12

 

Promissory Note, dated as of March 15, 2000, of AES Red Oak Urban Renewal Corporation to AES Red Oak, L.L.C.

 

 

 

10.13

 

Ground Lease Agreement, dated as of March 1, 2000, by and between AES Red Oak, L.L.C. and AES Red Oak Urban Renewal Corporation.

 

 

 

10.14

 

Sublease Agreement, dated as of March 1, 2000, by and between AES Red Oak Urban Renewal Corporation and AES Red Oak, L.L.C.

 

 

 

10.15

 

Memorandum of Ground Lease, dated as of March 1, 2000, by and between AES Red Oak, L.L.C. and AES Red Oak Urban Renewal Corporation.

 

 

 

10.16

 

Memorandum of Sublease, dated as of March 1, 2000, by and between AES Red Oak Urban Renewal Corporation and AES Red Oak, L.L.C.

 

 

 

10.17

 

Construction Agency Agreement, dated as of March 1, 2000, by and between AES Red Oak Urban Renewal Corporation and AES Red Oak, L.L.C.

 

 

 

10.18

 

Leasehold Mortgage, Security Agreement and Assignment of Leases and Income, dated as of March 1, 2000, by and between AES Red Oak Urban Renewal Corporation and AES Red Oak, L.L.C.

 

 

 

10.19

 

Assignment of Mortgage, dated as of March 1, 2000, by AES Red Oak, L.L.C. in favor of the Collateral Agent.

 

 

 

10.20

 

URC Security Agreement, dated as of March 1, 2000, by and between AES Red Oak Urban Renewal Corporation and AES Red Oak, L.L.C.

 

 

 

10.21

 

Assignment of Leases and Income, dated as of March 1, 2000, by and between AES Red Oak Urban Renewal Corporation and AES Red Oak, L.L.C.

 

 

 

10.22

 

Assignment of Assignment of Leases and Income, dated as of March 1, 2000, by AES Red Oak, L.L.C. in favor of the Collateral Agent.

 

 

 

10.23

 

Guaranty, dated as of March 1, 2000, by The Williams Companies, Inc. in favor of AES Red Oak, L.L.C. (Power Purchase Agreement Guaranty). (Portions of this exhibit have

 

69



 

Exhibit Number

 

Description

 

 

been omitted pursuant to a request for confidential treatment.)

 

 

 

10.24

 

Project Completion Agreement dates as of November 16, 2001, by and between Raytheon Company and Washington Group International, Inc. (incorporated herein by reference from Exhibit 10.1 to the Form 8-K filed on December 12, 2001, File No. 333-40478).

 

 

 

10.25

 

Owner/Guarantor Supplemental Agreement, dated as of November 21, 2001, by and among AES Red Oak, L.L.C. and Raytheon Company (incorporated herein by reference from Exhibit 10.2 to the Form 8-K filed on December 12, 2001, File No. 333-40478).

 

 

 

10.26**

 

Letter Agreement, dated November 7, 2002, between AES Red Oak, L.L.C. and Williams Energy Marketing & Trading Company.

 

 

 

10.27

 

Letter Agreement, dated March 5, 2003 between AES Red Oak, L.L.C. and Raytheon Company.

 

 

 

12*

 

Computation of Ratios of Earnings (Deficiency) to Fixed Charges.

 

 

 

21*

 

Subsidiary of the Registrant.

 

 

 

31.1*

 

Certification by Chief Executive Officer Required by Rule 13a-14(a) or 15d-14(a) of the Securities Exchange Act of 1934

 

 

 

31.2*

 

Certification by Chief Financial Officer Required by Rule 13a-14(a) or 15d— 14(a) of the Securities Exchange Act of 1934

 

 

 

32*

 

Section 1350 Certifications

 


* Filed herewith.

 

** Previously filed as an exhibit to the Company’s Quarterly Report on Form 10-Q for the period ended September 30, 2002 and incorporated by reference herein.

 

70



 

Supplementary Information to be Furnished With Reports filed Pursuant to
Section 15(d) of the Act by Registrants Which Have Not Registered
Securities Pursuant to Section 12 of the Act.

 

No annual report or proxy materials have been sent to security holders during the fiscal year ended December 31, 2004. No annual report or proxy materials will be sent to security holders subsequent to the filing of this annual report on Form 10-K.

 

71



 

SIGNATURES

 

Pursuant to the requirements of Section 13 or 15(d) of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

 

 

AES RED OAK, L.L.C.

 

 

 

 

 

 

 /s/ A.W. Bergeron

 

By:

 A.W. Bergeron

 

Title:

 President

 

 

 

 

 /s/ Thomas P. Keating

 

By:

 Thomas P. Keating

 

Title:

 Chief Financial Officer

 

Date: March 30, 2005

 

Pursuant to the requirements of the Securities Exchange Act of 1934, this report has been signed by the following persons on behalf of the registrant and in the capacities and on the dates indicated.

 

Signature

 

Title

 

Date

 

 

 

 

 

  /s/ A. W Bergeron

 

 

 

 

 

  A. W Bergeron

 

Director

 

March 24, 2005

 

 

 

 

 

  /s/ Edward P. Convery

 

 

 

 

 

  Edward P. Convery

 

Director

 

March 30, 2005

 

 

 

 

 

  /s/ Dan Rothaupt

 

 

 

 

 

  Dan Rothaupt

 

Director

 

March 30, 2005

 

72